READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 16 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
of the claimant or the last submittal of the
opposing party, if any.
D. No Claim for an adjustment in Contract Price or
Contract Times (or Milestones) will be valid if not
submitted in accordance with this paragraph 10.05.
ARTICLE 11 - COST OF THE WORK; CASH
ALLOWANCES; UNIT PRICE WORK
11.01 Cost of the Work
A. Costs Included: The term Cost of the Work
means the sum of all costs necessarily incurred and paid
by CONTRACTOR in the proper performance of the
Work. When the value ofany Work covered bya Change
Order or when a Claim for an adjustment in Contract
Price is determined on the basis of Cost of the Work, the
costs to be reimbursed to CONTRACTOR will be only
those additional or incremental costs required because of
the change in the Work or because of the event giving
rise to the Claim. Except as otherwise may be agreed to
in writing by OWNER, such costs shall be in amounts no
higher than those prevailing in the locality of the Project,
shall include only the following items, and shall not
include any of the costs itemized in paragraph 11.01.B.
1. Payroll costs for employees in the direct
employ of CONTRACTOR in the performance of the
Work under schedules of job classifications agreed
upon by OWNER and CONTRACTOR. Such
employees shall include without limitation superinten-
dents, foremen, and other personnel employed full
time at the Site. Payroll costs for employees not
employed full time on the Work shall be apportioned
on the basis of their time spent on the Work. Payroll
costs shall include, but not be limited to, salaries and
wages plus the cost of fringe benefits, which shall
include social security contributions, unemployment,
excise, and payroll taxes, workers’ compensation,
health and retirement benefits, bonuses, sick leave,
vacation and holiday pay applicable thereto. The
expenses of performing Work outside of regular
working hours, on Saturday, Sunday, or legal
holidays, shall be included in the above to the extent
authorized by OWNER.
Russell Stephenson — Electrical Manhole Rehabilitation
2. Cost of all materials and equipment fur-
nished and incorporated in the Work, including costs
of transportation and storage thereof, and Suppliers’
field services required in connection therewith. All
cash discounts shall accrue to CONTRACTOR unless
OWNER deposits funds with CONTRACTOR with
which to make payments, in which case the cash
discounts shall accrue to OWNER. All trade dis-
counts, rebates and refunds and returns from sale of
surplus materials and equipment shall accrue to
OWNER, and CONTRACTOR shall make
provisions so that they may be obtained.
3. Payments made by CONTRACTOR to
Subcontractors for Work performed by Sub-
contractors. If required by OWNER,
CONTRACTOR shall obtain competitive bids from
subcontractors acceptable to OWNER and CON-
TRACTOR and shall deliver such bids to OWNER,
who will then determine, with the advice of ENGI-
NEER, which bids, if any, will be acceptable. Ifany
subcontract provides that the Subcontractor is to be
paid on the basis of Cost of the Work plus a fee, the
Subcontractor’s Cost of the Work and fee shall be
determined in the same manner as CONTRACTOR’s
Cost of the Work and fee as provided in this para-
graph 11.01.
4. Costs of special consultants (including but
not limited to engineers, architects, testing laborato-
ries, surveyors, attorneys, and accountants) employed
for services specifically related to the Work.
5. Supplemental costs including the following:
a. The proportion of necessary trans-
portation, travel, and subsistence expenses of
CONTRACTOR's employees incurred in dis-
charge of duties connected with the Work.
b. Cost, including transportation and main-
tenance, of all materials, supplies, equipment,
machinery, appliances, office, and temporary
facilities at the Site, and hand tools not owned by
the workers, which are consumed in the perfor-
mance of the Work, and cost, less market value,
of such items used but not consumed which
remain the property of CONTRACTOR.
c. Rentals of all construction equipment
and machinery, and the parts thereof whether
rented from CONTRACTOR or others in accor-
dance with rental agreements approved by
OWNER with the advice of ENGINEER, and the
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-32
DATE: 5/13/2012
SECTION 00700 Russell Stephenson — Electrical Manhole Rehabilitation
GENERAL CONDITIONS
costs of transportation, loading, unloading,
assembly, dismantling, and removal thereof. All
such costs shall be in accordance with the terms
of said rental agreements. The rental of any such
equipment, machinery, or parts shall cease when
the use thereof is no longer necessary for the
Work.
d. Sales, consumer, use, and other similar
taxes related to the Work, and for which
CONTRACTOR is liable, imposed by Laws and
Regulations.
e. Deposits lost for causes other than
negligence of CONTRACTOR, any Sub-
contractor, or anyone directly or indirectly
employed by any of them or for whose acts any of
them may be liable, and royalty payments and
fees for permits and licenses.
f Losses and damages (and related
expenses) caused by damage to the Work, not
compensated by insurance or otherwise, sus-
tained by CONTRACTOR in connection with
the performance of the Work (except losses and
damages within the deductible amounts of
property insurance established in accordance
with paragraph 5.06.D), provided such losses
and damages have resulted from causes other
than the negligence of CONTRACTOR, any
Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of
them may be liable. Such losses shall include
settlements made with the written consent and
approval of OWNER. No such losses, damages,
and expenses shall be included in the Cost of the
Work for the purpose of determining
CONTRACTOR’s fee.
g. The cost of utilities, fuel, and sanitary
facilities at the Site.
h. Minor expenses such as telegrams, long
distance telephone calls, telephone service at the
Site, expressage, and similar petty cash items in
connection with the Work.
i. When the Cost of the Work is used to
determine the value of a Change Order or of a
Claim, the cost of premiums for additional Bonds
and insurance required because of the changes in
the Work or caused by the event giving rise to
the Claim.
j. When all the Work is performed on the
basis of cost-plus, the costs of premiums for all
Bonds and insurance CONTRACTOR is
required by the Contract Documents to purchase
and maintain.
