which the site-specific Safety Plan applies.
2. Contain a complete list of contractor and jobsite contact personnel, including
emergency contacts and office, home and cell phone numbers.
3. Include the name, qualifications, background and duties of the contractors’ Safety
Representative.
4. Define the safety responsibilities of the project superintendent, foremen and
employees.
5. Comply with safety requirements contained herein and elsewhere in the Project
Manual.
6. Comply with all applicable OSHA Regulations, which at a minimum include the
following:
a. OSHA Subpart T
1926.850 Preparatory operations
1926.852 Chutes
1926.853 Removal of material through floor openings
1926.854 Removal of walls, masonry sections and chimneys
1926.855 Manual removal of floors
1926.856 Walls, floors and material with equipment
1926.857 Storage
1926.858 Removal of steel construction
1926.859 Mechanical demolition
b. OSHA Subparts C,E,F,G,H,I,J,K,L,M,N,O,P,X (as applicable)
1926 Subpart C Housekeeping
1926 Subpart E Personal protective equipment
1926 Subpart F Fire Protection and Prevention
1926 Subpart G Barricades
1926 Subpart H Material Handling
1926 Subpart I Hand/Power Tools
1926 Subpart J Welding and cutting
1926 Subpart K Electrical Safety
1926 Subpart L Scaffolds
1926 Subpart M Fall Protection
1926 Subpart O Vehicle Safety
1926 Subpart P Trenching and excavations
1926 Subpart X Ladders/Stairways
CONTRACTOR SAFETY PLAN
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01324-2
SECTION 01324
CONTRACTOR SAFETY PLAN
1926.52 Occupational noise
1926.62 Lead/Asbestos
1926.101 Hearing protection
1926.103 Respiratory protection
1926.109 Recordkeeping
1910.146 Confined spaces
Note: This prior list of regulations represents the major areas of concern and is in no way meant
to imply that compliance with other sections of 29CFR1910 and 29CFR1926 are not required.
7. Provide employee-screening procedures including policy for drug testing.
8. Provide the content of the safety orientation and hazard awareness training to be given
by the contractor to all new workers at the project site. Define records to be kept to
substantiate each worker’s satisfactory completion of the training and a procedure to
identify these personnel on the job (e.g., sticker on hard hat).
9, Commit to a risk management program to review and evaluate tasks for potential
hazards; a plan to mitigate these hazards and timely coordination and training of work
crews in applicable safety procedures.
10. Provide a list of hazardous materials to be used on site and corresponding Material
Safety Data Sheets.
11. Provide lockout-tag out precautions to deal with potential live power and utility lines.
12. Include a description of personal protective dress and equipment mandatory for use at
the construction site as well as for special tasks.
13. Describe the respiratory protection program. This should include selection of
equipment, fit testing, training in equipment use and familiarization with symptomatic
warnings.
14. Provide a program for safety record maintenance. Submit sample copies of report and
record forms to the project manager. These should include training logs, accident and
injury reports, first aid logs, daily/weekly safety inspection checklists, safety
coordination meeting minutes, and corrective and disciplinary actions. (Note: A
“Wrap-Up” insurance program has been purchased by the City to cover Workmen’s
CONTRACTOR SAFETY PLAN
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01324-3
SECTION 01324
CONTRACTOR SAFETY PLAN
r Compensation, General Liability, and Pollution Liability. Records and reports must
be adequate to cover potential claims.)
15. Define essentials of the fall protection program at the job site.
16. Detail safety procedures for confined space permitting, monitoring, entry and
emergency extrication.
17. Describe procedures for job site security, barricades, fencing warning signs, etc. to
restrict site access and provide for public safety.
18. Prescribe procedures for hot-work/fire protection including permitting, shielding, fire
watch, fire extinguisher placement.
19. Include an emergency communication and response plan for security, fire and rescue.
Outside emergency response resources and medical service providers shall be listed.
Emergency response drills should also be prescribed.
20. Include a plan to ensure adequate ventilation, dust control, sanitation and safe
drinking water.
21. Prescribe site storage requirements for hazardous and flammable materials.
© 22. Include housekeeping and debris removal procedures.
23. Contain a copy of the contractor’s substance abuse policy.
24. Contain a copy of the contractor’s Tool Box Talk program.
25. Contain a copy of the contractor’s NTI Jobsite Orientation Program for its employees.
26. Contain copies of all safety training documentation for the Contractor’s Safety
Representative and other employees assigned to the work, such as OSHA 10 hour,
OSHA 510 (30 hour), OSHA 500, CPR/First Aid, etc.
1.05 COORDINATION
A. The Contractor shall coordinate its Safety Plan to include all trades, sub-contracts and
utilities. The Contractor shall ensure that all subcontractors are familiar with and abide
by the Safety Plan.
1.06 UPDATING
@ CONTRACTOR SAFETY PLAN
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01324-4
SECTION 01324
CONTRACTOR SAFETY PLAN
A. Updating of the final Safety Plan shall be required periodically as the work of this @
Contract progresses. Include major changes in Plan, and activities modified since
previous updating.
