RESOLUTION 2011 -10
A RESOLUTION OF THE CITY OF FORT WALTON BEACH, FLORIDA,
CERTIFYING THAT THE CITY MEETS THE FISCAL HARDSHIP CRITERIA OF
SECTION 218. 075 FLORIDA STATUTES, AND QUALIFIES FOR A REDUCTION
OR WAIVER OF PERMIT PROCESSING FEES FOR THE FLORIDA DEPARTMENT
OF ENVIRONMENTAL PROTECTION ( FDEP) AND /OR THE NORTHWEST
FLORIDA WATER MANAGEMENT DISTRICT (NWFWMD) FOR 2010/ 2011.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FORT
WALTON BEACH, FLORIDA AS FOLLOWS:
Section 1. Authority & Intent
Pursuant to section 218. 075, Florida Statutes, the City may qualify for a reduction
or waiver of permit processing fees payable to the Florida Department of Environmental
Protection or the Northwest Florida Water Management District. To qualify for the
reduction or waiver of permit processing fees for the 2010 -11 fiscal year, the City must
certify that the cost of the permit processing fee is a fiscal hardship due to one of the
enumerated factors in section 218. 075, Florida Statutes.
Section 2. Certification
The cost of permit processing fees is a fiscal hardship for the City pursuant to
section 218. 075( 2), Florida Statutes Section 218. 075( 2), Florida Statutes, specifies that a
fiscal hardship may be proven if the " percentage of assessed property value that is
exempt from ad valorem taxation is higher than the statewide average for the current
fiscal year." The City certifies that the cost of permit processing fees is a fiscal hardship
because the percentage of assessed property value that is exempt from ad valorem
taxation is higher than the statewide average for the current fiscal year. The facts that
support that conclusion are that according to data from the Florida Department of
Revenue, Office of Property Tax Oversight (Jan 2011):
a. The total assessed value of ad valorem property statewide was $ 1, 781, 700, 000
X1, 000).
b. Of the above amount, exempt properties including homestead exemptions and
those classified as " other ", is $436, 610,000 ( x1, 000).
c. Therefore, from the above data, the percentage of assessed property that is exempt
statewide is 24. 51 %.
d. The City of Fort Walton Beach had a total assessed value of ad valorem property
in 2010 of $1, 679, 673 ( x1, 000).
e. In 2010, the City' s total amount of exempt ad valorem properties was
469, 933, 333.
f. The percentage of exempt properties in the City of Fort Walton Beach was
28. 00 %.
g. Fort Walton Beach' s 28. 00% of exempt properties exceeds the statewide average
of 24. 51% and therefore the City is eligible for a fiscal hardship exemption under
Criteria 2 above.
Section 3. Effective Date
This Resolution shall take effect immediately upon approval by City Council and
signature of the Mayor.
Adopted ` , 2011
Mike Anderson, Mayor
Attest: Approved for form and legal
sufficiency:
Helen Spencer, CityFClerk Hayes ykes, City orne
pa,
2
TASK ORDER NO. 2
for
CONTRACT FOR GENERAL CONSULTING SERVICES
This task order is executed by the parties on the dates signed, shall become effective
as of the date signed by the last party, and incorporates by reference the entire Contract for
General Consulting Services between the City of Fort Walton Beach, a Florida municipality,
with its principal place of business at 107 Miracle Strip Pkwy, Fort Walton Beach, Florida,
City") and the Consultant:
CH2M HILL
Corporation
25 W. Cedar Street, Suite 560
Pensacola, ]FL 32502
Business Address
850- 438- 2740
Telephone Number
850- 438- 9385
Fax Number
Section 1. Scope of Work
Introduction
The City is considering implementing a system-wide sanitary sewer evaluation study (SSES)
and rehabilitation program to identify and reduce infiltration and inflow (I/ I) into their
sewer collection system. Prior to implementing a system-wide comprehensive I/ I program,
the City desires to conduct a pilot-level study to evaluate the effectiveness at identifying and
reducing I/ I. The City has selected two sanitary sewer collection basins to conduct this pilot
study, Lift Station 5 sewer collection basin and Lift Stations 10 & 11 sewer collection basin.
Scope of Services
CH2M HILL will assist the City with implementing a pilot study for the City' s sewer system
by performing a SSES on the selected basins. The scope of services will include performing
field services, evaluating results of the collected field data, and developing
recommendations for
addressing system deficiencies. This study will assist the City in
determining the viability of conducting a system-wide sanitary sewer evaluation program
and removal of excessive wet-weather induced I/ 1. The scope of services will consist of four
main tasks.
Task 1 - Project Development and Kick-off
Task 2- Field Inspection Services
Task 3 - Field Data Analysis and Model
Task 4- SSES Report
PNSITASK ORDER 2- SSES PILOT STUDY FINAL. DOCX 1
A detailed description of each task is provided below.
