TASK ORDER APPROVAL FORM
CONTRACT #:C22-3246-WS
TASK ORDER #: 8
TASK ORDER AMOUNT: $235,780
OFFERED BY CONSULTANT:
Jacobs Engineering Group Inc.
FIRM'S NAME
Scott Jernigan
REPRESENTATIVE'S PRINTED NAME
ST
SIGNATURE
Principal Project Manager 9/5/2024
TITLE DATE
RECOMMENDED FOR APPROVAL
(Department Director)
Michael
Hackett
SIGNATURE
email=mhackett@myokaloosa.com, c=US
Date: 2024.09.06 15:34:59 -0500"
Michael Hackett, Water & Sewer Director
TITLE
DATE
Digitally signed by John
Hofstad
John Hofstad vaie-5024.00.10
10:46:56 -05'00"
COUNTY ADMINISTRATOR (if applicable)
DATE
Revised January 21, 2020
APPROVED BY OKALOOSA COUNTY
(Per Purchasing Manual) Table 1
H Digitally signed by DeRita
DeRita Mason
Date: 2024.09.10
Mason 06:59:53 -05'00'
PURCHASING MANAGER
DATE
Digitally signed by Faye
Faye Douglas
Date: 2024.09.10
Douglas 10:11:10 -05'00"
OMB DIRECTOR/DATE
DATE
CHAIRMAN (if applicable)
DATE
CONTRACT #C22-3246-WS
Task Order 08
THIS TASK ORDER IS ISSUED PURSUANT TO THE AGREEMENT FOR CONSULTING SERVICES DATED SEPTEMBER 28, 2022,
FOR THE BOARD OF COUNTY COMMISSIONERS OF OKALOOSA COUNTY, FLORIDA, WHICH IS INCORPORATED HEREIN BY
THIS REFERENCE, WITH RESPECT TO:
Shoal River Ranch Well Design, Permitting, Bidding, and
Construction Services
Article A. Purpose
Introduction
The Board of County Commissioners of Okaloosa County (the “COUNTY”) Water and Sewer
Department provides drinking water to customers throughout the unincorporated areas of Okaloosa
County through groundwater wells located throughout the county. Within the County’s mid-county
service area, the COUNTY has six (6) wells which supply drinking water to customers around
Crestview in addition to supplementing supply in the south end of the county (Garnier and County
West service areas). Due to the increase in water demand in the COUNTY’s service area, a new
groundwater production well (well) is needed. The COUNTY has identified the Shoal River Ranch
area as the location for the proposed well. This task order (TO) was requested by the COUNTY for
Jacobs Engineering Group Inc. (Jacobs) to complete the design, permitting, bidding services, and
construction services for the Shoal River Ranch (SRR) Well.
Article B.Scope of Services
Task 1 - Project Kickoff Meeting, Site Visit, and Data Collection and
Evaluation
Jacobs will attend a project kickoff meeting with COUNTY staff at the COUNTY office. The purpose of
this meeting will be to introduce key project team members from each organization and to discuss
and gain alignment on various topics, including but not limited to the following:
e Scope, procedures, and schedule for well design and wellhead design
e Site access and security
e Procedures for coordination among project team members
e Project deliverables
Following the kickoff meeting, Jacobs staff will visit the well site to collect information relevant to
the well and wellhead design. As part of Task 1, Jacobs will also review existing data and reports and
other information relevant to the design of the SRR Well. Data evaluation will include the review of
existing water quality data, geophysical logs, well and aquifer performance testing, well completion
reports, and previous reports and designs prepared by others. Jacobs will coordinate an additional
meeting between FPL, COUNTY, and Jacobs to discuss power supply and delivery to the SRR Well
site.
Deliverables
Electronic portable document format (pdf) version of the kickoff meeting agenda, and
summary.
Meetings
One kickoff meeting at the COUNTY office attended by four Jacobs staff.
One meeting at site attended by up to two Jacobs staff.
Assumptions
1. The COUNTY will provide all well data, reports, and other information to support the well
design within 15 working days of notice-to-proceed (NTP) issuance.
2. The COUNTY will assign a project manager to be responsible for timely coordination and
decision making, as well as providing unified COUNTY direction.
3. Four Jacobs staff members will attend the kickoff meeting which will be followed by a site
visit on the same day, which is assumed to last approximately 2 to 4 hours.
4. The kickoff meeting will be held at the COUNTY office.
Task 2 - Permitting and Well Completion Report
The scope of services for this task includes permitting assistance for the construction of the SRR well
and preparation of the final well construction and testing report. Jacobs will perform the following
services as part of this task:
Onsite meeting with the Northwest Florida Water Management District (NWFWMD) for final
approval of the new well location within the existing property and to discuss the well
construction and testing approach. The onsite meeting will include up to two (2) Jacobs
staff and last approximately 1 hour.
As required by the NWFWMD, Jacobs will prepare a construction and testing plan for the
SRR well that outlines the approach and key features of the well construction. It is expected
that the key features of the plan will include the general construction/testing approach, well
construction details, and testing requirements. The construction and testing plans will serve
as the “roadmap” for executing the construction portion and will be used as the basis for
the overall well design and construction. Jacobs will provide an electronic copy of the draft
plan to the COUNTY for review prior to finalizing and submitting the plan to NWFWMD.
