Okaloosa County BOCC — October 15, 2013 — OTA_Internal Coordination_Email Comments — reading text
Part 6 of 10. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 86-OTA_Internal Coordination_Email Comments.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
sections 1.1 to 1.7.
Many responsibilities are delegated to TSA contractors such as the EDS Original
Equipment (OEM) Manufacturer, TSA Site Lead Contractor, and TSA Acceptance Test
Contractor but ultimate responsibility resides with TSA.
11 EDS PLACEMENT
If applicable, TSA will ship, rig and install EDS machines and associated EDS screening
equipment, to include any necessary ETD screening equipment, in their respective operational
locations within the CBIS Project location. TSA, through the EDS OEM or other TSA
contractors, shall be responsible for coordinating and integrating activities regarding placement
of EDS equipment with the local TSA Point of Contact and Airport Point of Contact.
1.2 INSTALLATION SUPPORT
1.2.1 Project Management
As applicable, the TSA Site Lead Contractor and the EDS OEM shall be responsible for
providing technical support throughout the entire period of performance during the installation
Project. The OEM shall be responsible for all labor, materials, equipment, and support services
required for planning, managing, and supervising all items related to the installation of the EDS
units and associated ancillary equipment.
1.2.2 Technical Support
TSA will provide technical support to the Project through existing TSA contracts with the EDS
OEM, TSA Site Lead Contractor, and TSA Acceptance Testing Contractor.
« The identified TSA Site Lead Contractor should be included in all relevant CBIS
planning/project meetings relevant to TSA contributions to the Project. Project schedules
and updates should be provided to the TSA Site Lead Contractor to ensure TSA has
timely and sufficient notice of deliverable dates. The TSA Site Lead Contractor will
assess the project progress against the project schedule and approved design to advise
TSA of issues related to cost, schedule and/or performance impacts to the in-line project.
«" The EDS OEM shall provide technical consultations to the TSA Regional Deployment
Coordinator (RDC), TSA Site Lead Contractor, TSA Acceptance Test Lead, TSA
Acceptance Testing Contractor and Airport regarding Project efforts that may include,
but are not limited to: teleconferences; reviews of drawings and specifications; and
exchanges of technical documentation such as specifications, manuals, and guides.
Page 17 of 39
HSTS04-13-H-CT1161
» TSA Acceptance Testing Contractor shall support ISAT of the CBIS (the EDS units,
BHS and the integration between them) and will develop relevant CBIS test plans and
reports that will be shared with the Airport.
« Support for the development and execution of the TSA Other Transaction Agreement in
place between TSA and the COUNTY will be provided by TSA Office of Acquisition.
" Oversight and coordination of technical aspects of the Project will be provided by the
TSA Regional Deployment Coordinator.
= Local TSA personnel shall support coordination of issues between TSA Regional
Deployment Coordinator (RDC) and the Airport as directed by the Federal Security
Director (FSD).
| Title Name Contact Information
Deployment John Reed john.reed1@dhs.gov
. 571-227-1563
Coordinator
1.2.3 Commissioning Services
TSA, through the EDS OEM and its other TSA contractors, shall be responsible for all labor,
materials, equipment, and support services needed to assemble, power up, configure, and install
the EDS machines into the required operational condition. The EDS OEM shall provide technical
support, documentation, and installation of the EDS units and the associated local Baggage
Viewing Stations (BVS) after confirmation that all pre-installation requirements have been met.
The EDS OEM shall coordinate with the TSA RDC, TSA Site Lead Contractor, TSA Acceptance
Test Lead, and the Airport to perform system testing.
1.3 Acceptance Testing
Mandatory testing for this system includes Site Acceptance Testing (SAT) for the EDS units
following installation; pre-Integrated Site Acceptance Testing following the integration of the
EDS units with the BHS is affirmed through a Test Readiness Review (TRR) and Test Readiness
Notice (TRN); and Integrated Site Acceptance Testing (ISAT) is conducted prior to TSA
acceptance of the CBIS system for operational use. TSA may elect to oversee BHS pre-ISAT
conduct to confirm readiness of the system and conduct the TRR within the timeline of the ISAT
to reduce the overall testing timeline. See the following table for minimum lead time
requirements for testing activities.
