Okaloosa County BOCC — October 15, 2013 — OTA_Internal Coordination_Email Comments — reading text
Part 7 of 10. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 86-OTA_Internal Coordination_Email Comments.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
develop a SSTP based on testing criteria
outlined in the TSA PGDS Appendix D. The Draft SSTP will be based on the Airport’s
responses to a Site Planning Checklist to be completed >120 days in advance of ISAT. The Final
SSTP shall be delivered to the Airport between 60 and 30 days in advance of projected ISAT
start-up. The ILDT and TSA Acceptance Testing Contractor will conduct review meetings of
the Draft SSTP and Final SSTP per schedule in Table 1, Section 1.3 of this OTA prior to ISAT.
Any requests for deviation from the SSTP testing requirements must be delivered in writing
through a RFV to the TSA RDC and Acceptance Test Lead prior to this Final SSTP meeting for
review and response.
Page 22 of 39
HSTS04-13-H-CT1161
The TSA RDC and TSA Acceptance Test Lead will review/evaluate any requests for phased
testing (e.g. non-consecutive testing activities requiring multiple TSA Test Team trips). Such
requests must be supported by compelling justification and submitted in writing through a RFV
to the TSA RDC and TSA Acceptance Test Lead during the design process and well in advance
of SSTP development. Programming or mechanical changes made before ISAT (typically
during Contractor pre-testing) must be documented and provided to the TSA RDC and TSA
Acceptance Testing Contractor. Once a system enters TRR, no variances will be permitted to the
testing criteria.
1.3.3. Integrated Site Acceptance Testing (ISAT)
Scheduling and Coordination: Construction schedule including the ISAT start date(s) and
duration(s) shall be shared with the TSA Site Lead Contractor, TSA RDC, TSA Acceptance Test
Lead and TSA Acceptance Test Contractor through weekly and monthly meetings and reports
upon submission of the SSTP checklist to ensure all stakeholders maintain schedule awareness.
This schedule shall be distributed each time changes are made to the ISAT start date and/or
duration. Changes made to the schedule within two weeks of the planned ISAT start date may
relieve the TSA of the obligation to begin testing within three business days of the TRR. In this
situation, the ISAT start date could depend on TSA’s testing workload and resource allocation.
Test Results and Reports:
Testing results will be shared in hard copy format with the Airport from the RDC through the
local TSA Point of Contact. Test results will identify security, efficiency and safety concerns.
There are four (4) possible test outcomes:
e Meets PGDS Criteria — The system under test meets CBIS design and PGDS criteria.
e Minor Defects Found — The system under test had no security failures and performance
deficiencies would not impede system performance and staffing levels.
e Major Defects Found — The system under test had no security failures but performance
deficiencies would be detrimental to system performance and/or staffing levels.
e Fail—The system under test produced security failures and/or deficiencies that would be
excessively detrimental to system performance and staffing levels.
In the event of a failed ISAT result, TSA reserves the right to defer any subsequent re-tests for a
period of at least 30 days.
1.4 INTEGRATION SERVICES
1.4.1. BHS Support
The EDS OEM shall assist the COUNTY’s contractor to establish digital and serial
communication for the EDS units. Once communication between devices has been established,
the EDS OEM shall provide the following support and integration services.
« Assist the BHS contractor to obtain efficient EDS operation.
« Provide on-site Integration Engineer Support Services to facilitate the entire integration
effort with the BHS.
« Be available to support system testing and validation conducted by internal or external
organizations including the Integrated Site Acceptance Test (ISAT) and pre-ISAT Project
testing and throughout the planning phases including the issuance of the ISAT TRN and
TRR.
Page 23 of 39
HSTS04-13-H-CT1161
" During initial Live Operations Run-In, provide system performance documentation and
technical assistance as requested by TSA, TSA Acceptance Testing Contractor and/or the
ILDT.
1.4.2. Software and Hardware
Following SAT and throughout the integration effort, the EDS OEM shall install and test the
required software and hardware to allow for digital and serial communication between the EDS
and the BHS PLC if required. Functionality of the EDS BHS interface hardware and software
shall be verified by the EDS OEM at the interface box prior to working with the Airport BHS
contractor to ensure a proper operating PLC interface and to avoid delays.
15 SYSTEM NETWORKING
1.5.1 Network Infrastructure
The EDS OEM shall provide required patch cables and miscellaneous hardware to interface
between network patch panel and EDS OEM supplied networking components.
1.5.2 Network Services
The EDS OEM shall provide: training for TSA staff; coordination and support for TSA and
testing certification; and resources to conduct installation, testing, and initial operational support
for networking. No other network may interface with the networked airport screening solution.
The implemented assigned network for operation shall be an isolated, stand-alone network.
1.6. TRAINING
TSA will provide training for TSA screening staff on the operation of the EDS and ETD
equipment.
1.7. MAINTENANCE
Upon successful completion of SAT testing for each unit, TSA will maintain and repair the EDS
and ETD units throughout their lifecycles.
B. COUNTY’s RESPONSIBILITIES with regard to the Project are listed below in sections
2.1 to 2.5 listed below.
2.0 DESIGN
The COUNTY will undertake design of a baggage screening system in accordance with the TSA
PGDS to meet the needs of the Airport and TSA FSD. The COUNTY shall submit all
applicable design requirements to the TSA RDC for review and as further defined in Chapter 2
of PGDS Version 4.1. The COUNTY shall respond to TSA design review comments promptly
and in writing prior to the start of the next design phase for the CBIS Project.