Jacobs will prepare a hydrogeologic and engineering report following completion of the SRR
well. The report will summarize regional and local hydrogeologic conditions, well
construction details, well and aquifer test procedures and results, and water quality
sampling results during and after well construction.
Permitting assistance and one response for the permit application to a request for
additional information from each agency will be provided for the following activities:
- Assist the COUNTY’S well drilling contractor in preparation of the water well
construction permit, including the preparation of applications, exhibits, drawings, and
specifications as necessary for the well construction permit application.
- Prepare the Florida Department of Environmental Protection (FDEP) Public Drinking
Water Facility Construction Permit application for the supply well, wellhead, and raw
water piping. Jacobs will attend one meeting with FDEP staff, if necessary.
- Assist COUNTY in obtaining the FDEP Certificate of Completion (COC) for the well,
wellhead, raw water piping by preparing the FDEP COC.
- Jacobs will respond to RFIs from FDEP and attend one FDEP field inspection, if required.
Deliverables
Onsite meeting minutes
Draft and Final Well Construction and Testing Plan
FDEP Public Drinking Water Facility Construction Permit Application for review by COUNTY
and submittal to FDEP
FDEP COC Application for review by COUNTY and submittal to FDEP
Okaloosa County Growth Management Department Permits Application for review by
COUNTY and submittal to Okaloosa County Growth Management Department
Draft and final Well Construction and Testing Engineering Report
Copies of all relevant correspondence related to this task
Meetings
Up to two Jacobs staff will attend one onsite meeting with NWFWMD and the COUNTY.
One meeting with FDEP for the Public Drinking Water Facility Construction Permit
Application
One field inspection with FDEP for COC, if required
Assumptions
1. Well siting services are not included as part of this scope. It is assumed that the new well
will be located on the COUNTY identified project site.
2. Proposed well location, as presented to NWFWMD and FDEP by COUNTY and Jacobs, will be
accepted by NWFWMD and FDEP for construction of the supply well. If the well site requires
relocation, additional fee may be required.
3. Any private well location information will be provided by the COUNTY. Private well
mitigation services are not included.
4. The SRR well is included in the COUNTY’s Water Use Permit (WUP) as Facility ID# MC-8 and
therefore the existing WUP does not require modification.
5. No groundwater modeling is required.
6. This project will not impact jurisdictional wetlands. No wetland delineation or mitigation
services are included as part of this scope of services. If any wetland delineation or
mitigation is required, additional compensation to Jacobs will be required, or the COUNTY
will provide the environmental services.
10.
11.
Environmental Resource Permitting is not included in this scope of services, but can be
provided as an additional service, if required.
A protected tree inventory of the well site will not be required.
Project does not require submittals to, nor approval of, the Okaloosa County Development
Review Committee.
Engineering report will be delivered electronically in pdf format.
The COUNTY will provide review of the draft engineering report and will provide comments
to Jacobs.
Task 3 - Production Well Design Services
Task 3 describes design services that will be provided for the well construction and testing. Jacobs
will prepare the contract documents that contain the well construction, drilling and testing plans
and technical specifications to be used for constructing the SRR well. Jacobs’s scope of services for
this task is as follows:
Prepare plans and technical specifications for the construction and testing of one 18-inch
diameter Floridian aquifer production well. Targeted design flow for the new supply well will
be 1,000 gallons per minute (gpm) or 1.44 million gallons per day (mgd).
Prepare the bid table for the COUNTY to insert into a COUNTY bid form. The bid table will
be prepared and delivered in Microsoft Excel.
The well construction and testing plans and specifications will be packaged as a separate
construction package for the COUNTY to procure a well drilling construction contractor.
Submit a review set of the drilling and specification package to COUNTY for review.
Incorporate review comments into drilling and specification package.
Jacobs will provide an opinion of probable cost for the construction and testing of the
production well.
Deliverables
Draft well construction and testing plans and specifications, and bid table at 30 percent
completion (3 full size plans and pdf format)
Draft well construction and testing plans and specifications, and bid table at 60 percent
completion (3 full size plans and pdf format)
Draft well construction and testing plans and specifications, and bid table at 90 percent
completion (3 full size plans and pdf format)
Final well construction and testing plans and specifications, and bid table at 100 percent
completion (3 full size plans and pdf format)
Copies of correspondence related to this task
Meetings
A 90% review meeting will be held at the COUNTY office and attended by up to three Jacobs
staff, which is expected to last up to 2 hours.
Assumptions
1. The SRR Well will be designed with approximately 100 feet of 24-inch surface casing and
approximately 400 feet of 18-inch diameter final casing. Actual casing depths will be determined
in the field and will be based on site-specific conditions encountered during drilling. The target
capacity of the well will be 1,000 gpm, depending on the final pump and size selected; however,
the specific and characteristics of the aquifer will influence the final capacity of the well.
2. The well will be located on the COUNTY identified property.
3. The COUNTY will review the draft 90 percent well design package and provide review comments
to Jacobs.
4. The COUNTY will provide front-end contract documents for the plans and technical specification
package produced by Jacobs and assembly final bid package.
Task 4 - Wellhead Design Services
Jacobs will provide design services for the SRR well wellhead and raw water piping, wellhead
appurtenances, onsite building, electrical, instrumentation, and control (1&C), and site work
construction package. Jacobs’s scope of services for this