CITY COUNCIL MEETING
June 30, 2005
a
Consent Agenda
Consideration of Award of Bid #05-122 Liza Jackson
Restroom Repairs to Whitfield Associates of Fort
Walton Beach, FL
(Parks and Recreation Director/Purchasing Director)
Council Action
1st
2nd
Vote:
a
Agenda Item Number: CA -2
CITY OF FORT WALTON BEACH
MEMORANDUM
Date: June 21, 2005
To: Joyce Shanahan, City Manager
From: Gene Peters, Parks & Recreation Director
SUBJECT: REQUEST TO AWARD BID #05-122 REPAIR/RENOVATION OF
TWO RESTROOM FACILITIES AT LIZA JACKSON PARK
(HURRICANE IVAN)
REQUEST
Pursuant to Chapter 2, Section 2-266, Purchasing Policies and Procedures, Fort Walton Beach
Code of Ordinances, request authorization to award Bid #05-122, Liza Jackson Park Restroom
Repairs, to the lowest responsive, responsible bidder, Whitfield Associates of Fort Walton Beach
Florida, in the amount of $78,775, for damages resulting from Hurricane Ivan.
DISCUSSION
At their March 22, 2005 meeting, Council rejected the sole bid received from Champion
Construction, in the amount of $103,000, and directed staff to re-bid the Liza Jackson Park
Restroom renovations.
The Purchasing Department solicited bids from sixteen (16) construction firms with three
(3) responsive bids submitted with the lowest responsive, responsible bid received from
Whitfield Associates of Fort Walton Beach, in the amount of $78,775.
Damage to both restroom facilities included the replacement of six (6) exterior doors, all interior
partitions, all interior electrical & plumbing elements and all interior restroom components. One
interior block wall will also be replaced in the west side restroom. Funding is provided in
Hurricane account # 001-1500-519-4939.
RECOMMENDATIONS
1. Request authorization to award Bid 405-122 for the repairs and renovations to both restroom
facilities at Liza Jackson Park to lowest responsive, responsible bidder, Whitfield Associates
of Fort Walton Beach in the amount of $78,775.
2. Request authorization for the City Manager to amend the contract, in an amount not to exceed
$12,000, for miscellaneous repairs and supplies as needed.
LA#HZ
—_ o_o ror nr SST SS Se a SS SSS
a — i ——— i — deen
DEPARTMENT: Parks & Recreation
DIVISION: Administration
FUND: General Fund
ACCOUNT #001-1500-519-4939
ACCT. DESCRIPTION: Hurricane Ivan
FY BUDGET: N/A
AMOUNT BUDGETED: N/A
GRANT FUNDS: YES NO_XX__ AMOUNT
FUND TRANSFER: YES NO xX AMOUNT
FROM ACCT: N/A
11. TO ACCT: N/A
12. REASON FUNDS AVAILABEL FOR TRANSFER: N/A
13. PRICE ANALYSIS: ATTACHED X ADD’L MAT FDR NONE
OY Ora oO & WN FE
a
Oo
.
14. Description: Labor & materials to renovate two restrooms at
Liza Jackson Park
15. SUPPLEMENTAL MATERIAL: ATTACHED X_ ADD‘L MAT FDR
16. # BID INVITATIONS SENT:16
17. # BIDS RECEIVED: 3
18. # RESPONSIVE BIDS:3
19. RECOMMENDED VENDOR: Whitfield Associates of Fort Walton Bch
20. BID AWARD AMOUNT: $78,775
21. COMMENTS: N/A
22. ESTIMATED QUANTITY TO BE PURCHASED: N/A
23. ESTIMATED PURCHASE AMOUNT: $78,775
24. BID TABULATION ATTACHED: YES X_ NO ADD’L MAT FDR___
25. TERM OF CONTRACT: 60 days
26. BID PRICE VALID FOR TERM OF CONTRACT: YES _X_ NO
27. WARRANTY PERIOD: One year Labor & Materials
28. DELIVERY TIME: 60 days
29. STATE CONTRACT: YES NO X
30. CONTRACT #: N/A
31. CO-OP PURCHASE: YES NOX
32. AGENCY: N/A
33. EXPECTED LIFE OF ITEM: N/A
34, ITEM DEMO’D: YES NO_N/A
35. REFERENCES CHECKED: YES_X_ NO N/A
36. CONTRACT: ATTACHED ADD’L MAT FDR N/A_X__
37. CONTRACT APPROVED FOR LEGAL SUFFICIENCY: YES NO X
38. CURRENT VENDOR:N/A
> .
