Okaloosa County BOCC — December 1, 2015 — 12) CDM Final Negotiated Cost - APWRF Expan — reading text
Part 1 of 2. These parts divide the reading text for browsing; they are not the source document's page numbers.
12) CDM Final Negotiated Cost - APWRF Expan — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
8381 Dix Ellis Trail, Suite 400
Jacksonville, Florida 32256
tel: 904 731-7109
October 7, 2015
Okaloosa County Purchasing Department
602-C North Pearl Street
Crestview, FL 32536
Subject: Cost Proposal for Expansion of the Arbennie Pritchett WRF
RFP Number WS01-15
Dear Okaloosa County Board of County Commissioners:
Thank you for meeting with us on October 5, 2015 in Fort Walton Beach to reach an agreement on
the budget for the expansion of the Arbennie Pritchett WRF. As discussed, CDM Smith agrees to
build the expansion for a lump sum amount of $12,480,704 (see attached cost estimate). As part of
our lump sum amount, we will develop and build a solution to the pressure and volume problem at
the headworks. CDM Smith commits up to $100,000 to solve that problem. Please refer to the
attached cost estimate for what is included in our proposal.
We look forward to continuing our relationship with Okaloosa County and TCG in building this
expansion successfully. Please do not hesitate to call us with questions.
Sincerely,
Patrick R. Victor, P.E., D.WRE
Vice President
CDM Smith Inc.
Attachment
CONFIDENTIAL Business Information
Okaloosa County, FL Page 1
Arbennie Pritchett WRF Expansion 10/5/2015 11:47 AM
Okaloosa County, FL
Arbennie Pritchett WRF Expansion
Design Build Cost Estimate - 4th REVISION (CLIENT ACCEPTED)
Project name APWRF Expansion
Okaloosa
FL
Estimator CMB
Labor rate table FL15 Labor Pensacola
Equipment rate table 00 15 Equip Rate BOF
Job size 5000000 gal
OPCC Type
Design Level
ENR 20 City CCI
Notes This breakdown is provided for informational purposes only.
Report format Sorted by 'Package/Area/Element'
'Package' summary
Allocate addons
E:\Estimating\01 PROJECTS\03 SER-ORL\FL\Okaloosa County\2015-04 Arbennie Pritchett WRF D-B\130 Timberline Estimates2015-05-009-CUTS-APWRF Exp CAG FINAL TO CLIENT.pee
CONFIDENTIAL Business Information
Okaloosa County, FL Page 2
Arbennie Pritchett WRF Expansion 10/5/2015 11:47 AM
Spreadsheet Level Labor Amount Material Amount Sub Amount Equip Amount Other Amount Total Amount
01-0001 General Conditions 632,420 13,700 73,850 68,507 250,905 1,039,382
01-0040 Survey Subcontract 118,500 118,500
02-2100 Sitework Subcontract 33,125 45,218 35,042 68,627 2,500 184,512
02-3700 Erosion and Sediment Control Subcontract 2,372 7,450 2,763 2,625 15,210
02-5002 Yard Piping Subcontract 53,359 113,668 43,504 53,323 70 263,924
03-0002 Concrete Subcontract 4,269 5,860 9,000 386 19,515
03-0030 Concrete Ready Mix Material 3,925 3,925
03-4200 Prestressed Concrete Subcontract 138,733 491,574 3,049,741 33,479 2,452 3,715,980
09-9730 Paint Pipe & Valves 15,162 3,676 9 18,847
11-0010 Equipment Installation 147,309 18,338 109,820 16,477 291,944
11-0020 Bolts & Anchors 1,891 32,663 1,238 35,792
11-1020 Vertical Turbine Pumps Line Shaft w/Can 147,979 147,979
11-1135 Centrifugal Pumps Self Priming 58,000 58,000
11-2003 Positive Displacement Blowers 53,000 53,000
11-2910 Mechanical Slide Gates 38,800 38,800
11-3040 Secondary Clairifier Round 253,640 2,000 255,640
11-3210 BNR Equipment 411,000 411,000
11-6550 Air Diffusers 35,000 35,000
11-7010 UV System Inchannel 243,000 243,000
13-0001 Building Subcontract 40,087 55,889 16,720 3,993 32 116,721
15-0010 Mechanical Self Perform 47,260 2,319 3,514 5 53,098
15-0040 Hangers & Supports 5,408 5,408
15-1010 Plug Valves 135,806 135,806
15-1030 Butterfly Valves 364 6,954 7,318
15-1050 Gate Valves 11,411 11,411
15-1120 Check Valves 26,848 26,848
15-1190 Ball Valves 50 376 426
15-1210 Special Purpose Valves 9,298 9,298
15-1410 Ductile Iron Pipe 145 562,474 562,618
15-2250 Stainless Steel Pipe 14,750 14,750
15-2275 Galvanized Steel Pipe 7,274 7,274
16-0002 Electrical Subcontract 339,743 838,321 80,324 27,975 26,135 1,312,498
16-0200 Generators 215,050 215,050
E:\Estimating\01 PROJECTS\03 SER-ORL\FL\Okaloosa County\2015-04 Arbennie Pritchett WRF D-B\130 Timberline Estimates2015-05-009-CUTS-APWRF Exp CAG FINAL TO CLIENT.pee
CONFIDENTIAL Business Information
Okaloosa County, FL