Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 26 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
DATE: 8/15/2013
00100-14
SECTION 00810 Russell Stephenson - Electrical Manhole Rehabilitation
SPECIAL CONDITIONS
(THIS PAGE INTENTIONALLY LEFT BLANK)
SPECIAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
00810-4
SECTION 01010
Russell Stephenson - Electrical Manhole Rehabilitation
SUMMARY OF WORK
SECTION 01010 -SUMMARY OF WORK
PART 1 - GENERAL
1.1. SECTION INCLUDES
Faw >
General Description of Project
CONTRACTOR - Responsibility
OWNER - Responsibility
Contractor’s Use of Site
1.2 GENERAL DESCRIPTION OF PROJECT
A. The project shall include the rehabilitation of the electrical manholes to mitigate
the propagation of ground water infiltration in to the existing electrical manholes,
installation and repair of underground electrical conduit, dewatering, and
installation of a high water level monitoring system. In addition, the Contractor
shall be responsible for all other appurtenances and related work required to
complete the Work.
B. Contracting Method: Most Responsive Lowest Bid
1.3. CONTRACTOR RESPONSIBILITY
A. The following items are intended to identify the general scope of work to be
included in the Contractor’s bid proposal.
1. ELECTRICAL MANHOLE REHABILITATION — The Contractor shall be
responsible for performing the following tasks to mitigate the current ground
water infiltration in to the existing electrical manholes:
a.
The electrical manholes shall be required to be partially unearthed such
that visual evaluation of the electrical manhole can be performed.
During the visual inspection the contractor shall identify any areas on
the electrical manhole that shall require concrete repair or grout filling.
The electrical manhole exterior shall be cleaned and prepared per the
instructions of the exterior coating manufacturer. This shall include but
is not limited to pressure washing the exterior to remove any materials
that may impede the adhesion of the exterior coating.
Following the cleaning process any areas that were identified during
the visual inspection shall be repaired. Any concrete voids shall be
gout filled.
In addition, the three main electrical manholes shall have the new
conduits installed per the project documents. These conduits shall be
installed by core drilling and link sealing the penetration.
After cleaning the exterior of the electrical manholes shall be coated
with a polyurethane coating to prevent future ground water infiltration.
SUMMARY OF WORK
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01010-1
SECTION 01010 Russell Stephenson - Electrical Manhole Rehabilitation
SUMMARY OF WORK
f. The final task in the electrical rehabilitation shall be to replace the
existing electrical conductors as detailed in the project plans. The
existing electrical conductors shall be re-fed from the electrical source
to the existing electrical load. The splicing of the existing electrical
conductors shall not be allowed.
2. DEWATERING - Furnish the following components and appurtenances.
a. If elected by OWNER, provide all necessary pumps, piping, supports,
filters and fuel to operate a continuous dewater system of the electrical
manhole rehabilitation area excavation and underground electrical
conduit zones. The dewatering system must be designed to remove
groundwater at minimum elevation foundation and invert depths as
noted on drawings.
b. Contractor shall be responsible for means and methods to maintain a
dry environment for the installation of rock foundation and concrete
installation and curing time. Dewatering system must be designed by a
licensed engineer in the state of Florida, with prior experience with
similar installations and site conditions.
c. Provide one (1) stand-by back-up dewatering pump, for largest pump
in operation. Include wireless or dedicated analog communication
service (telemetry) to monitor pump(s) operation during all operations
periods. Coordinate with OWNER on notification set-up and hierarchy
of respondents. CONTRACTOR shall be responsible for providing
trained staff to operate and maintain system at all times while
equipment is on site and is place into operation.
1.4 OWNER RESPONSIBILITY
A. OWNER or OWNER”S REPRESENTATIVE shall perform inspections
throughout the construction. The Contractor shall be responsible for having the
OWNER or OWNER’S REPRESENTATIVE inspect the exterior of the electrical
manhole following the cleaning, after the point repairs, and after the exterior
coating are applied.
1.5 MATERIAL CONTRACTOR'S USE OF SITE
A. CONTRACTOR'S use of the Site shall be confined to the areas as dictated during
the pre-bid meeting.
B. CONTRACTOR shall:
1. Contractor shall coordinate with the OWNER and assume full
responsibility upon delivery to the project site to off load the equipment.
2. Obtain and pay for all additional storage or work areas required for its
equipment and material, prior to schedule delivery to Project site.
END OF SECTION 01010
SUMMARY OF WORK
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01010-2
SECTION 01250
SECTION 01250 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1]
A.
1.2
SUMMARY
This Section specifies administrative and procedural requirements for handling and
processing Contract modifications.
See Division 1 Section "Allowances" for procedural requirements for handling and
processing allowances.
See Division 1 Section "Unit Prices" for administrative requirements for using unit
prices.
MINOR CHANGES IN THE WORK
ENGINEER will issue supplemental instructions authorizing Minor Changes in the
Work, not involving adjustment to the Contract Sum or the Contract Time, on form
provided by ENGINEER.
