Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 17 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
or
3. where the Work involved is not covered by
unit prices contained in the Contract Documents and
agreement to a lump sum is not reached under para-
graph 12.01.B.2, on the basis of the Cost of the Work
(determined as provided in paragraph 11.01) plus a
CONTRACTOR’s fee for overhead and profit (deter-
mined as provided in paragraph 12.01.C).
C. CONTRACTOR’s Fee: The CONTRACTOR’s
fee for overhead and profit shall be determined as
follows:
1. amutually acceptable fixed fee; or
2. ifa fixed fee is not agreed upon, then a fee
based on the following percentages of the various
portions of the Cost of the Work:
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-34
Russell Stephenson — Electrical Manhole Rehabilitation
SECTION 00700
GENERAL CONDITIONS
a. for costs incurred under paragraphs
11.01.A.1 and 11.01.A.2, the CONTRACTOR’s
fee shall be 15 percent;
b. for costs incurred under paragraph
11.01.A.3, the CONTRACTOR’s fee shall be
five percent;
c. where one or more tiers of subcontracts
are on the basis of Cost of the Work plus a fee
and no fixed fee is agreed upon, the intent of
paragraph 12.01.C.2.a is that the Subcontractor
who actually performs the Work, at whatever
tier, will be paid a fee of 15 percent of the costs
incurred by such Subcontractor under paragraphs
11.01.A.1 and 11.01.A.2 and that any higher tier
Subcontractor and CONTRACTOR will each be
paid a fee of five percent of the amount paid to
the next lower tier Subcontractor;
d. no fee shall be payable on the basis of
costs itemized under paragraphs 11.01.A.4,
11.01.A.5, and 11.01.B;
e. the amount of credit to be allowed by
CONTRACTOR to OWNER for any change
which results in a net decrease in cost will be the
amount of the actual net decrease in cost plus a
deduction in CONTRACTOR’s fee by an
amount equal to five percent of such net
decrease; and
f. when both additions and credits are in-
volved in any one change, the adjustment in
CONTRACTOR’ fee shall be computed on the
basis of the net change in accordance with para-
graphs 12.01.C.2.a through 12.01.C.2.e, inclu-
sive.
12.02 Change of Contract Times
A. The Contract Times (or Milestones) may only be
changed by a Change Order or by a Written Amendment.
Any Claim for an adjustment in the Contract Times (or
Milestones) shall be based on written notice submitted by
the party making the claim to the ENGINEER and the
other party to the Contract in accordance with the
provisions of paragraph 10.05.
B. Any adjustment of the Contract Times (or
Milestones) covered by a Change Order or of any Claim
for an adjustment in the Contract Times (or Milestones)
will be determined in accordance with the provisions of
this Article 12.
Russell Stephenson — Electrical Manhole Rehabilitation
12.03 Delays Beyond CONTRACTOR ’s Control
A. Where CONTRACTOR is prevented from
completing any part of the Work within the Contract
Times (or Milestones) due to delay beyond the control of
CONTRACTOR, the Contract Times (or Milestones)
will be extended in an amount equal to the time lost due
to such delay if'a Claim is made therefor as provided in
paragraph 12.02.A. Delays beyond the control of CON-
TRACTOR shall include, but not be limited to, acts or
neglect by OWNER, acts or neglect of utility owners or
other contractors performing other work as contemplated
by Article 7, fires, floods, epidemics, abnormal weather
conditions, or acts of God.
12.04 Delays Within CONTRACTOR’s Control
A. The Contract Times (or Milestones) will not be
extended due to delays within the control of
CONTRACTOR. Delays attributable to and within the
control ofa Subcontractor or Supplier shall be deemed to
be delays within the control of CONTRACTOR.
12.05 Delays Beyond OWNER’s and
CONTRACTOR'S Control
A. Where CONTRACTOR is prevented from
completing any part of the Work within the Contract
Times (or Milestones) due to delay beyond the control of
both OWNER and CONTRACTOR, an extension of the
Contract Times (or Milestones) in an amount equal to the
time lost due to such delay shall be CONTRACTOR’s
sole and exclusive remedy for such delay.
12.06 Delay Damages
A. In no event shall OWNER or ENGINEER be
liable to CONTRACTOR, any Subcontractor, any
Supplier, or any other person or organization, or to any
surety for or employee or agent of any of them, for
damages arising out of or resulting from:
1. delays caused by or within the control of
CONTRACTOR; or
2. delays beyond the control of both OWNER
and CONTRACTOR including but not limited to
fires, floods, epidemics, abnormal weather conditions,
acts of God, or acts or neglect by utility owners or
other contractors performing other work as
contemplated by Article 7.
B. Nothing in this paragraph 12.06 bars a change in
Contract Price pursuant to this Article 12 to compensate
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-35
SECTION 00700
GENERAL CONDITIONS
CONTRACTOR due to delay, interference, or disruption
directly attributable to actions or inactions of OWNER or
anyone for whom OWNER is responsible.
ARTICLE 13 - TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
A. Prompt notice of all defective Work of which
OWNER or ENGINEER has actual knowledge will be
given to CONTRACTOR. All defective Work may be
rejected, corrected, or accepted as provided in this
Article 13.