B. Costs Excluded: The term Cost of the Work shall
not include any of the following items:
1. Payroll costs and other compensation of
CONTRACTOR’ s officers, executives, principals (of
partnerships and sole proprietorships), general
managers, engineers, architects, estimators, attorneys,
auditors, accountants, purchasing and contracting
agents, expediters, timekeepers, clerks, and other
personnel employed by CONTRACTOR, whether at
the Site or in CONTRACTOR’s principal or branch
office for general administration of the Work and not
specifically included in the agreed upon schedule of
job classifications referred to in paragraph 11.01.A.1
or specifically covered by paragraph 11.01.A.4, all of
which are to be considered administrative costs
covered by the CONTRACTOR’s fee.
2. Expenses of CONTRACTOR’s principal
and branch offices other than CONTRACTOR’s
office at the Site.
3. Any part of CONTRACTOR’s capital
expenses, including interest on CONTRACTOR’s
capital employed for the Work and charges against
CONTRACTOR for delinquent payments.
4. Costs due to the negligence of CONTRAC-
TOR, any Subcontractor, or anyone directly or
indirectly employed by any of them or for whose acts
any of them may be liable, including but not limited
to, the correction of defective Work, disposal of
materials or equipment wrongly supplied, and making
good any damage to property.
5. Other overhead or general expense costs of
any kind and the costs of any item not specifically and
expressly included in paragraphs 11.01.A and
11.01.B.
C. CONTRACTOR’s Fee: When all the Work is
performed on the basis of cost-plus, CONTRACTOR’s
fee shall be determined as set forth in the Agreement.
When the value of any Work covered by a Change Order
or when a Claim for an adjustment in Contract Price is
determined on the basis of Cost of the Work,
CONTRACTOR’s fee shall be determined as set forth in
paragraph 12.01.C.
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-33
SECTION 00700
GENERAL CONDITIONS
D. Documentation: Whenever the Cost ofthe Work
for any purpose is to be determined pursuant to
paragraphs 11.01.A and 11.01.B, CONTRACTOR will
establish and maintain records thereof in accordance with
generally accepted accounting practices and submit in a
form acceptable to ENGINEER an itemized cost
breakdown together with supporting data.
11.02 Cash Allowances
A. Itis understood that CONTRACTOR has includ-
ed in the Contract Price all allowances so named in the
Contract Documents and shall cause the Work so covered
to be performed for such sums as may be acceptable to
OWNER and ENGINEER. CONTRACTOR agrees that:
1. the allowances include the cost to
CONTRACTOR (less any applicable trade discounts)
of materials and equipment required by the allowanc-
es to be delivered at the Site, and all applicable taxes;
and
2. CONTRACTOR’s costs for unloading and
handling on the Site, labor, installation costs, over-
head, profit, and other expenses contemplated for the
allowances have been included in the Contract Price
and not in the allowances, and no demand for addi-
tional payment on account of any of the foregoing will
be valid.
B. Prior to final payment, an appropriate Change
Order will be issued as recommended by ENGINEER to
reflect actual amounts due CONTRACTOR on account
of Work covered by allowances, and the Contract Price
shall be correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that all
or part of the Work is to be Unit Price Work, initially the
Contract Price will be deemed to include for all Unit
Price Work an amount equal to the sum of the unit price
for each separately identified item of Unit Price Work
times the estimated quantity of each item as indicated in
the Agreement. The estimated quantities of items of Unit
Price Work are not guaranteed and are solely for the
purpose of comparison of Bids and determining an initial
Contract Price. Determinations of the actual quantities
and classifications of Unit Price Work performed by
CONTRACTOR will be made by ENGINEER subject to
the provisions of paragraph 9.08.
B. Each unit price will be deemed to include an
amount considered by CONTRACTOR to be adequate to
cover CONTRACTOR’s overhead and profit for each
separately identified item.
C. For provisions for an adjustment of a unit price
for an increase or decrease in the quantity of Unit Price
Work, if any, see General Requirements Section 01025,
Measurement and Payment.
ARTICLE 12 - CHANGE OF CONTRACT PRICE;
CHANGE OF CONTRACT TIMES
12.01 Change of Contract Price
A. The Contract Price may only be changed by a
Change Order or by a Written Amendment. Any Claim
for an adjustment in the Contract Price shall be based on
written notice submitted by the party making the claim to
the ENGINEER and the other party to the Contract in
accordance with the provisions of paragraph 10.05.
B. The value of any Work covered by a Change
Order or of any Claim for an adjustment in the Contract
Price will be determined as follows:
1. where the Work involved is covered by unit
prices contained in the Contract Documents, by
application of such unit prices to the quantities of the
items involved (subject to the provisions of paragraph
11.03); or
2. where the Work involved is not covered by
unit prices contained in the Contract Documents, bya
mutually agreed lump sum (which may include an
allowance for overhead and profit not necessarily in
accordance with paragraph 12.01.C.2);