Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 7 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
friable or is releasing
asbestos fibers into the air above current action levels
established by the United States Occupational Safety
and Health Administration.
5. Bid--The offer or proposal of a bidder
submitted on the prescribed form setting forth the
prices for the Work to be performed.
6. Bidding Documents--The Bidding
Requirements and the proposed Contract Documents
(including all Addenda issued prior to receipt of
Bids).
7. Bidding Requirements--The Advertisement
or Invitation to Bid, Instructions to Bidders, Bid
security form, if any, and the Bid form with any
supplements.
8. Bonds--Performance and payment bonds and
other instruments of security.
9. Change Order--A document recommended
by ENGINEER which is signed by CONTRACTOR
and OWNER and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract
Price or the Contract Times, issued on or after the
Effective Date of the Agreement.
10. Claim--A demand or assertion by OWNER
or CONTRACTOR seeking an adjustment of
Contract Price or Contract Times, or both, or other
relief with respect to the terms of the Contract. A
demand for money or services by a third party is nota
Claim.
11. Contract--The entire and integrated written
agreement between the OWNER and CONTRAC-
TOR concerning the Work. The Contract supersedes
prior negotiations, representations, or agreements,
whether written or oral.
12. Contract Documents--The Contract Docu-
ments establish the rights and obligations of the
parties and include the Agreement, Addenda (which
pertain to the Contract Documents),
CONTRACTOR’s Bid (including documentation
accompanying the Bid and any post Bid documenta-
tion submitted prior to the Notice of Award) when
attached as an exhibit to the Agreement, the Notice to
Proceed, the Bonds, these General Conditions, the
Supplementary Conditions, the Specifications and the
Drawings as the same are more specifically identified
in the Agreement, together with all Written Amend-
ments, Change Orders, Work Change Directives,
Field Orders, and ENGINEER’s written interpreta-
tions and clarifications issued on or after the
Effective Date of the Agreement. Approved Shop
Drawings and the reports and drawings of subsurface
and physical conditions are not Contract Documents.
Only printed or hard copies of the items listed in this
paragraph are Contract Documents. Files in
electronic media format of text, data, graphics, and
the like that may be furnished by OWNER to
CONTRACTOR are not Contract Documents.
13. Contract Price--The moneys payable by
OWNER to CONTRACTOR for completion of the
Work in accordance with the Contract Documents as
stated in the Agreement (subject to the provisions of
paragraph 11.03 in the case of Unit Price Work).
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-7
DATE: 5/13/2012
SECTION 00700
GENERAL CONDITIONS
14. Contract Times--The number of days or the
dates stated in the Agreement to: (i) achieve Substan-
tial Completion; and (ii) complete the Work so that it
is ready for final payment as evidenced by
ENGINEER’s written recommendation of final
payment.
15. CONTRACTOR--The individual or entity
with whom OWNER has entered into the Agreement.
16. Cost of the Work--See paragraph 11.01.A
for definition.
17. Drawings--That part of the Contract
Documents prepared or approved by ENGINEER
which graphically shows the scope, extent, and
character of the Work to be performed by
CONTRACTOR. Shop Drawings and other
CONTRACTOR submittals are not Drawings as so
defined.
18. Effective Date of the Agreement--The date
indicated in the Agreement on which it becomes
effective, but ifno such date is indicated, it means the
date on which the Agreement is signed and delivered
by the last of the two parties to sign and deliver.
19. ENGINEER--The individual or entity named
as such in the Agreement.
20. ENGINEER's Consultant--An individual or
entity having a contract with ENGINEER to furnish
services as ENGINEER’s independent professional
associate or consultant with respect to the Project and
who is identified as such in the Supplementary
Conditions.
21. Field Order--A written order issued by
ENGINEER which requires minor changes in the
Work but which does not involve a change in the
Contract Price or the Contract Times.
22. General Requirements--Sections of Division
1 of the Specifications. The General Requirements
pertain to all sections of the Specifications.
23. Hazardous Environmental Condition--The
presence at the Site of Asbestos, PCBs, Petroleum,
Hazardous Waste, or Radioactive Material in such
quantities or circumstances that may present a
substantial danger to persons or property exposed
thereto in connection with the Work.
24. Hazardous Waste--The term Hazardous
Waste shall have the meaning provided in Section
Russell Stephenson — Electrical Manhole Rehabilitation
1004 of the Solid Waste Disposal Act (42 USC
Section 6903) as amended from time to time.
25. Laws and Regulations; Laws or Regulat-
ions--Any and all applicable laws, rules, regulations,
ordinances, codes, and orders of any and all govern-
mental bodies, agencies, authorities, and courts
having jurisdiction.
26. Liens--Charges, security interests, or
encumbrances upon Project funds, real property, or
personal property.
27. Milestone--A principal event specified in the
Contract Documents relating to an intermediate com-
pletion date or time prior to Substantial Completion
of all the Work.
28. Notice of Award--The written notice by
OWNER to the apparent successful bidder stating
that upon timely compliance by the apparent
successful bidder with the conditions precedent listed
therein, OWNER will sign and deliver the
Agreement.
29. Notice to Proceed--A written notice given
by OWNER to CONTRACTOR fixing the date on
which the Contract Times will commence to run and
on which CONTRACTOR shall start to perform the
Work under the Contract Documents.
