READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 19 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
due, and when due will be paid by OWNER
to CONTRACTOR.
D. Reduction in Payment
1. OWNER may refuse to make payment of the
full amount recommended by ENGINEER because:
a. claims have been made against OWN-
ER on account of CONTRACTOR’s perfor-
mance or furnishing of the Work;
b. liens have been filed in connection with
the Work, except where CONTRACTOR has
delivered a specific Bond satisfactory to OWN-
ER to secure the satisfaction and discharge of
such Liens;
c. there are other items entitling OWNER
to a set-off against the amount recommended; or
d. OWNER has actual knowledge of the
occurrence of any of the events enumerated in
paragraphs 14.02.B.5.a through 14.02.B.5.c or
paragraph 15.02.A.
2. IfOWNER refuses to make payment of the
full amount recommended by ENGINEER, OWNER
must give CONTRACTOR immediate written notice
(with a copy to ENGINEER) stating the reasons for
such action and promptly pay CONTRACTOR any
amount remaining after deduction of the amount so
withheld. OWNER - shall promptly pay
CONTRACTOR the amount so withheld, or any
adjustment thereto agreed to by OWNER and
CONTRACTOR, when CONTRACTOR corrects to
OWNER’s satisfaction the reasons for such action.
3. If it is subsequently determined that
OWNER’ refusal of payment was not justified, the
Russell Stephenson — Electrical Manhole Rehabilitation
amount wrongfully withheld shall be treated as an
amount due as determined by paragraph 14.02.C.1.
14.03 CONTRACTOR’s Warranty of Title
A. CONTRACTOR warrants and guarantees that
title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the
Project or not, will pass to OWNER no later than the time
of payment free and clear of all Liens.
14.04 Substantial Completion
A. When CONTRACTOR considers the entire
Work ready for its intended use CONTRACTOR shall
notify OWNER and ENGINEER in writing that the entire
Work is substantially complete (except for items
specifically listed by CONTRACTOR as incomplete) and
request that ENGINEER issue a certificate of Substantial
Completion. Promptly thereafter, OWNER, CONTRAC-
TOR, and ENGINEER shall make an inspection of the
Work to determine the status of completion. If
ENGINEER does not consider the Work substantially
complete, ENGINEER will notify CONTRACTOR in
writing giving the reasons therefor. If ENGINEER
considers the Work substantially complete, ENGINEER
will prepare and deliver to OWNER a tentative certificate
of Substantial Completion which shall fix the date of
Substantial Completion. There shall be attached to the
certificate a tentative list of items to be completed or
corrected before final payment. OWNER shall have
seven days after receipt of the tentative certificate during
which to make written objection to ENGINEER as to any
provisions of the certificate or attached list. If, after
considering such objections, ENGINEER concludes that
the Work is not substantially complete, ENGINEER will
within 14 days after submission of the tentative certificate
to OWNER notify CONTRACTOR in writing, stating the
reasons therefor. If, after consideration of OWNER’s
objections, ENGINEER considers the Work substantially
complete, ENGINEER will within said 14 days execute
and deliver to OWNER and CONTRACTOR a definitive
certificate of Substantial Completion (with a revised
tentative list of items to be completed or corrected)
reflecting such changes from the tentative certificate as
ENGINEER believes justified after consideration of any
objections from OWNER. At the time of delivery of the
tentative certificate of Substantial Completion
ENGINEER will deliver to OWNER and CONTRAC-
TOR a written recommendation as to division of
responsibilities pending final payment between OWNER
and CONTRACTOR with respect to security, operation,
safety, and protection of the Work, maintenance, heat,
utilities, insurance, and warranties and guarantees.
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-40
SECTION 00700
GENERAL CONDITIONS
Unless OWNER and CONTRACTOR agree otherwise in
writing and so inform ENGINEER in writing prior to
ENGINEER’s issuing the definitive certificate of
Substantial Completion, ENGINEER’s aforesaid recom-
mendation will be binding on OWNER and CONTRAC-
TOR until final payment.
B. OWNER shall have the right to exclude
CONTRACTOR from the Site after the date of Substan-
tial Completion, but OWNER - shall allow
CONTRACTOR reasonable access to complete or
correct items on the tentative list.
14.05 Partial Utilization
A. Use by OWNER at OWNER’s option of any
substantially completed part of the Work which has
specifically been identified in the Contract Documents, or
which OWNER, ENGINEER, and CONTRACTOR
agree constitutes a separately functioning and usable part
ofthe Work that can be used by OWNER for its intended
purpose without significant interference with
CONTRACTOR’ s performance of the remainder of the
Work, may be accomplished prior to Substantial Com-
pletion of all the Work subject to the following condi-
tions.
1. OWNER at any time may request
CONTRACTOR in writing to permit OWNER to use
any such part of the Work which OWNER believes to
be ready for its intended use and substantially
complete. If CONTRACTOR agrees that such part of
the Work is substantially complete, CONTRACTOR
will certify to OWNER and ENGINEER that such
part of the Work is substantially complete and request
ENGINEER to issue a certificate of Substantial Com-
pletion for that part of the Work. CONTRACTOR at
any time may notify OWNER and ENGINEER in
writing that CONTRACTOR considers any such part
of the Work ready for its intended use and substan-
tially complete and request ENGINEER to issue a
certificate of Substantial Completion for that part of
the Work. Within a reasonable time after either such
request, OWNER, CONTRACTOR, and
ENGINEER shall make an inspection of that part of
the Work to determine its status of completion. If
ENGINEER does not consider that part of the Work
to be substantially complete, ENGINEER will notify
OWNER and CONTRACTOR in writing giving the
reasons therefor. If ENGINEER considers that part
of the Work to be substantially complete, the
provisions of paragraph 14.04 will apply with respect
to certification of Substantial Completion of that part
of the Work and the division of responsibility in
respect thereof and access thereto.