Prepared and Submitted by: C2. Ct G-Zl-o +
Gene Peters Date
Parks & Recreation Director
Reviewed and Concur: . Docpe Cir, 623-06
wure e ‘Shanahan Date
y Manager
Comments:
City of Fort Walton Beach
MEMORANDUM
DATE: June 22, 2005
TO: Gene Peters
Parks & Recreation Director
FROM: Michael C. Tatum LS
Purchasing Director
SUBJECT: Repair / Restore Two (2) Restroom Facilities at Liza Jackson Park
Bid #05-122
The referenced bid tabulation is forwarded for your review. Please take the necessary
action to prepare the Memorandum for Approval by the City Manager and Council. The
bid file is available for review at the Purchasing Department.
The following information is furnished for those items applicable to Purchasing on the
Request To Award Bid Memorandum:
ITEM NO./DESCRIPTION RESPONSE
16. Number of Bids Solicited 15
17. Number of Bids Received 3
18. Number of Responsive Bids 3
24. Tabulation Attached Yes
30. State Contract No
MCT/mhj
BID TABULATION
Repair/Restore Two (2) Restroom Facilities at Liza Jackson Park June 21, 2005
Bid #05-122
Crestview Carpentry Whitfield Assoc. Construction | Chandler Construction Co.
Crestview, FL Fort Walton Beach, FL Freeport, FL
Item
No. | Qty./Unit |Description Total Total Total
1 1|Job |Labor, materials and supervision
to repair/restore two restroom /caris00
facilities at Liza Jackson Park: $88,650.00 $78,775.00 $133,790.00
Total Bid: $88,650.00 \. $78,775.00 / $133,790.00
i ae
Performance Period: 60 Days 60 Days 90 Days
Warranty on Labor: 3 Years 1 Year 1 Year
Warranty on Materials: Mfg. Standard Mfg. Standard 1 Year
Bid Expires: 60 Days 60 Days 60 Days
Payment Terms Net Net Net 10
References: Yes Yes Yes
Drug Free: Yes Yes Yes
State Contract: No No No
CITY COUNCIL MEETING
June 14, 2005
a
June 30, 2005
Consideration Award of Contract for Additional Housing
Rehabilitation Work at 118 Carson Drive SE to
Ponderosa Builders, Inc.
(CDS Director/Purchasing Director)
Council Action
1st
2nd
Vote:
a
Agenda Item Number: | CA-3
CITY OF FORT WALTON BEACH, FLORIDA
MEMORANDUM
DATE: June 15, 2005
TO: Joyce Shanahan, City Manager
THROUGH: Peggy Fowler, Planner 1Q¢
FROM: Missy McKim, CDS Direct
SUBJECT: Residential Rehabilitation Change Order Request for 118 Carson Drive SE
BACKGROUND:
On February 22, 2005, the City Council awarded a bid of $12,696 to Ponderosa Builders, Inc., to
rehabilitate a single-family residence at 118 Carson Drive SE. The contractor’s bid price was
based on a work write-up prepared by A+ Home Inspection who is under contract as the City’s
housing rehabilitation specialist. On April 22, 2005, Ponderosa Builders, Inc. submitted a
change order for additional expenses necessary to complete one of the work items. The City’s
building inspector concurred with Ponderosa Builders that the additional work needed to be done
in order to complete the work item.
The City’s Rehabilitation Policies and Procedures Manual allows for the City Manager to
approve change orders that cost less than 10% of the total rehabilitation contract cost. The
change order requested on April 22 in the amount of $1,265.00 was approved by the City
Manager.
DISCUSSION:
During the course of finalizing the rehabilitation in May 2005, Ponderosa Builders, Inc.,
encountered additional problems that were unforeseen when the original write-up was conducted
in August 2004 and in the construction work to date. On May 23, 2005, the contractor submitted
an additional “Rehabilitation Specification Work Write-up” to describe the additional work items
they have completed (because it was necessary for work underway) or would need to complete to
finish the required work in the proper manner.
Ponderosa Builders, Inc. has submitted a quote of $3,185.00 to complete this work item as
described in the additional Rehabilitation Specification Work Write-Up.
The current cost of rehabilitating the property is $13,961.00 (adding the figures for the original
bid amount of $12,696.00 and the approved change order for $1,265.00). The additional cost to
complete the project properly is $3,185.00, which is in line with recent quotes and estimates
submitted for other rehab projects. This would bring the total cost of the rehabilitation to
$20,331.00, which is under the maximum amount of $30,000 allowed for a residential rehab in
the CRA.
LY Bet?
The City’s Rehabilitation Policies and Procedures Manual allows for the City Manager to
approve change orders that cost less than 10% of the total rehabilitation contract cost. An
amount greater than10% must be approved by City Council. If approved, sufficient funds are
available from account #109-2000-552-6997.
