Okaloosa County BOCC — October 21, 2014 — Total Project Costs including GMP - 10-21-2014 — reading text

Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.

Machine-extracted text — 78-Total Project Costs including GMP - 10-21-2014.pdf

Machine-extracted OCR text · Review label: Machine produced / unreviewed

Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.

Okaloosa County Administration Building Contract C12-1995-FM Change Order 5 Breakdown for Contract Adjustment per Approved GMP Preconstruction Services (includes Architect. Construction Administration and CM Construction Fee) New Design Budget (CO 2} $817,597.00 New €M Build Budget (CO 2) $645,950.00 Total New Design and CM Build Budget $1,463,547.00 Less Architect Construction Administration (CO 2) ($150,841.71) Less CM Construction Fee (CO 2) ($508,500.00) Total Preconstruction Budget $804,205.29 Approved Construction GMP | $11,262,329.00 Appeared Less Est, Sales Tax Savings ($168,935.00) t.NP Adjusted GMP Budget - Approved $11,093,394.00 Additional Scope - Asbestos Abatement - CO 1 $170,854.54 Additional Scope - Asbestos Abatement Portion - CO 4 $6,506.15 Additional Scope - Bond fer Asbestos - CO 4 $65.06 Total Additional Scope - Asbestos $177,425.75 Total for all work - Precon, GMP, Asbestos Preconstruction Budget $804,205.29 Tote | GMP Budget $11,093,394.00 Feejnck Asbestos Scope Addition $177,425.75 Cask Total for all work $12,075,025.04 Less Currently Funded Amount ($5,837,940.44) Total Adjustment for Approved GMP - CO 5 $6,237,084.60

Download this text file with its original spacing ↓