READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 15 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
will be binding on OWNER and
CONTRACTOR. IfOWNER and CONTRACTOR are
unable to agree on entitlement to or on the amount or
extent, if any, of any adjustment in the Contract Price or
Contract Times, or both, that should be allowed as a
Russell Stephenson — Electrical Manhole Rehabilitation
result of a written clarification or interpretation, a Claim
may be made therefor as provided in paragraph 10.05.
9.05 Authorized Variations in Work
A. ENGINEER may authorize minor variations in
the Work from the requirements of the Contract
Documents which do not involve an adjustment in the
Contract Price or the Contract Times and are compatible
with the design concept of the completed Project as a
functioning whole as indicated by the Contract Docu-
ments. These may be accomplished by a Field Order and
will be binding on OWNER and also on CON-
TRACTOR, who shall perform the Work involved
promptly. If OWNER and CONTRACTOR are unable
to agree on entitlement to or on the amount or extent, if
any, of any adjustment in the Contract Price or Contract
Times, or both, as a result of a Field Order, a Claim may
be made therefor as provided in paragraph 10.05.
9.06 Rejecting Defective Work
A. ENGINEER will have authority to disapprove or
reject Work which ENGINEER believes to be defective,
or that ENGINEER believes will not produce a
completed Project that conforms to the Contract
Documents or that will prejudice the integrity of the
design concept of the completed Project as a functioning
whole as indicated by the Contract Documents. ENGI-
NEER will also have authority to require special inspec-
tion or testing of the Work as provided in paragraph
13.04, whether or not the Work is fabricated, installed, or
completed.
9.07 Shop Drawings, Change Orders and Payments
A. In connection with ENGINEER’s authority as to
Shop Drawings and Samples, see paragraph 6.17.
B. Inconnection with ENGINEER’s authority as to
Change Orders, see Articles 10, 11, and 12.
C. In connection with ENGINEER’s authority as to
Applications for Payment, see Article 14.
9.08 Determinations for Unit Price Work
A. ENGINEER will determine the actual quantities
and classifications of Unit Price Work performed by
CONTRACTOR. ENGINEER will review with
CONTRACTOR the ENGINEER’s preliminary
determinations on such matters before rendering a written
decision thereon (by recommendation of an Application
for Payment or otherwise). ENGINEER’s written
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-29
SECTION 00700
GENERAL CONDITIONS
decision thereon will be final and binding (except as
modified by ENGINEER to reflect changed factual
conditions or more accurate data) upon OWNER and
CONTRACTOR, subject to the provisions of paragraph
10.05.
9.09 Decisions on Requirements of Contract
Documents and Acceptability of Work
A. ENGINEER will be the initial interpreter of the
requirements of the Contract Documents and judge of the
acceptability of the Work thereunder. Claims, disputes
and other matters relating to the acceptability of the
Work, the quantities and classifications of Unit Price
Work, the interpretation of the requirements of the
Contract Documents pertaining to the performance of the
Work, and Claims seeking changes in the Contract Price
or Contract Times will be referred initially to
ENGINEER in writing, in accordance with the provisions
of paragraph 10.05, with a request for a formal decision.
B. When functioning as interpreter and judge under
this paragraph 9.09, ENGINEER will not show partiality
to OWNER or CONTRACTOR and will not be liable in
connection with any interpretation or decision rendered in
good faith in such capacity. The rendering ofa decision
by ENGINEER pursuant to this paragraph 9.09 with
respect to any such Claim, dispute, or other matter
(except any which have been waived by the making or
acceptance of final payment as provided in paragraph
14.07) will be a condition precedent to any exercise by
OWNER or CONTRACTOR of such rights or remedies
as either may otherwise have under the Contract
Documents or by Laws or Regulations in respect of any
such Claim, dispute, or other matter.
9.10 Limitations on ENGINEER's Authority and
Responsibilities
A. Neither ENGINEER’s authority or responsibility
under this Article 9 or under any other provision of the
Contract Documents nor any decision made by
ENGINEER in good faith either to exercise or not exer-
cise such authority or responsibility or the undertaking,
exercise, or performance of any authority or responsibility
by ENGINEER shall create, impose, or give rise to any
duty in contract, tort, or otherwise owed by ENGINEER
to CONTRACTOR, any Subcontractor, any Supplier, any
other individual or entity, or to any surety for or employee
or agent of any of them.
B. ENGINEER will not supervise, direct, control, or
have authority over or be responsible for
Russell Stephenson — Electrical Manhole Rehabilitation
CONTRACTOR’s means, methods, techniques, se-
quences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any
failure of CONTRACTOR to comply with Laws and
Regulations applicable to the performance of the Work.
ENGINEER will not be responsible for
CONTRACTOR’s failure to perform the Work in accor-
dance with the Contract Documents.
C. ENGINEER will not be responsible for the acts
or omissions of CONTRACTOR or ofany Subcontractor,
any Supplier, or of any other individual or entity
performing any of the Work.
D. ENGINEER’s review of the final Application for
Payment and accompanying documentation and all
maintenance and operating instructions, schedules,
guarantees, Bonds, certificates of inspection, tests and
approvals, and other documentation required to be
delivered by paragraph 14.07.A will only be to determine
generally that their content complies with the require-
ments of, and in the case of certificates of inspections,
tests, and approvals that the results certified indicate
compliance with, the Contract Documents.
