Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 18 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
defective land or areas, or (ii) correct such defective
Work or, if the defective Work has been rejected by
OWNER, remove it from the Project and replace it with
Work that is not defective, and (iii) satisfactorily correct
or repair or remove and replace any damage to other
Work, to the work of others or other land or areas
resulting therefrom. If CONTRACTOR does not
promptly comply with the terms of such instructions, or in
an emergency where delay would cause serious risk of
loss or damage, OWNER may have the defective Work
corrected or repaired or may have the rejected Work re-
moved and replaced, and all Claims, costs, losses, and
damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to such correction or
repair or such removal and replacement (including but
not limited to all costs of repair or replacement of work of
others) will be paid by CONTRACTOR.
B. In special circumstances where a particular item
of equipment is placed in continuous service before
Substantial Completion of all the Work, the correction
period for that item may start to run from an earlier date if
so provided in the Specifications or by Written Amend-
ment.
C. Where defective Work (and damage to other
Work resulting therefrom) has been corrected or removed
and replaced under this paragraph 13.07, the correction
period hereunder with respect to such Work will be
extended for an additional period of one year after such
correction or removal and replacement has been
satisfactorily completed.
D. CONTRACTOR’s obligations under _ this
paragraph 13.07 are in addition to any other obligation or
warranty. The provisions of this paragraph 13.07 shall
not be construed as a substitute for or a waiver of the
provisions of any applicable statute of limitation or
repose.
13.08 Acceptance of Defective Work
A. If instead of requiring correction or removal and
replacement of defective Work, OWNER (and, prior to
ENGINEER’s recommendation of final payment,
ENGINEER) prefers to accept it, OWNER may do so.
CONTRACTOR shall pay all Claims, costs, losses, and
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-37
SECTION 00700
GENERAL CONDITIONS
damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) attributable to OWNER’s evaluation of and
determination to accept such defective Work (such costs
to be approved by ENGINEER as to reasonableness) and
the diminished value of the Work to the extent not
otherwise paid by CONTRACTOR pursuant to this
sentence. If any such acceptance occurs prior to
ENGINEER’s recommendation of final payment, a
Change Order will be issued incorporating the necessary
revisions in the Contract Documents with respect to the
Work, and OWNER shall be entitled to an appropriate
decrease in the Contract Price, reflecting the diminished
value of Work so accepted. Ifthe parties are unable to
agree as to the amount thereof, OWNER may make a
Claim therefor as provided in paragraph 10.05. If the
acceptance occurs after such recommendation, an
appropriate amount will be paid by CONTRACTOR to
OWNER.
13.09 OWNER May Correct Defective Work
A. IfCONTRACTOR fails within a reasonable time
after written notice from ENGINEER to correct defective
Work or to remove and replace rejected Work as required
by ENGINEER in accordance with paragraph 13.06.A,
or if CONTRACTOR fails to perform the Work in accor-
dance with the Contract Documents, or if
CONTRACTOR fails to comply with any other provision
of the Contract Documents, OWNER may, after seven
days written notice to CONTRACTOR, correct and
remedy any such deficiency.
B. Inexercising the rights and remedies under this
paragraph, OWNER shall proceed expeditiously. In
connection with such corrective and remedial action,
OWNER may exclude CONTRACTOR from all or part
of the Site, take possession of all or part of the Work and
suspend CONTRACTOR’s services related thereto, take
possession of CONTRACTOR’s tools, appliances, con-
struction equipment and machinery at the Site, and incor-
porate in the Work all materials and equipment stored at
the Site or for which OWNER has paid CONTRACTOR
but which are stored elsewhere. CONTRACTOR shall
allow OWNER, OWNER’s representatives, agents and
employees, OWNER’s other contractors, and ENGI-
NEER and ENGINEER’s Consultants access to the Site
to enable OWNER to exercise the rights and remedies
under this paragraph.
C. All Claims, costs, losses, and damages (including
but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court
Russell Stephenson — Electrical Manhole Rehabilitation
or arbitration or other dispute resolution costs) incurred
or sustained by OWNER in exercising the rights and
remedies under this paragraph 13.09 will be charged
against CONTRACTOR, and a Change Order will be
issued incorporating the necessary revisions in the
Contract Documents with respect to the Work; and
OWNER shall be entitled to an appropriate decrease in
the Contract Price. Ifthe parties are unable to agree as to
the amount of the adjustment, OWNER may make a
Claim therefor as provided in paragraph 10.05. Such
claims, costs, losses and damages will include but not be
limited to all costs of repair, or replacement of work of
others destroyed or damaged by correction, removal, or
replacement of CONTRACTOR’s defective Work.
D. CONTRACTOR shall not be allowed an
extension of the Contract Times (or Milestones) because
of any delay in the performance of the Work attributable
to the exercise by OWNER of OWNER’s rights and
remedies under this paragraph 13.09.
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND
COMPLETION
14.01 Schedule of Values
A. The schedule of values established as provided in
paragraph 2.07.A will serve as the basis for progress
payments and will be incorporated into a form of
Application for Payment acceptable to ENGINEER.
