being extended to the following dates:
67 – Marler Park Boat Parking & Exhibit Pad CEI – 9/30/14
Packet Pg. 241
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: 12th Avenue Sidewalk CEI Services Final Payment
DEPARTMENT: Public Works
BCC DISTRICT: Two
STATEMENT OF ISSUE: On January 6, 2014 Okaloosa County entered into a contract with
Genesis CEI Services, LLC to perform Construction Engineering & Inspection services for the
12th Avenue Sidewalk LAP project in Shalimar. The negotiated contract was a Not-To-Exceed
amount of $17,010.26. The project was substantially complete as of April 24, 2014 and the
Contractor is in the process of submitting documentation to close out the project.
BACKGROUND AND ANALYSIS: The 12th Ave. Sidewalk addition project consisted of
adding pedestrian sidewalk along the south side of 12th Avenue from State Road 85 (Eglin
Parkway) to 12th Street in Shalimar, FL. The project was funded via LAP Agreement from the
Florida Department of Transportation. There was no funding match required by Okaloosa
County with this Agreement. Genesis CEI Services, LLC has requested final payment be made
for services performed. The final invoice amount is $4,189.27 and a complete summary can be
found in the table below.
12th Ave. Sidewalk CEI Invoicing Summary (NTE $17,010.26)
Date Invoice # Period Amount Total To-Date
1/26/14 G001 1/06/14 - 1/26/14 $3,187.67 $3,187.67
3/26/14 G002 1/27/14 - 3/02/14 $5,272.24 $8,459.91
4/11/14 G003 3/03/14 - 3/30/14 $4,361.08 $12,820.99
4/27/14 G004 3/31/14 - 4/27/14 $4,189.27 $17,010.26
OPTIONS: Approve/Disapprove the request for final payment to Genesis CEI Services, LLC
in the amount of $4,189.27 for the 12th Avenue Sidewalk LAP project.
RECOMMENDATION: Approve the request for final payment to Genesis CEI Services, LLC
in the amount of $4,189.27 for the 12th Avenue Sidewalk LAP project.
.
RECOMMENDED BY:
Packet Pg. 242
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 243
Packet Pg. 244
Packet Pg. 245
Packet Pg. 246
Packet Pg. 247
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: Ed Schroeder
SUBJECT: Public Hearing Request - TDT Ordinance Amendment
DEPARTMENT: Tourist Development Department
BCC DISTRICT:
STATEMENT OF ISSUE: Request to schedule a public hearing on July 15, 2014 regarding
proposed amendment of the tourist development plan.
BACKGROUND: Pursuant to F.S. 125.0104(4)(c), the County has previously approved and
adopted a tourist development ordinance setting forth the plan for tourist development. In order
to substantially amend the plan of tourist development, F.S. 125.0104(4)(d) requires an
ordinance enacted by an affirmative vote of a majority plus one additional member of the Board.
The primary purpose of this amendment is to update the plan to identify funding for aquariums
and museums as an appropriate use of tourist development tax revenues, and to update revenue
projections under each percentage point.
The TDC recommended approval of this amendment to the tourist development plan ordinance
at its meeting on June 26.
OPTIONS: Approve or Disapprove
RECOMMENDATION: Approve public hearing to convene on or after 9:00 am on July 15,
2014 to receive comments regarding proposed amendments to the tourist development plan.
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 248
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: Ed Schroeder
SUBJECT: ECCC Floor Plan & Capacities Brochure Update – payment approval
DEPARTMENT: Tourist Development Department
BCC DISTRICT:
STATEMENT OF ISSUE: Request approval of payment in the amount of $760 to Life’s A
Beach for design work to incorporate Bayview Plaza on the Floor Plan & Capacities brochure for
the ECCC sales kit.
BACKGROUND: At the time services were engaged for the design work, staff thought payment
would be made via credit card due to the dollar amount of the purchase. After services were
performed and the invoice was received, the vendor advised he does not accept credit card
payments.
At this point, there is no method to pay the vendor in accordance with County purchasing policy
now that the work has been performed without a prior arrangement for payment. Board approval
is requested to pay the vendor.
OPTIONS: Approve or Disapprove
RECOMMENDATION: Approve payment in the amount of $760 to Life’s A Beach for design
work to incorporate Bayview Plaza on the Floor Plan & Capacities brochure for the ECCC sales
kit.
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 249
Packet Pg. 250
Packet Pg. 251
Packet Pg. 252
Packet Pg. 253
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Willow Creek Phase 2A Subdivision
DEPARTMENT: Public Works
BCC DISTRICT: one
STATEMENT OF ISSUE: The developer is requesting an extension of the warranty period and
acceptance of the maintenance bond (new Irrevocable Standby Letter of credit No. 201101 from
Summit Bank N. A.) for Willow Creek Plantation Subdivision Phase 2A.