Page 18 of 39
Table 1. ISAT Timeline
HSTS04-13-H-CT1161
Lead Times for Activity Responsible Parties
ISAT
(Days Prior to
projected test
date)
Site Initiation or Site Survey Data Collection Checklist TSA RDC, TSA
>180 days from provided to the ILDT to complete to support | Site Lead Contractor
ISAT the ISAT Site Specific Test Plan (SSTP)
development.
>120 days Completed Site Survey Data Collection ILDT, TSA Site
Checklist and supporting site documentation
received by TSA Acceptance Test Contractor
from TSA Site Lead Contractor, to include:
e Any and All Approved Request for
Variance (RFV)
e Basis of Design Report
e Sample BHS & CBIS Reports for all
PGDS required Reports
e BHS & EDS Network Diagrams and
Server Architecture
e Local Procedures for Fail-Safe, E-Stop,
Jam Clearing and IQ Test Conduct
e Airport/Airline Bag Induction/Hygiene
Procedures
e BHS Specifications
e Controls Description and/or Description
of Operation (if both exist then provide
both)
e Fail-safe and/or E-Stop Zone Drawings
e BHS Mechanical Plan and Elevation
Drawings from Natural Induction
Locations to & through the CBIS, CBRA
and Make-up Locations with Conveyors
labeled, Plan View Drawings and
Electrical Drawings of the BHS/CBIS
with Control Station & Photoeye
Locations and labeling. All drawings will
be “Approved for Construction” by the
Airport and not Pre-Bid or Bid Use Only
versions.
e Atleast 1 Plan/OverView Drawing that
shows the entire CBIS in a single view
e Conveyor Motor Manifest to include not
Lead Contractor
Page 19 of 39
HSTS04-13-H-CT1161
less than (Conveyor Name, Phase,
Conveyor Type, Degree of Turn, Degree
of Incline/Decline, Length, Speed in FPM,
Motor HP, Control Type (VFD yes/no),
Brake Type, Motor Type, drive Type,
FLA Rating).
e Installation & Commissioning Phasing
Plan Narrative and Phasing Plan Drawings
e Construction and Testing Schedule(s)
>90 days On-site Site Survey Meeting held. to conduct | ILDT,
initial test coordination and review the draft TSA RDC, TSA Site
SSTP. This visit will allow the TSA Lead Contractor,
Acceptance Test Contractor to tour the site, TSA Acceptance
review the draft SSTP with the ILDT, Test Contractor
coordinate logistics and manpower and
initiate the SIDA badge application process, if
required. TSA Site Lead Contractor
coordinates schedule with the ILDT and
TSA’s Acceptance Test Contractor.
>45 days Final SSTP Review Meeting between the ILDT,
TSA Acceptance Test Contractor and the
ILDT to review the final SSTP, include any
other approved RFV, verify logistics &
manpower, and review specific tests to be
*| performed. Any requests for variance from
the SSTP testing requirements must be
delivered in writing to the TSA RDC prior to
this meeting for review and response. This is
the last chance for the ILDT to disclose any
test standards that cannot be met in writing
and formally justify exemption from test
criteria. Any final revisions to the SSTP will
be made and distributed to the ILDT and
RDC prior to test execution.
TSA Site Lead
Contractor, TSA
Acceptance Test
Contractor, TSA
RDC
Typically 14 days
to 1 day
TSA Acceptance Test Contractor will ship
test articles to the ILDT. The ILDT receives
the test articles and stores in a secure and
weather protected laydown area as agreed to
by the ILDT and TSA Acceptance Testing
Contractor in the Final SSTP Review
Meeting.
