Okaloosa County BOCC — April 7, 2015 — Final Payment on New Jail Chiller — agenda request
Final Payment on New Jail Chiller — agenda request in the April 7, 2015 Okaloosa County BOCC meeting materials. Preserved county-portal original with machine-extracted reading text.
Preserved among the April 7, 2015 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1258). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used May 9, 2015; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Action Item Printout
Date
April 7, 2015
Publisher
Okaloosa County Board of County Commissioners
Where to find it
2
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Final Payment on New Jail Chiller — agenda request — extracted reading text
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
Final Payment on New Jail Chiller — agenda request — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: April 7, 2015
TO: Honorable Chairman and Members of the Board
FROM: Don Turner
SUBJECT: Final Payment on New Jail Chiller
DEPARTMENT: Facility Maintenance
BCC DISTRICT: 1
STATEMENT OF ISSUE: Requests BCC approval to Pay to WD Rogers Mechanical
Contractors, Inc. the Final Invoice Amount of $30,227.00 for the New Chiller at the County Jail.
BACKGROUND: In Fiscal Year 2014, the main chiller at the county jail was over 20 years old.
It had been overhauled multiple times and had suffered multiple major components failures over
the years. It had exceeded its predicted useful life expectancy. The chiller's replacement first
appeared on Facilities Maintenance's 5-Year CIP in FY '07. Replacement of the chiller was
approved by the Board and funded in FY '14.
By the time the purchasing process had completed and the new chiller fabricated, it was late in
the summer of 2014. Taking the A/C off line for several days at the jail during the hottest time
of the year was not a viable option. WD Rogers proposed to install the new chiller alongside the
existing chiller in a temporary location, so that it could be used as a back-up to the existing
chiller. Their proposal including doing this work immediately and then planning an appropriate
time after the first of the year, when the weather was much cooler, to remove to existing chiller
and relocate the new chiller to its permanent location. WD Rogers agreed to the modified work
plan at the same contract price.
This work plan was agreed to by Facilities Maintenance and phase 1 was completed in 2014. As
agreed, WD Rogers returned to the jail when the weather permitted and relocated the new chiller
to its permanent location. The work of the base contract has been completed and final payment
to WD Rogers Mechanical Contractors, Inc. is recommended by Facilities Maintenance.
OPTIONS: Approve Final Payment in the amount of $30,227.00 to WD Rodgers Mechanical
Contractors, Inc. for the New Chiller at the County Jail. Authorize Transferring $30,227.00 from
301 Capital Outlay Fund -3110 Capital Outlay Projects -562190 Account to 301 Capital Outlay
Fund - 3120 Capital Outlay Project Projects - Public Safety - 562245 Account Jail- Replace
Chiller to be used to pay the Final Payment to WD Rogers Mechanical Contractors, Inc.; or,
Authorize Transferring $30,227.00 from General Fund Reserves or another funding source that
the Board Deems Suitable to be used to Pay the Final Payment to WD Rogers Mechanical
Contractors, Inc.
RECOMMENDATIONS: Approve payment to WD Rodgers Mechanical Contractors, Inc. for
the final invoice amount of $30,227.00 for the new chiller at the County Jail and to transfer
$30,227.00 from 301-3110-562190 to 301-3120-562245, or from such other funding source as
the Board deems appropriate.
RECOMMENDED BY:
APPROVED BY:
John Hofstad, County Administrator
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — April 7, 2015 — Final Payment on New Jail Chiller — agenda request.” April 7, 2015. Action Item Printout. Crypt of Echoes evidence ID LED-2026-92bfb64b9bd44213894b549a38c0f5f6. http://127.0.0.1:58097/evidence/LED-2026-92bfb64b9bd44213894b549a38c0f5f6. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, Final Payment on New Jail Chiller — agenda request, meeting materials for April 7, 2015. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=30&ID=13292&MeetingID=1258
Preserved county public-record source. Third-party attachments may retain their original rights.