30. OWNER--The individual, entity, public
body, or authority with whom CONTRACTOR has
entered into the Agreement and for whom the Work is
to be performed.
31. Partial Utilization--Use by OWNER of a
substantially completed part of the Work for the pur-
pose for which it is intended (or a related purpose)
prior to Substantial Completion of all the Work.
32. PCBs--Polychlorinated biphenyls.
33. Petroleum--Petroleum, including crude oil
or any fraction thereof which is liquid at standard
conditions of temperature and pressure (60 degrees
Fahrenheit and 14.7 pounds per square inch
absolute), such as oil, petroleum, fuel oil, oil sludge,
oil refuse, gasoline, kerosene, and oil mixed with
other non-Hazardous Waste and crude oils.
34. Project--The total construction of which the
Work to be performed under the Contract Documents
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER DATE: 5/13/2012
00700-8
SECTION 00700
GENERAL CONDITIONS
Russell Stephenson — Electrical Manhole Rehabilitation
may be the whole, or a part as may be indicated
elsewhere in the Contract Documents.
35. Project Manual--The bound documentary
information prepared for bidding and constructing the
Work. A listing of the contents of the Project Manual,
which may be bound in one or more volumes, is
contained in the table(s) of contents.
36. Radioactive Material--Source, special
nuclear, or byproduct material as defined by the
Atomic Energy Act of 1954 (42 USC Section 2011 et
seq.) as amended from time to time.
37. Resident Project Representative--The autho-
rized representative of ENGINEER who may be
assigned to the Site or any part thereof.
38. Samples--Physical examples of materials,
equipment, or workmanship that are representative of
some portion of the Work and which establish the
standards by which such portion of the Work will be
judged.
39. Shop Drawings--All drawings, diagrams,
illustrations, schedules, and other data or information
which are specifically prepared or assembled by or
for CONTRACTOR and _— submitted by
CONTRACTOR to illustrate some portion of the
Work.
40. Site--Lands or areas indicated in the Contract
Documents as being furnished by OWNER upon
which the Work is to be performed, including rights-
of-way and easements for access thereto, and such
other lands furnished by OWNER which are desig-
nated for the use of CONTRACTOR.
41. Specifications--That part of the Contract
Documents consisting of written technical
descriptions of materials, equipment, systems, stan-
dards, and workmanship as applied to the Work and
certain administrative details applicable thereto.
42. Subcontractor--An_ individual or entity
having a direct contract with CONTRACTOR or with
any other Subcontractor for the performance ofa part
of the Work at the Site.
43. Substantial Completion--The time at which
the Work (or a specified part thereof) has progressed
to the point where, in the opinion of ENGINEER, the
Work (or a specified part thereof) is sufficiently
complete, in accordance with the Contract
Documents, so that the Work (or a specified part
thereof) can be utilized for the purposes for which it
is intended. The terms “substantially complete” and
“substantially completed” as applied to all or part of
the Work refer to Substantial Completion thereof.
44, Supplementary Conditions--That part ofthe
Contract Documents which amends or supplements
these General Conditions.
45. Supplier--A manufacturer, _ fabricator,
supplier, distributor, materialman, or vendor having a
direct contract with CONTRACTOR or with any
Subcontractor to furnish materials or equipment to be
incorporated in the Work by CONTRACTOR or any
Subcontractor.
46. Underground Facilities--All underground
pipelines, conduits, ducts, cables, wires, manholes,
vaults, tanks, tunnels, or other such facilities or
attachments, and any encasements containing such
facilities, including those that convey electricity,
gases, steam, liquid petroleum products, telephone or
other communications, cable television, water,
wastewater, storm water, other liquids or chemicals,
or traffic or other control systems.
47. Unit Price Work--Work to be paid for on the
basis of unit prices.
48. Work--The entire completed construction or
the various separately identifiable parts thereof
required to be provided under the Contract
Documents. Work includes and is the result of
performing or providing all labor, services, and
documentation necessary to produce such
construction, and furnishing, installing, and
incorporating all materials and equipment into such
construction, all as required by the Contract
Documents.
49. Work Change Directive--A written
statement to CONTRACTOR issued on or after the
Effective Date of the Agreement and signed by
OWNER and recommended by ENGINEER ordering
an addition, deletion, or revision in the Work, or
responding to differing or unforeseen subsurface or
physical conditions under which the Work is to be
performed or to emergencies. A Work Change
Directive will not change the Contract Price or the
Contract Times but is evidence that the parties expect
that the change ordered or documented by a Work
Change Directive will be incorporated in a subse-
quently issued Change Order following negotiations
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-9
DATE: 5/13/2012
SECTION 00700
GENERAL CONDITIONS
by the parties as to its effect, if any, on the Contract
Price or Contract Times.
50. Written Amendment--A written statement
modifying the Contract Documents, signed by
OWNER and CONTRACTOR on or after the
Effective Date of the Agreement and normally dealing
with the nonengineering or nontechnical rather than
strictly construction-related aspects of the Contract
Documents.
1.02 Terminology
A. Intent of Certain Terms or Adjectives
1. Whenever in the Contract Documents the
terms “as ordered,” “as directed,” “as required,” “as
allowed,” “as approved,” or terms of like effect or
import are used to authorize an exercise of
professional judgement by the ENGINEER, or the
adjectives “reasonable,” “suitable,” “acceptable,”