E. The limitations upon authority and responsibility
set forth in this paragraph 9.10 shall also apply to
ENGINEER’s Consultants, Resident Project Repre-
sentative, and assistants.
ARTICLE 10 - CHANGES IN THE WORK; CLAIMS
10.01 Authorized Changes in the Work
A. Without invalidating the Agreement and without
notice to any surety, OWNER may, at any time or from
time to time, order additions, deletions, or revisions in the
Work by a Written Amendment, a Change Order, or a
Work Change Directive. Upon receipt of any such
document, CONTRACTOR shall promptly proceed with
the Work involved which will be performed under the
applicable conditions of the Contract Documents (except
as otherwise specifically provided).
B. IfOWNER and CONTRACTOR are unable to
agree on entitlement to, or on the amount or extent, ifany,
of an adjustment in the Contract Price or Contract Times,
or both, that should be allowed as a result of a Work
Change Directive, a Claim may be made therefor as
provided in paragraph 10.05.
10.02 Unauthorized Changes in the Work
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-30
SECTION 00700
GENERAL CONDITIONS
A. CONTRACTOR shall not be entitled to an
increase in the Contract Price or an extension of the
Contract Times with respect to any work performed that
is not required by the Contract Documents as amended,
modified, or supplemented as provided in paragraph
3.04, except in the case of an emergency as provided in
paragraph 6.16 or in the case of uncovering Work as
provided in paragraph 13.04.B.
10.03 Execution of Change Orders
A. OWNER and CONTRACTOR shall execute
appropriate Change Orders recommended by ENGI-
NEER (or Written Amendments) covering:
1. changes in the Work which are: (i) ordered
by OWNER pursuant to paragraph 10.01.A, (ii) re-
quired because of acceptance of defective Work under
paragraph 13.08.A or OWNER’s correction of
defective Work under paragraph 13.09, or (iii) agreed
to by the parties;
2. changes in the Contract Price or Contract
Times which are agreed to by the parties, including
any undisputed sum or amount of time for Work
actually performed in accordance with a Work
Change Directive; and
3. changes in the Contract Price or Contract
Times which embody the substance of any written
decision rendered by ENGINEER pursuant to para-
graph 10.05; provided that, in lieu of executing any
such Change Order, an appeal may be taken from any
such decision in accordance with the provisions of the
Contract Documents and applicable Laws and
Regulations, but during any such appeal,
CONTRACTOR shall carry on the Work and adhere
to the progress schedule as provided in paragraph
6.18.A.
10.04 Notification to Surety
A. If notice of any change affecting the general
scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract Price
or Contract Times) is required by the provisions of any
Bond to be given to a surety, the giving of any such notice
will be CONTRACTOR'’s responsibility. The amount of
each applicable Bond will be adjusted to reflect the effect
of any such change.
Russell Stephenson — Electrical Manhole Rehabilitation
10.05 Claims and Disputes
A. Notice: Written notice stating the general nature
of each Claim, dispute, or other matter shall be delivered
by the claimant to ENGINEER and the other party to the
Contract promptly (but in no event later than 20 days)
after the start of the event giving rise thereto. Notice of
the amount or extent of the Claim, dispute, or other
matter with supporting data shall be delivered to the
ENGINEER and the other party to the Contract within 45
days after the start of such event (unless ENGINEER
allows additional time for claimant to submit additional or
more accurate data in support of such Claim, dispute, or
other matter). A Claim for an adjustment in Contract
Price shall be prepared in accordance with the provisions
of paragraph 12.01.B. A Claim for an adjustment in
Contract Time shall be prepared in accordance with the
provisions of paragraph 12.02.B. Each Claim shall be
accompanied by claimant's written statement that the
adjustment claimed is the entire adjustment to which the
claimant believes it is entitled as a result of said event.
The opposing party shall submit any response to
ENGINEER and the claimant within 30 days after receipt
of the claimant’s last submittal (unless ENGINEER
allows additional time).
B. ENGINEER’s Decision: ENGINEER will
render a formal decision in writing within 30 days after
receipt of the last submittal of the claimant or the last
submittal of the opposing party, if any. ENGINEER’s
written decision on such Claim, dispute, or other matter
will be final and binding upon OWNER and
CONTRACTOR unless:
1. an appeal from ENGINEER’s decision is
taken within the time limits and in accordance with
the dispute resolution procedures set forth in Article
16; or
2. ifno such dispute resolution procedures have
been set forth in Article 16, a written notice of
intention to appeal from ENGINEER’s written
decision is delivered by OWNER or CONTRACTOR
to the other and to ENGINEER within 30 days after
the date of such decision, and a formal proceeding is
instituted by. the appealing party in a forum of
competent jurisdiction within 60 days after the date of
such decision or within 60 days after Substantial
Completion, whichever is later (unless otherwise
agreed in writing by OWNER and CONTRACTOR),
to exercise such rights or remedies as the appealing
party may have with respect to such Claim, dispute,
or other matter in accordance with applicable Laws
and Regulations.
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-31
SECTION 00700
GENERAL CONDITIONS
C. IfENGINEER does not render a formal decision
in writing within the time stated in paragraph 10.05.B, a
decision denying the Claim in its entirety shall be deemed
to have been issued 31 days after receipt of the last
submittal