BACKGROUND: Willow Creek Plantation Subdivision Phase 2A was accepted by the Board of
County Commissioners to enter into the 18-month warranty period on September 4, 2012. The
Irrevocable Standby Letter of Credit No.201101 issued by Summit Bank, N. A. In the amount of
Two Hundred Seven Thousand Five Hundred Seventy Three and 30/100 Dollars ($207,573.30)
was provided by the developer to serve as maintenance bond. The said letter of credit expires on
July 20, 2014, but project deficiencies have not been rectified by the developer.
With the imminent expiration of the Letter of Credit on file the developer is requesting the Board
of County Commissioners to approve an extension of the warranty period and acceptance of a
new letter of credit. The new letter of credit is also from Summit Bank, N. A. (No. 201101) with
an expiration date of July 20, 2015. All remediation work will be performed by the developer
during the extended warranty period.
OPTIONS: Approve/Disapprove the developer's request to extend the warranty period and
accept Letter of Credit No. 201101 from Summit Bank, N. A. In the amount of ($207,573.30)
which expires on July 20, 2015, for Willow Creek Plantation Subdivision Phase 2A.
RECOMMENDATIONS: Approve the developer's request to extend the warranty period and
accept Letter of Credit No. 200101 from Summit Bank, N. A. In the amount of ($207,573.30)
which expires on July 20, 2015, for Willow Creek Plantation Subdivision Phase 2A.
RECOMMENDED BY:
Packet Pg. 254
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 255
Packet Pg. 256
Packet Pg. 257
Packet Pg. 258
Packet Pg. 259
Packet Pg. 260
Packet Pg. 261
Packet Pg. 262
Packet Pg. 263
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Authorization to Advertise Request for Qualifications for PJ Adams
Parkway - Phase 1
DEPARTMENT: Public Works
BCC DISTRICT: 3
STATEMENT OF ISSUE: Request authorization from the Board of County Commissioners to
advertise to receive letters of interest from qualified engineering firms to perform the Phase 1
Widening Design (from SR 85 to I-10) and Right of Way acquisition assistance (from SR 85 to
Ashley Drive) Project.
BACKGROUND: Okaloosa County and the Florida Department of Transportation (FDOT)
entered into a Transportation Regional Incentive Program (TRIP) grant on April 24th to develop
the widening plans for PJ Adams Parkway from SR 85 to I-10. Additionally, right of way
acquisition is part of the grant for the four lane section from SR 85 to Ashley Drive. In total, the
full project (design and right of way acquisition) is estimated to be $4.4 million.
In order to complete the design and determine the exact right of way needs, it is necessary to
obtain professional services from a qualified firm. In order to comply with the County
Purchasing Policy, a request for qualifications advertisement has been prepared. Interested firms
are being requested to submit Letters of Interest to perform the necessary work.
Received letters will be evaluated and scored based on the guidelines in the RFQ by a selection
committee. The recommended review committee includes:
Nathan Boyles, District 3 Commissioner
Jason Autrey, P.E., County Engineer
Eric Broome, P.E., Design Engineer
Rob VandenBroeck, Operations Manager
Jeremy Williams, Water & Sewer Senior Right-of-Way Agent
Rankings from the selection committee review will be presented to the Board of County
Commissioners in the form of a recommendation to award.
OPTIONS: Approve/Disapprove advertisement of the Request for Qualifications for the PJ
Adams Parkway Phase 1 Widening Design and Right of Way Acquisition Assistance project and
approve the proposal review committee.
RECOMMENDATIONS: Approve advertisement of the Request for Qualifications for the PJ
Adams Parkway Phase 1 Widening Design and Right of Way Acquisition Assistance project and
approve the proposal review committee.
Packet Pg. 264
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 265
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 1, 2014
TO: Honorable Chairman and Members of the Board
FROM: Elliot Kampert
SUBJECT: Setting Public Hearing for Fixed Route Transit Discontinuance
DEPARTMENT: Growth Management
BCC DISTRICT: All
STATEMENT OF ISSUE: Set public hearing for discontinuance of Transit Routes 1, 2, 3, 4,
5, 14, 20, 30, 32, and 33.
BACKGROUND: Due to a projected budgetary shortfall, it is no longer feasible to operate the
fixed route system without substantially increasing local funding. The Board of County
Commissioners has requested assistance from the local municipalities, but as of this writing there
is no commitment. As provided by the Okaloosa County Public Transit Fare and Route
Modification Policy, the County must hold a public hearing to hear comments on route changes
prior to implementation. In