READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 29 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
operations.
Retain professional land surveyor or civil engineer registered in state of Project
who shall perform or supervise engineering surveying necessary for additional
construction staking and layout.
Maintain complete accurate log of survey Work as it progresses as a Record
Document.
On request of ENGINEER, submit documentation.
Provide competent employee(s), tools, stakes, and other equipment and materials
as ENGINEER may require to:
Establish control points, lines, and easement boundaries.
b Check layout, survey, and measurement Work performed by others.
c. Measure quantities for payment purposes.
d Assist OWNER’s staff during bypassing or other interruption of normal
operation.
Cooperate with ENGINEER so that checking and measuring may be
accomplished with least interference to CONTRACTOR’s operations.
=
PROJECT MANAGEMENT AND COORDINATION
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01310-9
SECTION 01310 Russell Stephenson - Electrical Manhole Rehabilitation
PROJECT MANAGEMENT AND COORDINATION
© PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SALVAGE OF MATERIALS
A. OWNER reserves the right to salvage the following equipment and materials prior to
and during demolition. Specific materials to be salvaged include:
1. Five blowers and enclosures.
B. Salvage materials for OWNER’s use.
1. | Remove material with extreme care so as not to damage for future use.
2. Promptly remove from Work area salvaged materials.
3. Store materials on site where instructed by OWNER.
C. Meet with ENGINEER and OWNER prior to starting to dismantle equipment or piping
designated to be salvaged. ENGINEER will indicate locations where equipment is to be
disconnected. Unless modified by ENGINEER, CONTRACTOR shall disassemble
valves, pipes, and equipment at normal connection points.
D. Provide new or repair damaged equipment or material specified or indicated to be
salvaged that is damaged during removal. Store equipment as directed.
END OF SECTION 01310
PROJECT MANAGEMENT AND COORDINATION
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01310-10
SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1
A.
1.2
SUMMARY
This Section includes administrative and procedural requirements for documenting the
progress of construction during performance of the Work, including the following:
CONTRACTOR's Construction Schedule.
Submittals Schedule.
Daily construction reports.
Field condition reports.
AYN
See Division | Section "Payment Procedures" for submitting the Schedule of Values.
See Division 1 Section "Photographic Documentation" for submitting construction
photographs.
DEFINITIONS
Activity: A discrete part of a project that can be identified for planning, scheduling,
monitoring, and controlling the construction project. Activities included in a
construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on
the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
*
3. Successor Activity: An activity that follows another activity in the network.
CPM: Critical path method, which is a method of planning and scheduling a
construction project where activities are arranged based on activity relationships.
Network calculations determine when activities can be performed and the critical path
of Project.
Critical Path: The longest connected chain of interdependent activities through the
network schedule that establishes the minimum overall Project duration and contains no
float.
Float: The measure of leeway in starting and completing an activity.
|. Float time belongs to OWNER.
CONSTRUCTION PROGRESS DOCUMENTATION
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01320-1
SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
@ E. Fragnet: A partial or fragmentary network that breaks down activities into smaller
activities for greater detail.
F. Major Area: A story of construction, a separate building, or a similar significant
construction element.
1.3 SUBMITTALS
A. Submittals Schedule: Submit three copies of schedule. Arrange the following
information in a tabular format:
Scheduled date for first submittal.
Specification Section number and title.
Submittal category (action or informational).
Name of subcontractor.
Description of the Work covered.
Scheduled date for ENGINEER's final release or approval.
AARWN =
B. Preliminary Network Diagram: Submit 3 opaque copies, large enough to show entire
network for entire construction period. Show logic ties for activities.
C. CONTRACTOR's Construction Schedule: Submit 3 opaque copies of initial schedule,
@ large enough to show entire schedule for entire construction period.
1. Submit an electronic copy of schedule, using software indicated, on CD-R, and
labeled to comply with requirements for submittals. Include type of schedule
(Initial or Updated) and date on label.
D. CPM Reports: Concurrent with CPM schedule, submit 3 copies of each of the
following computer-generated reports. Format for each activity in reports shall contain
activity number, activity description, cost and resource loading, original duration,
remaining duration, early start date, early finish date, late start date, late finish date, and
total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early
start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for all activities, sorted
in ascending order by activity number and then early start date, or actual start date
if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
E. Daily Construction Reports: Submit 3 copies at monthly intervals.
F. Field Condition Reports: Submit 3 copies at time of discovery of differing conditions.
CONSTRUCTION PROGRESS DOCUMENTATION
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01320-2
SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
1.4
A.