RECOMMENDATION:
Staff recommends that City Council approve the waiver of the formal bid process and award the
additional funds to Ponderosa Builders, Inc. to complete the project properly.
1 DEPARTMENT: Community Development Services
2. DIVISION: Planning & Zoning
3. FUND: CRA Special Revenue Fund
4 ACCOUNT #: 109-5068-552-6997
5 ACCT. DESCRIPTION: CIP #5068—-Residential Improvements
Program
6. FY BUDGET: 2004/2005
7. AMOUNT BUDGETED: $75,000 (2004/2005)
8. GRANT FUNDS: YES NO X AMOUNT
9. FUND TRANSFER: YES NO xX AMOUNT
10. FROM ACCT: N/A
11. TO ACCT: N/A
12. REASON FUNDS AVAILABEL FOR TRANSFER: N/A
13. PRICE ANALYSIS: ATTACHED
14. DESCRIPTION OF BID ITEM: Rehabilitation of the residence
at 118 Carson Drive SE.
15. SUPPLEMENTAL MATERIAL: ATTACHED
16. # QUOTES SENT: 1
17. # QUOTES RECEIVED: 1
18. # RESPONSIVE QUOTES: 1
19. RECOMMENDED VENDOR: Ponderosa Builders Inc.
20. BID AWARD AMOUNT: Not to exceed $3,185.00
21. COMMENTS: --
22. ESTIMATED QUANTITY TO BE PURCHASED: N/A
23. ESTIMATED PURCHASE AMOUNT: N/A
24. BID TABULATION ATTACHED: YES NO_X
25. TERM OF CONTRACT: Completion of services.
26. BID PRICE VALID FOR TERM OF CONTRACT: YES xX NO
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
WARRANTY PERIOD: One year—labor; materials per
manufacturer’s warranty.
DELIVERY TIME: 20 days
STATE CONTRACT: YES NO xX
CONTRACT #: N/A
CO-OP PURCHASE: YES NO X
AGENCY: N/A
EXPECTED LIFE OF ITEM: N/A
ITEM DEMO’D: N/A
REFERENCES CHECKED: YES X_ NO N/A___
CONTRACT: N/A
CONTRACT APPROVED FOR LEGAL SUFFICIENCY: N/A
CURRENT VENDOR: N/A
CURRENT PRICE: N/A
REPORT PREPARED BY: <> wa C VEVLEX
Pegg Fofler’ Date
REVIEWED & SUBMITTED BY:
Missy McKim Date
CDS Director
aa
REVIEWED AND CONCUR: oun An dh Uo/ 227 OD,
ycR Shanahan Date”
ty Manager
@5/@6/2085 12:15 858-2434848 PONDEROSA BLDRS PAGE
PONDEROSA BUILDERS, INC.
648 LOVEJOY ROAD
P. O. BOX 987
FT. WALTON BEACH, FL, 32549
(850) 243-7696 FAX (850) 243-4848
FLORIDA STATE LICENSE CB C058636
May 23, 2005
June 3, 2005
City of Ft. Walton Beach
FAX 833-9926
RE: John Baker
118 Carson Drive
Ft, Walton Beach, Fl. 32548
To whom it may concern:
Please find enclosed an additional Rehabilitation Specification Work Write-up based
upon items that were unforeseen when the first walk thru was done.
A plaster wall in the dining room area was scheduled for repair. Additional work is
needed on the walls in the living room, kitchen, laundry and hall. These areas were
covered up with contents. Unable to see all of the damage until furniture was moved and
the ceilings repaired.
Bid to repair plaster walls and paint walls in living room, dining room, hall, kitchen, and
laundry......... $ 1,800.00 (this is only if the plaster does not come off when we are
rolling on the new paint as the plaster appears to be flaking and loose in numerous areas)
The dryer vent was to be vented through the laundry room wall and a piece of glass
replaced in the window where the dryer vent is now vented. The house has a stucco finish
on it and we cannot determine if the block behind the stucco in this area is solid or
hollow. Either way there may be a problem. Alternate repairs may consist of the
following:
Cut hole in wood floor. Attach schedule 40 pipe to back of dryer and run piping under the
Continued page 2
@2
45/66/2085 12:15 858-2434848 PONDEROSA BLDRS PAGE 43
PONDEROSA BUILDERS, INC.
Baker renovations
Page 2 of 2
house between floor joists and out back side of house near doorway. (solid block tn other
areas) Bid price ..... $250.00
Specifications called for correcting over pressurization vent pipe from the water heater
and to install a drain pan under the water heater. The existing water heater is 10 years old.
When we went to remove & reinstall the water heater, the plumber found out that the
electrical