Progress payments on account of Unit Price Work will be
based on the number of units completed.
14.02 Progress Payments
A. Applications for Payments
1. Atleast 10 days before the date established
for each progress payment (but not more often than
once a month), CONTRACTOR shall submit to
ENGINEER for review an Application for Payment
filled out and signed by CONTRACTOR covering the
Work completed as of the date of the Application and
accompanied by such supporting documentation as is
required by the Contract Documents. If payment is
requested on the basis of materials and equipment not
incorporated in the Work but delivered and suitably
stored at the Site or at another location agreed to in
writing, the Application for Payment shall also be
accompanied by a bill of sale, invoice, or other docu-
mentation warranting that OWNER has received the
materials and equipment free and clear of all Liens
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-38
SECTION 00700
GENERAL CONDITIONS
and evidence that the materials and equipment are
covered by appropriate property insurance and other
arrangements to protect OWNER’s interest therein,
all of which must be satisfactory to OWNER.
2. Beginning with the second Application for
Payment, each Application shall include an affidavit
of CONTRACTOR stating that all previous progress
payments received on account of the Work have been
applied on account to discharge CONTRACTOR’s
legitimate obligations associated with prior
Applications for Payment.
3. The amount ofretainage with respect to pro-
gress payments will be as stipulated in the
Agreement.
B. Review of Applications
1. ENGINEER will, within 10 days after
receipt of each Application for Payment, either
indicate in writing a recommendation of payment and
present the Application to OWNER or return the
Application to CONTRACTOR indicating in writing
ENGINEER’s reasons for refusing to recommend
payment. In the latter case, CONTRACTOR may
make the necessary corrections and resubmit the
Application.
2. ENGINEER’s recommendation of any pay-
ment requested in an Application for Payment will
constitute a representation by ENGINEER to
OWNER, based on ENGINEER’s observations on
the Site of the executed Work as an experienced and
qualified design professional and on ENGINEER's
review of the Application for Payment and the
accompanying data and schedules, that to the best of
ENGINEER’s knowledge, information and belief:
a. the Work has progressed to the point
indicated;
b. the quality of the Work is generally in
accordance with the Contract Documents (sub-
ject to an evaluation of the Work as a functioning
whole prior to or upon Substantial Completion,
to the results of any subsequent tests called for in
the Contract Documents, to a final determination
of quantities and classifications for Unit Price
Work under paragraph 9.08, and to any other
qualifications stated in the recommendation); and
c. the conditions precedent to
CONTRACTOR’s being entitled to such pay-
Russell Stephenson — Electrical Manhole Rehabilitation
ment appear to have been fulfilled in so far as it
is ENGINEER’s responsibility to observe the
Work.
3. Byrecommending any such payment ENGI-
NEER will not thereby be deemed to have represent-
ed that: (i) inspections made to check the quality or
the quantity of the Work as it has been performed
have been exhaustive, extended to every aspect of the
Work in progress, or involved detailed inspections of
the Work beyond the responsibilities specifically as-
signed to ENGINEER in the Contract Documents; or
(ii) that there may not be other matters or issues
between the parties that might entitle CONTRAC-
TOR to be paid additionally by OWNER or entitle
OWNER to withhold payment to CONTRACTOR.
4. Neither ENGINEER’s review of
CONTRACTOR’s Work for the purposes of recom-
mending payments nor ENGINEER’s recommenda-
tion of any payment, including final payment, will
impose responsibility on ENGINEER to supervise,
direct, or control the Work or for the means, methods,
techniques, sequences, or procedures of construction,
or the safety precautions and programs incident
thereto, or for CONTRACTOR’ failure to comply
with Laws and Regulations applicable to
CONTRACTOR’s performance of the Work.
Additionally, said review or recommendation will not
impose responsibility on ENGINEER to make any
examination to ascertain how or for what purposes
CONTRACTOR has used the moneys paid on
account of the Contract Price, or to determine that
title to any of the Work, materials, or equipment has
passed to OWNER free and clear of any Liens.
5. ENGINEER may refuse to recommend the
whole or any part of any payment if, in ENGINEER’s
opinion, it would be incorrect to make the representa-
tions to OWNER referred to in paragraph 14.02.B.2.
ENGINEER may also refuse to recommend any such
payment or, because of subsequently discovered
evidence or the results of subsequent inspections or
tests, revise or revoke any such payment
recommendation previously made, to such extent as
may be necessary in ENGINEER’ s opinion to protect
OWNER from loss because:
a. the Work is defective, or completed
Work has been damaged, requiring correction or
replacement;
b. the Contract Price has been reduced by
Written Amendment or Change Orders;
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-39
DATE: 5/13/2012
SECTION 00700
GENERAL CONDITIONS
c. OWNER has been required to correct
defective Work or complete Work in accordance
with paragraph 13.09; or
d. ENGINEER has actual knowledge of
the occurrence of any of the events enumerated in
paragraph 15.02.A.
C. Payment Becomes Due
1. Thirty days after presentation of the Applica-
tion for Payment to OWNER with ENGINEER’s
recommendation, the amount recommended will
(subject to the provisions of paragraph 14.02.D)
become