2.1 EDS PLACEMENT
If applicable, the COUNTY shall ensure that the Project site will be ready to accommodate the
installation of the EDS and associated equipment. The COUNTY shall provide adequate
protection to the EDS machines and to the airport infrastructure during any and all EDS
movements. The COUNTY shall coordinate with the OEM to integrate all activities regarding
Page 24 of 39
HSTS04-13-H-CT1161
placement of EDS equipment. The COUNTY shall provide reasonable measures to protect the
EDS and ETD equipment from damage in the screening area.
2.1.1 Site Readiness and Storage
The COUNTY shall confirm site readiness to receive EDS units to the TSA Site Lead
Contractor no later than 10 business days prior to requested delivery date. Site readiness shall
address availability of temporary or permanent power; removal of obstacles to the rigging path;
and adequacy of physical environmental conditions within the delivery area that meet EDS OEM
standards for protecting the EDS units. The COUNTY shall provide secure storage for the EDS
units and any ancillary screening equipment if site conditions at the time of delivery do not
provide adequate protection. The COUNTY shall provide secure storage space for hardware
associated with EDS integration and multiplexing until it can be installed by EDS OEM
Integration Support Staff. Failure to meet these minimum requirements may result in
reallocation of equipment to other sites, thus affecting the airport’s overall project schedule.
2.1.2 Rigging Services
The COUNTY will be responsible for providing rigging path verification, ingress path, and/or
structural analysis. If required, the Airport will remove and replace any walls, windows, glass,
doors, or other physical barriers in support of rigging activities.
2.2 INSTALLATION SUPPORT
2.2.1 Power Requirements
The COUNTY will provide terminations to the EDS for electrical power. The COUNTY will be
responsible for providing all infrastructure power requirements including separate metering. If
applicable, the COUNTY will design and install all power requirements to terminal locations
within the Checked Baggage Resolution Areas and at EDS locations. The COUNTY will
provide cabling from terminations to EDS equipment. The COUNTY shall attest to the
availability of power supply to adequately support the EDS and associated equipment in
accordance with OEM specifications and be liable for damage to this equipment resulting from
intentional deviations to accepted power supply conditions.
2.2.2 Commissioning Services
The COUNTY will be responsible for obtaining all other infrastructures not mentioned in
Section 2.2.1 to support EDS operations and maintenance.
2.3. INTEGRATION SERVICES
The COUNTY shall ensure that the BHS Contractor coordinates with EDS OEM in support of
integration activities (e.g. installation and testing the required software and hardware to allow for
digital and serial communication between the EDS and the BHS PLC) as needed. Terminations
to the EDS for BHS PLC communication shall be performed by the COUNTY.
2.4 NETWORKING
2.4.1. Network Infrastructure
The COUNTY will design and install all communication conduit, fiber, etc. as required by the
EDS OEM’s design criteria for the EDS and EDS networking system, including but not limited
Page 25 of 39
HSTS04-13-H-CT1161
to connectivity of Checked Baggage Resolution Areas, TSA network control room, and BHS
Control Room as required. Exact parameters will be reviewed at Project start-up by TSA.
The COUNTY will provide cabling and network patch panels in TSA control rooms, ETD
search areas, and the TSA network room as determined by the network design conducted in
conjunction with the COUNTY. The EDS OEM shall provide required patch cables and
miscellaneous hardware to interface between network patch panel and EDS OEM-supplied
networking components. The COUNTY will provide all electrical outlets to support installation
and operation of a fully multiplexed explosive detection system.
2.4.2. Network Services
No other network may interface with the networked airport screening solution. The implemented
assigned network for operation shall be an isolated, stand-alone network.
2.5. ACCEPTANCE - TESTING SUPPORT
The Project schedule shall allow for sufficient time to conduct mandatory testing of the EDS
units after installation and integration. The Project schedule shall also factor in minimum lead
times for notification of readiness for testing (7 days for SAT; 3 days for TRR; and at least 3
business days for ISAT). The COUNTY shall identify operational windows in time in which
testing activities can be accomplished. Testing activities will be scheduled for normal 8-hour
business days (Monday-Friday) and should not include holidays.
Testing activities shall also be scheduled such that test articles shall not be comingled either
physically with Live Passenger Bags on existing or new screening systems or their electronic
screening images shall not appear on consoles being used for Live Passenger Bag screening. Use
of temporary networks or phased testing to accommodate the separation of Live Bags and Test
Articles must be approved in writing through a RFV in advance of TRR/ISAT by the TSA RDC
and TSA Acceptance Test Lead.
Requests for overtime or multiple shifts are discouraged and will only be considered based on
compelling justification. The TSA RDC and TSA Acceptance Test Lead will review/evaluate
any requests for phased testing (e.g. non-consecutive testing activities requiring multiple test
team trips). Such requests must be in writing supported by compelling justification and
submitted to the TSA RDC well in advance of SSTP development. Programming or mechanical
changes made before ISAT (typically during Contractor pre-testing or TRR) must be
documented and provided to the TSA RDC and Acceptance Test Contractor.
2.5.1 Site Specific Test Plan (SSTP)
The COUNTY shall ensure that information needed to develop an accurate SSTP is provided to