OCWS Budget BCC Presentation — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
-37,000+ water service connections
-34,000+ sewer service connections
-32,000+ water meters read each month
-30,000+ customer accounts/bills sent each month
-< 1.0% bad debt written off
-2,500,000,000+ gallons of potable water produced per year
from 21 wells and 19 tanks
-466+ miles of water mains, valves, and hydrants
-2,800,000,000+ gallons wastewater treated per year at 3
water reclamation facilities
-150 sewer pump stations
-448+ miles of sewer mains, valves, and manholes
Eglin Main Base Wastewater – 2 large pump stations and 7
miles of large force mains
Del Cerro II Well – new public water supply well in
unincorporated Crestview
Newcastle Area Water System Improvements – new mains,
meters, and hydrants serving 271 homes
Shoal River Buffer & Reservoir Land Acquisition – closed
on 961 acres and under contract for 641 acres
2015 Bond Issuance – saves $635K in annual debt service
Because of increased revenue & decreased expenses related
to partnerships & grants, we have a modest rate increase
plan, both current 5-year plan and upcoming plan.
New website with additional features
145
140
135
130
125
120
115
110
105
FY2008 FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015
FY2016 budget includes 4 additional positions:
-Utilities Financial Services Specialist
-Utilities Technician I
-Water Treatment Plant Operator or Apprentice
-WWTP Operator or Apprentice
Design-Build Team procurement is almost complete,
and work will begin in FY2016.
Increases storage, reliability,
and redundancy to service
area that contains Bob Sikes
Industrial Park.
Land acquisition is complete.
Design, permitting, and bid
process will occur in FY2016.
Construction should begin in
FY2017.
Pipeline substantially
complete.
Pump station construction
to occur in FY2016.
Divert East County Flow to Arbennie Pritchett WRF
(RePump Station & Transmission Main) - $5.2M
Meigs-Seminole Lift Station & Force Mains - $1.6M
Brooks Bridge Water Main Bore - $1.2M ($600K from
FDEP grant)
Residential Water Meter Replacement - $1.0M
First year of $12M project through FY2020
Sewer Rehabilitation (Manhole & Main Lining) - $500K
Marlowe Area Water System Improvements - $400K
Poquito Bayou Water & Force Main Bores - $265K
SCADA Replacements/Upgrades - $175K
Begin design on:
Lake Pippin Area Sanitary Sewer - $2M FDEP grant
Supplemental Reclaimed Water - $3M FDEP grant
FY14 FY15 FY16 FY15/FY16 Increase/
Code Category Approved Approved Proposed +/- Decrease
10 SALARIES & WAGES $5,309,219 $5,306,741 $5,405,037 $98,296 1.9%
20 BENEFITS $1,930,190 $1,960,415 $2,1485828 $188,413 9.6%
31 PROFESSIONAL SERVICES $447,000 $414,000 $425,500 $11,500 2.8%
32 ACCOUNTING & AUDITING $27,500 $27,500 $27,500 $0 0%
34 CONTRACT SERVICES $3,164,006 $3,325,867 $3,40,623 $76,756 2.3%
40 TRAVEL & PER DIEM $10,200 $7,200 $9,200 $2,000 27.8%
41 COMMUNICATIONS SERVICES $75,000 $70,000 $80,000 $10,000 14.3%
42 FREIGHT & POSTAGE $5,000 $5,500 $5,500 $0 0%
43 UTILITY SERVICES $1,690,000 $1,588,000 $1,956,000 $368,000 23.2%
44 RENTS & LEASES $385,408 $384,323 $391,789 $7,466 1.9%
RISK MANAGEMENT
45 ALLOCATION $450,560 $503,456 $503,456 $0 0%
46 REPAIR & MAINTENANCE $2,402,048 $2,049,088 $2,050,187 $1,099 0.1%
47