13.02 Access to Work
A. OWNER, ENGINEER, ENGINEER’s Con-
sultants, other representatives and personnel of OWNER,
independent testing laboratories, and governmental
agencies with jurisdictional interests will have access to
the Site and the Work at reasonable times for their obser-
vation, inspecting, and testing. CONTRACTOR shall
provide them proper and safe conditions for such access
and advise them of CONTRACTOR’s Site safety
procedures and programs so that they may comply
therewith as applicable.
13.03 Tests and Inspections
A. CONTRACTOR shall give ENGINEER timely
notice of readiness of the Work for all required
inspections, tests, or approvals and shall cooperate with
inspection and testing personnel to facilitate required
inspections or tests.
B. OWNER shall employ and pay for the services of
an independent testing laboratory to perform all
inspections, tests, or approvals required by the Contract
Documents except:
1. for inspections, tests, or approvals covered
by paragraphs [3.03.C and 13.03.D below;
2. that costs incurred in connection with tests or
inspections conducted pursuant to paragraph 13.04.B
shall be paid as provided in said paragraph 13.04.B;
and
3. as otherwise specifically provided in the
Contract Documents.
Russell Stephenson — Electrical Manhole Rehabilitation
C. IfLaws or Regulations of any public body having
jurisdiction require any Work (or part thereof)
specifically to be inspected, tested, or approved by an
employee or other representative of such public body,
CONTRACTOR shall assume full responsibility for
arranging and obtaining such inspections, tests, or
approvals, pay all costs in connection therewith, and
furnish ENGINEER the required certificates of inspec-
tion or approval.
D. CONTRACTOR shall be responsible for
arranging and obtaining and shall pay all costs in connec-
tion with any inspections, tests, or approvals required for
OWNER’s and ENGINEER’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance
of materials, mix designs, or equipment submitted for
approval prior to CONTRACTOR’s purchase thereof for
incorporation in the Work. Such inspections, tests, or
approvals shall be performed by organizations acceptable
to OWNER and ENGINEER.
E. Ifany Work (or the work of others) that is to be
inspected, tested, or approved is covered by
CONTRACTOR without written concurrence of
ENGINEER, it must, if requested by ENGINEER, be
uncovered for observation.
F. Uncovering Work as provided in paragraph
13.03.E shall be at CONTRACTOR’s expense unless
CONTRACTOR has given ENGINEER timely notice of
CONTRACTOR’s intention to cover the same and
ENGINEER has not acted with reasonable promptness in
response to such notice.
13.04 Uncovering Work
A. If any Work is covered contrary to the written
request of ENGINEER, it must, if requested by
ENGINEER, be uncovered for ENGINEER’s
observation and replaced at CONTRACTOR’s expense.
B. If ENGINEER considers it necessary or
advisable that covered Work be observed by ENGINEER
or inspected or tested by others, CONTRACTOR, at
ENGINEER’s request, shall uncover, expose, or
otherwise make available for observation, inspection, or
testing as ENGINEER may require, that portion of the
Work in question, furnishing all necessary labor, materi-
al, and equipment. If it is found that such Work is
defective, CONTRACTOR shall pay all Claims, costs,
losses, and damages (including but not limited to all fees
and charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-36
DATE: 5/13/2012
SECTION 00700
GENERAL CONDITIONS
resolution costs) arising out of or relating to such
uncovering, exposure, observation, inspection, and
testing, and of satisfactory replacement or reconstruction
(including but not limited to all costs of repair or
replacement of work of others); and OWNER shall be
entitled to an appropriate decrease in the Contract Price.
Ifthe parties are unable to agree as to the amount thereof,
OWNER may make a Claim therefor as provided in
paragraph 10.05. If, however, such Work is not found to
be defective, CONTRACTOR shall be allowed an
increase in the Contract Price or an extension of the
Contract Times (or Milestones), or both, directly attribut-
able to such uncovering, exposure, observation,
inspection, testing, replacement, and reconstruction. If
the parties are unable to agree as to the amount or extent
thereof, CONTRACTOR may make a Claim therefor as
provided in paragraph 10.05.
13.05 OWNER May Stop the Work
A. Ifthe Work is defective, or CONTRACTOR fails
to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way
that the completed Work will conform to the Contract
Documents, OWNER may order CONTRACTOR to stop
the Work, or any portion thereof, until the cause for such
order has been eliminated; however, this right of
OWNER to stop the Work shall not give rise to any duty
on the part of OWNER to exercise this right for the
benefit of CONTRACTOR, any Subcontractor, any
Supplier, any other individual or entity, or any surety for,
or employee or agent of any of them.
13.06 Correction or Removal of Defective Work
A. CONTRACTOR shall correct all defective Work,
whether or not fabricated, installed, or completed, or, if
the Work has been rejected by ENGINEER, remove it
from the Project and replace it with Work that is not
defective. CONTRACTOR shall pay all Claims, costs,
losses, and damages (including but not limited to all fees
and charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such
correction or removal (including but not limited to all
costs of repair or replacement of work of others).
13.07 Correction Period
A. If within one year after the date of Substantial
Completion or such longer period of time as may be
prescribed by Laws or Regulations or by the terms of any
applicable special guarantee required by the Contract
Documents or by any specific provision of the Contract
Documents, any Work is found to be defective, or if the
Russell Stephenson — Electrical Manhole Rehabilitation
repair of any damages to the land or areas made available
for CONTRACTOR’s use by OWNER or permitted by
Laws and Regulations as contemplated in paragraph
6.11.A is found to be defective, CONTRACTOR shall
promptly, without cost to OWNER and in accordance
with OWNER’s written instructions: (i) repair such