COORDINATION
Coordinate preparation and processing of schedules and reports with performance of
construction activities and with scheduling and reporting of separate contractors.
Coordinate CONTRACTOR's Construction Schedule with the Schedule of Values, list
of subcontracts, Submittals Schedule, progress reports, payment requests, and other
required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from
parties involved.
2. Coordinate each construction activity in the network with other activities and
schedule them in proper sequence.
PART 2 - PRODUCTS
2.1
A.
2.2
SUBMITTALS SCHEDULE
Preparation: Submit a schedule of submittals, arranged in chronological order by dates
required by construction schedule. Include time required for review, resubmittal,
ordering, manufacturing, fabrication, and delivery when establishing dates.
1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values,
and CONTRACTOR's Construction Schedule.
2. Submit concurrently with the first complete submittal of CONTRACTOR's
Construction Schedule.
CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
Time Frame: Extend schedule from date established for Notice to Proceed to date of
Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that
shows an early completion date, unless specifically authorized by Change Order.
Activities: Treat each story or separate area as a separate numbered activity for each
principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 10 days, unless
specifically allowed by ENGINEER.
2. Submittal Review Time: Include review and resubmittal times indicated in
Division | Section "Submittal Procedures" in schedule. Coordinate submittal
review times in CONTRACTOR's Construction Schedule with Submittals
Schedule.
CONSTRUCTION PROGRESS DOCUMENTATION
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01320-3
SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
© 3. Substantial Completion: Indicate completion in advance of date established for
Substantial Completion, and allow time for ENGINEER's administrative
procedures necessary for certification of Substantial Completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract
Documents and as follows in schedule, and show how the sequence of the Work is
affected.
1. Phasing: Arrange list of activities on schedule by phase.
2. Work under More Than One Contract: Include a separate activity for each
contract.
3. | Work by OWNER: Include a separate activity for each portion of the Work
performed by OWNER.
4. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Completion of demolition before Substantial Completion.
d. _—_ Use of premises restrictions.
e. Seasonal variations.
f. Environmental control.
@ 5. Work Stages: Indicate important stages of construction for each major portion of
the Work.
6. Other Constraints:
D. Milestones: Include milestones indicated in the Contract Documents in schedule,
including, but not limited to, the Notice to Proceed, Substantial Completion, and Final
Completion, and the following interim milestones:
Mobilization of major equipment to be used for demolition
Demolition of each major structure
Demolition of underground utilities
Site Restoration
bh WN me
E. Contract Modifications: For each proposed contract modification and concurrent with
its submission, prepare a time-impact analysis using fragnets to demonstrate the effect
of the proposed change on the overall project schedule.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (CPM SCHEDULE)
A. General: Prepare network diagrams using AON (activity-on-node) format.
B. Preliminary Network Diagram: Submit diagram within 14 days of date established for
@ the Notice to Proceed. Outline significant construction activities for the first 120 days
CONSTRUCTION PROGRESS DOCUMENTATION
OKALOOSA COUNTY WATER AND SEWER DATE:8/15/2013
01320-4
SECTION 01320
CONSTRUCTION PROGRESS DOCUMENTATION
of construction. Include skeleton diagram for the remainder of the Work and a cash
requirement prediction based on indicated activities.
C. CPM Schedule: Prepare CONTRACTOR's Construction Schedule using Microsoft
Project, computerized resource-loaded, time-scaled CPM network analysis diagram for
the Work.
1. Develop network diagram in sufficient time to submit CPM schedule so it can be
accepted for use no later than 14 days after date established for the Notice to
Proceed.
a. Failure to include any work item required for performance of this Contract
shall not excuse CONTRACTOR from completing all work within
applicable completion dates, regardless of ENGINEER's approval of the
schedule.
2. Establish procedures for monitoring and updating CPM schedule and for reporting
progress. Coordinate procedures with progress meeting and payment request
dates.
Use "one workday" as the unit of time. Include list of nonworking days and
holidays incorporated into the schedule.
Go
D. CPM Schedule Preparation: Prepare a list of all activities required to complete the
Work. Using the preliminary network diagram, prepare a skeleton network to identify
probable critical paths.
1. Activities: Indicate the estimated time duration, sequence requirements, and
relationship of each activity in relation to other activities. Include estimated time
frames for the following activities:
Preparation and processing of submittals.
Mobilization and demobilization of major equipment used for demolition.
Demolition of each major facility.
Demolition of different components and materials, ie., concrete walls,
slabs, electrical, controls, pumps, etc..
e. |