Russell Stephenson — Electrical Manhole Rehabilitation
2. No occupancy or separate operation of part
of the Work may occur prior to compliance with the
requirements of the Supplementary Conditions
regarding property insurance.
14.06 Final Inspection
A. Upon written notice from CONTRACTOR that
the entire Work or an agreed portion thereof is complete,
ENGINEER will promptly make a final inspection with
OWNER and CONTRACTOR and will notify
CONTRACTOR in writing of all particulars in which this
inspection reveals that the Work is incomplete or
defective. CONTRACTOR shall immediately take such
measures as are necessary to complete such Work or
remedy such deficiencies.
14.07 Final Payment
A. Application for Payment
1. After CONTRACTOR has, in the opinion of
ENGINEER, satisfactorily completed all corrections
identified during the final inspection and has delivered, in
accordance with the Contract Documents, all main-
tenance and operating instructions, schedules, guarantees,
Bonds, certificates or other evidence of insurance
certificates of inspection, marked-up record documents
(as provided in paragraph 6.12), and other documents,
CONTRACTOR may make application for final payment
following the procedure for progress payments.
2. The final Application for Payment shall be
accompanied (except as previously delivered) by: (i)
all documentation called for in the Contract Docu-
ments, including but not limited to the evidence of
insurance required by subparagraph 5.04.B.7; (ii)
consent of the surety, ifany, to final payment; and (iii)
complete and legally effective releases or waivers
(satisfactory to OWNER) ofall Lien rights arising out
of or Liens filed in connection with the Work.
3. In lieu of the releases or waivers of Liens
specified in paragraph 14.07.A.2 and as approved by
OWNER, CONTRACTOR may furnish receipts or
releases in full and an affidavit of CONTRACTOR
that: (i) the releases and receipts include all labor,
services, material, and equipment for which a Lien
could be filed; and (ii) all payrolls, material and
equipment bills, and other indebtedness connected
with the Work for which OWNER or OWNER's
property might in any way be responsible have been
paid or otherwise satisfied. If any Subcontractor or
Supplier fails to furnish such a release or receipt in
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-41
SECTION 00700
GENERAL CONDITIONS
full, CONTRACTOR may furnish a Bond or other
collateral satisfactory to OWNER to indemnify
OWNER against any Lien.
B. Review of Application and Acceptance
1. If, onthe basis op ENGINEER’ s observation
of the Work during construction and final inspection,
and ENGINEER’ review of the final Application for
Payment and accompanying documentation as re-
quired by the Contract Documents, ENGINEER is
satisfied that the Work has been completed and
CONTRACTOR’s other obligations under the Con-
tract Documents have been fulfilled, ENGINEER
will, within 10 days after receipt of the final Applica-
tion for Payment, indicate in writing ENGINEER’s
recommendation of payment and present the Applica-
tion for Payment to OWNER for payment. At the
same time ENGINEER will also give written notice
to OWNER and CONTRACTOR that the Work is
acceptable subject to the provisions of paragraph
14.09. Otherwise, ENGINEER will return the
Application for Payment to CONTRACTOR, indicat-
ing in writing the reasons for refusing to recommend
final payment, in which case CONTRACTOR shall
make the necessary corrections and resubmit the
Application for Payment.
C. Payment Becomes Due
1. Thirty days after the presentation to OWN-
ER of the Application for Payment and accompanying
documentation, the amount recommended by
ENGINEER will become due and, when due, will be
paid by OWNER to CONTRACTOR.
D. Final Completion Delayed
1. If, through no fault of CONTRACTOR, final
completion of the Work is significantly delayed, and if
ENGINEER so confirms, OWNER shall, upon
receipt of CONTRACTOR’s final Application for
Payment and recommendation of ENGINEER, and
without terminating the Agreement, make payment of
the balance due for that portion of the Work fully
completed and accepted. If the remaining balance to
be held by OWNER for Work not fully completed or
corrected is less than the retainage stipulated in the
Agreement, and if Bonds have been furnished as
required in paragraph 5.01, the written consent of the
surety to the payment of the balance due for that
portion of the Work fully completed and accepted
shall be submitted by CONTRACTOR to ENGI-
NEER with the Application for such payment. Such
payment shall be made under the terms and conditions
Russell Stephenson — Electrical Manhole Rehabilitation
governing final payment, except that it shall not
constitute a waiver of Claims.
14.08 (Not Used)
14.09 Waiver of Claims
A. The making and acceptance of final payment will
constitute:
1. a waiver of all Claims by OWNER against
CONTRACTOR, except Claims arising from
unsettled Liens, from defective Work appearing after
final inspection pursuant to paragraph 14.06, from
failure to comply with the Contract Documents or the
terms of any special guarantees specified therein, or
from CONTRACTOR’s continuing obligations under
the Contract Documents; and
2. a waiver of all Claims by CONTRACTOR
against OWNER other than those previously made in
writing which are still unsettled.
ARTICLE 15 - SUSPENSION OF WORK AND
TERMINATION
15.01 OWNER May Suspend Work
A. At any time and without cause, OWNER may
suspend the Work or any portion thereof for a period of
not more than 90
