Okaloosa County BOCC — December 6, 2016 — Gap Creek QAPP Task Order Approval — agenda request
Gap Creek QAPP Task Order Approval — agenda request in the December 6, 2016 Okaloosa County BOCC meeting materials. Preserved county-portal original with machine-extracted reading text.
Preserved among the December 6, 2016 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1366). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used September 20, 2016; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Action Item Printout
Date
December 6, 2016
Publisher
Okaloosa County Board of County Commissioners
Where to find it
2
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Gap Creek QAPP Task Order Approval — agenda request — extracted reading text
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
Gap Creek QAPP Task Order Approval — agenda request — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: December 6, 2016
TO: Honorable Chairman and Members of the Board
FROM: Jason Autrey
SUBJECT: Gap Creek QAPP Task Order Approval
DEPARTMENT: Public Works
BCC DISTRICT: 4
STATEMENT OF ISSUE: Okaloosa County and the Florida Department of Environmental
Protection (FDEP) entered into a grant agreement for improvements to the Poplar Avenue pond
in the Gap Creek watershed. As a condition of the grant, the County must monitor water in the
pond after storms and report the findings to FDEP. A Task Order with HDR Engineering Inc. is
recommended to meet the grant conditions.
BACKGROUND AND ANALYSIS: In February of 2012, Okaloosa County and the Florida
Department of Environmental Protection (FDEP) entered into an agreement (Agreement No.
G0326) for improvements to the Gap Creek watershed. The agreement is part of the 319 grant
program promulgated by FDEP and the scope of work included the design, permitting and
construction of the project. Through the course of designing and permitting the project, the scope
was reduced in April of 2015. Terms of the agreement required a match by Okaloosa County, in
the form of paying for the design, performed by HDR Engineering, Inc. and construction
administration. The FDEP provided funds for construction; which is substantially complete.
Though the scope of the project was reduced, the remaining improvements to the Poplar Avenue
pond are expected to improve water quality and improve longstanding stormwater flooding
issues in the area. By improving flow capacity and outfall structures, there is an anticipated
increase in treatment of 11% of overall runoff that formerly exceeded conveyance channel
capacity. A condition of the Grant requires the County to monitor and report the effectiveness of
the improvements. Over the next year, between 7 and 10 rain events, measuring between .2
inches and 1.5 inches of rainfall in a 24 hour period, are to be analyzed. The following will be
measured for reduction: Total Metals (Cadmium, Chromium, Copper, Zinc), Nitrates, Total
Kjeldahl Nitrogen, Total Nitrogen, Ortho-Phosphate, Total Ammonia, Total Phosphorus, Total
Suspended Solids, Oil & Grease, and Fecal Coliform. Three quarterly reports and a final report
will be provided to FDEP.
OPTIONS: Approve/Disapprove Task Order 15 under contract C14-2078-PW for the Not to
Exceed amount of $67,620.00
RECOMMENDATION: Approve proposed Task Order 15 with HDR Engineering Inc. under
contract C14-2078-PW for the Not to Exceed amount of $67,620.00 for stormwater sampling
and reporting services in the Gap Creek watershed.
RECOMMENDED BY:
APPROVED BY:
John Hofstad, County Administrator
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — December 6, 2016 — Gap Creek QAPP Task Order Approval — agenda request.” December 6, 2016. Action Item Printout. Crypt of Echoes evidence ID LED-2026-770d59e4d313431f85d5ff57d06ff10c. http://127.0.0.1:58097/evidence/LED-2026-770d59e4d313431f85d5ff57d06ff10c. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, Gap Creek QAPP Task Order Approval — agenda request, meeting materials for December 6, 2016. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=30&ID=22808&MeetingID=1366
Preserved county public-record source. Third-party attachments may retain their original rights.