PROPOSAL REQUESTS
OWNER-Initiated Proposal Requests: ENGINEER will issue a detailed description of
proposed changes in the Work that may require adjustment to the Contract Sum or the
Contract Time. If necessary, the description will include supplemental or revised
Drawings and Specifications.
1. Proposal Requests issued by ENGINEER are for information only. Do not
consider them instructions either to stop work in progress or to execute the
proposed change.
2. Within time specified in Proposal Request after receipt of Proposal Request,
submit a quotation estimating cost adjustments to the Contract Sum and the
Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs,
with total amount of purchases and credits to be made. If requested, furnish
survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts
of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
CONTRACT MODIFICATION PROCEDURES
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01250-1
Russell Stephenson - Electrical Manhole Rehabilitation
CONTRACT MODIFICATION PROCEDURES
SECTION 01250 Russell Stephenson - Electrical Manhole Rehabilitation
CONTRACT MODIFICATION PROCEDURES
@ d. ‘Include an updated CONTRACTOR's Construction Schedule that indicates
the effect of the change, including, but not limited to, changes in activity
duration, start and finish times, and activity relationship. Use available total
float before requesting an extension of the Contract Time.
B. CONTRACTOR-Initiated Proposals: If latent or unforeseen conditions require
modifications to the Contract, CONTRACTOR may propose changes by submitting a
request for a change to ENGINEER.
1. Include a statement outlining reasons for the change and the effect of the change
on the Work. Provide a complete description of the proposed change. Indicate
the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with
total amount of purchases and credits to be made. If requested, furnish survey
data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of
trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated CONTRACTOR's Construction Schedule that indicates the
effect of the change, including, but not limited to, changes in activity duration,
start and finish times, and activity relationship. Use available total float before
requesting an extension of the Contract Time.
@ 6. Comply with requirements in Division 1 Section "Product Requirements" if the
proposed change requires substitution of one product or system for product or
system specified.
C. Proposal Request Form: Use forms provided by ENGINEER
1.4 ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, base each Change Order
proposal on the difference between purchase amount and the allowance, multiplied by
final measurement of work-in-place. If applicable, include reasonable allowances for
cutting losses, tolerances, mixing wastes, normal product imperfections, and similar
margins.
1. Include installation costs in purchase amount only where indicated as part of the
allowance.
2. Ifrequested, prepare explanation and documentation to substantiate distribution of
overhead costs and other margins claimed.
Submit substantiation of a change in scope of work, if any, claimed in Change
Orders related to unit-cost allowances.
4. OWNER reserves the right to establish the quantity of work-in-place by
independent quantity survey, measure, or count.
wo
CONTRACT MODIFICATION PROCEDURES
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01250-2
SECTION 01250
B.
1.5
1.6
Submit claims for increased costs because of a change in scope or nature of the
allowance described in the Contract Documents, whether for the Purchase Order
amount or CONTRACTOR's handling, labor, installation, overhead, and profit. Submit
claims within 14 days of receipt of the Change Order or Construction Change Directive
authorizing work to proceed. OWNER will reject claims submitted later than 14 days
after such authorization.
1. Do not include CONTRACTOR's or subcontractor's indirect expense in the
Change Order cost amount unless it is clearly shown that the nature or extent of
work has changed from what could have been foreseen from information in the
Contract Documents.
2. No change to CONTRACTOR's indirect expense is permitted for selection of
higher- or lower-priced materials or systems of the same scope and nature as
originally indicated.
CHANGE ORDER PROCEDURES
On OWNER's approval of a Proposal Request, ENGINEER will issue a Change Order
for signatures of OWNER and CONTRACTOR on forms provided by ENGINEER.
CONSTRUCTION CHANGE DIRECTIVE
Work Change Directive: ENGINEER may issue a Construction Change Directive on
forms provided by ENGINEER. Work Change Directive instructs CONTRACTOR to
proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. | Work Change Directive contains a complete description of change in the Work. It
also designates method to be followed to determine change in the Contract Sum
or the Contract Time.
Documentation: Maintain detailed records on a time and material basis of work
required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data
necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01250
CONTRACT MODIFICATION PROCEDURES
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01250-3
Russell Stephenson - Electrical Manhole Rehabilitation
CONTRACT MODIFICATION PROCEDURES
SECTION 01250 Russell Stephenson - Electrical Manhole Rehabilitation
CONTRACT MODIFICATION PROCEDURES
(THIS PAGE INTENTIONALLY LEFT BLANK)
CONTRACT MODIFICATION PROCEDURES
OKALOOSA COUNTY WATER AND SEWER DATE: 8/15/2013
01250-4
SECTION 01270
MEASUREMENT AND PAYMENT
SECTION 01270 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1
A.
1.2
DESCRIPTION
The items listed below beginning with Article 1.5, refer to and are