1.07 DISTRIBUTION
A. Distribute copies of the Safety Plan to:
1. Project Manager.
2. Subcontractors.
3. Other Concerned Parties (surety, insurance, etc.).
4. Instruct recipients to report any inability to comply, and provide detailed explanation,
with suggested remedies.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
END OF SECTION
CONTRACTOR SAFETY PLAN @
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01324-5
SECTION 01324
CONTRACTOR SAFETY PLAN
[This page left out intentionally]
® CONTRACTOR SAFETY PLAN
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01324-6
SECTION 01330
SUBMITTALS
SECTION 01330 - SUBMITTALS
PART 1 - GENERAL
1.01 DESCRIPTION
A. Submittals are required prior to, during, and at the end of the installation period.
The submittals shall conform to the requirements described in this Section and all
referenced Sections or Articles.
1.02 PROCEDURE
A. Submit the following items within ten days after the Contract is executed.
1. Shop Drawings, Product Data and Samples: Submit Shop Drawings, product
data and samples in accordance with Section 01332, Shop Drawing
Procedures, and as required in applicable Sections of the Contract
Documents.
2. Request for Information: Submit a Request for Information (RFI), when any
of the following are required: an interpretation of the Specifications;
additional details; information not shown on the Drawings or in the
Specifications; or clarification of discrepancies is required. Manufacturer
shall retain one copy and submit one copy to the ENGINEER for response.
B. Submittal At Final Completion: Submit the following items in the proper form as
a condition of Final Acceptance of the Work:
1. Guarantees, Warranties, and Bonds: Submit as listed in various Sections of
the Specifications.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 01330
SUBMITTALS
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01330-1
SECTION 01330
SUBMITTALS
[This page left out intentionally]
|
SUBMITTALS
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01330-2
SECTION 01332
SHOP DRAWING PROCEDURES
SECTION 01332 - SHOP DRAWING PROCEDURES
PART 1 - GENERAL
1.1
A.
DESCRIPTION
The submittal of Shop Drawings shall conform to requirements of General
Conditions and procedures described in this Section. A separate transmittal form
shall be used for each specific item or class of material or equipment for which a
submittal is required.
The term “Shop Drawings” as used herein shall be understood to include detailed
design calculations, fabrication and installation drawings, lists, graphs, test data,
operating instructions, and other items which shall include, but are not necessarily
limited to:
1. Drawings and catalog information and cuts for shoring.
2. Applicable certifications.
3. Anchor bolt templates, mounting instructions, and mounting design
calculations as required.
4. Note, highlight, and explain proposed changes to the Contract Documents.
5. Drawings showing CONTRACTOR field verifications illustrating all field
dimensions. CONTRACTOR shall field verify all dimensions and existing
materials shown on the Drawings. Any modifications required shall be at
CONTRACTOR’S expense.
Preliminary Submittal Schedule: CONTRACTOR, within ten days after the
Notice to Proceed, shall prepare and submit to the ENGINEER a Preliminary
Submittal Schedule. CONTRACTOR shall identify on his Preliminary Submittal
Schedule all of the submittal items required by the Contract Documents governing
the Work.
Submittal Schedule. CONTRACTOR, within twenty-one (21) days after the
Notice to Proceed, shall prepare and submit to the ENGINEER a comprehensive
Submittal Schedule. CONTRACTOR shall identify on his Submittal Schedule all
of the submittal items required by the Contract Documents governing his Work.
CONTRACTOR shall indicate, for each submittal item on his Submittal Schedule
the following:
1. The date by which that item will be submitted to the ENGINEER.
Whether the submittal is for a substitute or “equal” item. Complete submittal
for all substitute or “equal” items shall be made to the ENGINEER, in
accordance with the Contract requirements. Identification by
CONTRACTOR of substitute or “equal” items does
not relieve CONTRACTOR of their responsibility to furnish equipment and
materials that meet all the requirements of the Contract Documents. Items of
SHOP DRAWING PROCEDURES
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01332-1
SECTION 01332
SHOP DRAWING PROCEDURES
1.2
manufacturers’ equipment listed with CONTRACTOR’S Bid Proposal shall
not be replaced with any substitute or “equal” items as part of this Submittal
Schedule process. Procedure for substitutions is specified under the General
Conditions.
3. Whether the submittal is for review or “for record only."
4. The date by which response is required.
5. The date by which the material or equipment must be on Site in order not to
delay the progress of the Work.
Note: Equipment in this section refers to machinery necessary for demolition,
i.€., pavement breakers, crushers, etc.
In preparing his Submittal Schedule. CONTRACTOR shall consider the nature
and complexity of each submittal item and shall allow ample time for review,
revision or correction. Submittal will normally be returned to CONTRACTOR
within ten calendar days following receipt of the submittal. Complex submittals,
for example, Instrumentation and Control Systems, Variable Frequency Drives
and other such submittals may require additional review time. CONTRACTOR
shall identify submittals for which he anticipates long review periods.
The ENGINEER will review CONTRACTOR’S Submittal Schedule to determine
its completeness and compatibility with the Progress Schedule. A Submittal
Schedule which is incompatible with the Progress Schedule or a review schedule
which places extraordinary manpower demands on the ENGINEER will be
sufficient reason(s) to reject the Submittal Schedule. It shall be understood that
certain submittals will take longer than ten days to review and that these particular
submittals will be identified during the review of the Submittal Schedule, by the
ENGINEER to allow for very complex submittal reviews. CONTRACTOR shall
also identify submittal for which he anticipates long review periods.
CONTRACTOR’S Submittal Schedule shall be consistent with the Progress
Schedule as described in Section 01320, Progress