Task 1 — Project Development, Management and Kick-off
Subtask 1. 1 — Project Planning and Progress Reports
CH2M HILL will prepare a detailed work plan for the study effort. The detailed work plan
and schedule will be presented to the City at the Project Chartering Workshop and will form
the basis for project delivery. The work plan and schedule will be updated as needed to
reflect changes in scope or schedule. This subtask also includes preparation of monthly
progress summary for submission to the City and coordination of project activities.
Subtask 1. 2— Chartering Workshop (Workshop# 1)
A project chartering workshop will be held between the City and CH2M HILL. The purpose
of this workshop will be to confirm the City' s goals and objectives for the project, identify
roles and responsibilities and communication protocols for project team members, and
discuss the overall project work plan and schedule. Up to three CH2M HILL staff will
attend
Workshop # 1 with remaining team members participating via conference call.
At the Chartering Workshop, CH2M HILL and the City will conduct a site visit at the
selected basins and review components of the field and desktop evaluations.
Deliverables:
Two (2) hard copies of work plan and schedule
Workshop agenda (electronic delivery)
Meeting summary of Project Chartering Workshop ( electronic delivery)
Task 2 —Field Inspection Services
The purpose of this task is to develop the framework for the SSES field study, develop and
provide field inspection forms and assist/ train the City staff in conducting the field work,
reconnaissance, and data collection for the study.
Subtask 2. 1 — Field Inspection and Data Management Plan
CH2M HILL will develop of a field inspection and data management plan for use on this
project. The plan will be designed to identify and catalog potential causes of I/ I into the
sewer collection system. The field inspection services will be conducted utilizing a series of
study components divided into two phases to provide preliminary, cost- efficient data
results on initial causes and then obtain additional data on areas identified for further study.
Details about the components of the field inspection phases are summarized below.
Phase I Field Inspection Components
Phase I inspections involve low cost procedures to gather initial data about potential causes
or sources of I/ I. Upon the conclusion of Phase I inspections, CH2M HILL will prepare a
technical memorandum summarizing the results and providing a recommendation for
which areas/ line segments need additional inspection. CH2M HILL' s PM will meet with
the City to review the TM and confirm the Phase II Field Inspection Plan.
PNSITASK ORDER 2- SSES PILOT STUDY FINAL. DOCX 2
Smoke Testing
The smoke testing program will force non-toxic smoke into the sewer pipes with a high-
volume mechanical blower and observe the areas from which the smoke appears. While the
blower is running, CH2M HILL will travel throughout the area documenting,
photographing, and getting physical measurements of the observed defects in a line
segment-by- segment process. The white smoke should appear from sources of private-
sector inflow (i.e. downspouts and area or yard drains on the roofs of buildings) and public-
sector inflow (i.e. defects in the collection system such as directly and indirectly connected
storm sewer inlets and vented manhole covers that are subject to ponding).
Public notices will be prepared by CH2M HILL to inform the area residents of the smoke
testing activities. Individual notices will be delivered by the City to businesses and
institutions. Residential notification will be performed by the City through direct mailings
and media releases. In addition, additional notifications such as newspaper notices and use
of the City' s website to keep residents informed of the smoke testing activities are
recommended. Observed sources of I/ I for both public- and private-sectors will be recorded
on field inspection forms and then compiled in an Access database which could then be
migrated by the City into the City' s Geographic Information System( GIS) once it is
developed.
This task order is based on 35, 000 linear feet of sewer lines being tested.
Manhole Inspection with Visual Pipe Lamping
Visible manholes within the selected basins will be inspected from the street surface. Non-
visible manholes will not noted on the field forms and provided to the City for further
investigation and location. Each manhole will be inspected to document the condition of
the manhole casting, barrel sections, base, and pipe connections. Manhole center invert
elevations will also be measured in each manhole. For manholes with multiple pipes
entering or where there is an apparent elevation difference between incoming and outgoing
pipes, a measurement from the rim to the pipe invert will be made without entering the
manhole unless it is felt that such measurement would be inaccurate due to angling of the
level rod or other reason. Selected internal measurements will be performed if necessary to
obtain an accurate invert elevation or pipe diameter. A digital photograph of the lid and
interior of the structure will be taken. In addition, a pole-mounted camera/ recorder, similar
to a QuickView®manufactured by Envirosight®,will be utilized to take pictures and record
views from the manhole of the connecting pipes. All observations of manhole condition and
leakage will be recorded on field inspection forms and then compiled in an Access database
which could then be migrated by the City into the City' s Geographic Information System
GIS) once it is developed.
This task order is based on 150 manholes being inspected.
Flow Monitoring
Flow monitors will be installed and monitored at key locations identified by CH2M HILL
and City staff. Flow monitoring duration will depend on rain events, but is anticipated to
be conducted over a 60- day period to establish sufficient data. Monitoring period will need
to capture at least six ( 6) rain events with at least 6- inch of total rainfall and at least one rain
event approaching a one-year typical event. Weekly field checks and data downloads will
be performed during the