ILDT, TSA
Acceptance Test
Contractor
>11 business days
CBIS pre-testing - The ILDT conducts pre-
testing. The TSA Site Lead contractor will
provide oversight of CBIS pre-testing to
ILDT, TSA Site
Lead Contractor
Page 20 of 39
HSTS04-13-H-CT1161
validate the Test Readiness Notification
(TRN) to the TSA RDC and Acceptance Test
Team. The ILDT delivers internal pre-ISAT
test results to the TSA Site Lead Contractor
and the Site and TRR readiness confirmation
letter to the TSA RDC and Acceptance Test
Team. Upon successful review, the TSA Site
Lead Contractor is deployed to the site within
7 days.
Note: TSA may combine TRN with CBIS
pre-testing and/or conduct TRR as a subset of
ISAT
>7 business days
TSA Acceptance Testing Contractor or Site
Lead Contractor initiates & performs the
TRR.
Note: TRR Performance by Acceptance
Testing Contractor will be a subset of overall
ISAT duration and permit passed tests to be
credited toward ISAT completion. TRR
failure will result in 2 week moratorium.
ILDT, TSA Site
Lead Contractor
>3 business days
When notice of successful TRR is completed
and delivered to the TSA Acceptance Testing
Contractor via a TRN no later than COB
Wednesday (5:00 p.m. EST), ISAT
deployment will occur the following
Monday. If delivered any time Thursday
through Sunday, the TSA Test Team
deployment will occur on the second Monday.
TSA Site Lead
Contractor, TSA
Acceptance Test
Contractor
1 business days
TSA Acceptance Test Contractor travel day
(normally Monday)
TSA Acceptance
Test Contractor
Test start
TSA Acceptance Test Contractor travel day
(normally Monday) with mobilization
activities and an in-brief meeting with ILDT
on the next business day. Prior to start of
testing, TSA Acceptance Test Contractor will
accept PLC code from TSA Site Lead
Contractor or ILDT prior to the start of
testing. TSA Acceptance Test Contractor and
ILDT will work together to perform ISAT and
collect BHS and EDS performance
documentation. Prior to departing the site, an
Out-brief meeting will be held for all site
stakeholders.
ILDT, TSA
Acceptance Test
Contractor, TSA Site
Lead Contractor
<2 business days
QLR is submitted by the TSA Test
TSA Acceptance
Page 21 of 39
HSTS04-13-H-CT1161
after ISAT
complete
Acceptance Contractor to the TSA
Acceptance Test Lead and RDC for review
and approval
Test Contractor,
TSA Acceptance
Test Lead, TSA
RDC
X business days
after QLR receipt
TSA conducts ISAT review board based on
QLR results to determine readiness of CBIS
to enter Live Operations and Bag Screening
or whether to return CBIS to ILDT for
correction of deficiencies prior to Live
Operations
TSA RDC, TSA
Acceptance Test
Lead,
5 business days QLR is distributed by the TSA Deployment TSA RDC
after ISAT review | RDC
board decision
The TSA Acceptance Test Contractor ILDT, TSA
For 30+ days from
start of substantial
use
remotely monitors system performance during
live operations run-in period and observes
system on-site for 3+ days
Acceptance Test
Contractor, TSA
Test Lead
5 business days
following
completion of data
collection and
onsite observation
for run-in
The TSA Acceptance Test Contractor
provides a Test Summary Report (TSR) to the
TSA Acceptance Test Lead and RDC for
review and approval.
TSA Acceptance
Test Contractor,
TSA RDC, TSA
Acceptance Test
Lead
5 business days
RDC distributes TSA approved TSR to ILDT
ILDT, TSA RDC
1.3.1. Site Acceptance Testing (SAT)
The EDS OEM shall coordinate and conduct SAT testing on the EDS machines in the presence
of a TSA designated government witness. The EDS OEM shall implement and coordinate
testing by issuing a Test Readiness Notification (TRN) at least 7 days prior to the scheduled
Acceptance testing. Passing SAT results are required prior to final integration of EDS to the
BHS and to certify equipment readiness for operational use in screening baggage. In the event
that the TSA supplied EDS units cannot meet SAT test requirements, TSA will ensure that any
EDS machine defects are corrected or that the EDS unit is replaced.
1.3.2. Site Specific Test Plan Development (SSTP)
TSA has arranged for its Acceptance Test Contractor to