READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — 2013 meeting #1142 (date undetermined) — 1-7 Water & Sewer — reading text
Part 1 of 6. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 19-1-7 Water _ Sewer.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
BOARD OF COUNTY COMMISSIONERS
OKALOOSA COUNTY, FLORIDA
SERVICE AREA: PHYSICAL ENVIRONMENT
DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/WATER OPERATIONS
PROGRAM DESCRIPTION: This program is responsible for assuring that safe and adequate water supplies
are provided to users of the County water system. This is accomplished through a network of 20 wells, 19 water
tanks, 462.0 miles of water distribution mains, 51.51 miles of water service lines and 3,980 fire hydrants. Read
in excess of 30,000 meters each month and maintain backflow preventer program.
REVENUE: The Water & Sewer enterprise fund receives all revenue through monthly customer billings,
capacity expansion charges and related ancillary charges for use of both the Water and Sewer systems within
the Okaloosa County service area. The funds customer base is currently in excess of 36,000 water service and
33,000 sewer service connections both residential and commercial.
EXPENDITURES:
Expenditures Budget
FY11 FY12 FY13 FY14
Category Actual $ Actual $ Original $ Approved $
Personal Services 774,662 673,578 795,964 847,076
Operating Expenses 1,884,610 1,843,436 1,163,972 1,145,281
Capital Outlay 181,663 363,612 879,102 1,348,651
Debt Service 421,398 439,728 951,938 954,290
Reserves 0 0 1,728,512 1,990,472
Total 3,262,333 3,320,354 5,519,488 6,285,770
HISTORICAL STAFFING SUMMARY:
Category FY11 FY12 FY13 FY14
Full-time 15 14 14 15
Part-Time 0 0 0 0
Relief 0 0 0 0
Total 15 14 14 15
MAJOR ACCOMPLISHMENTS LAST YEAR:
Continued large meter testing & calibration program.
Performed major maintenance and painting on 2 elevated water tanks (East Island & Shalimar Annex).
Del Cerro II Well (design) – install new potable water well in the Mid-County area to increase potable water
supply and reliability of the system.
1
PROGRAM GOAL:
Provide safe, adequate and affordable water supplies to users of the County water system. Provide seamless
addition of new water customers. Repair & maintain water wells, tanks, and potable water booster pump
stations. Maintain backflow preventer program. Read in excess of 30,000 meters each month and perform all
account turn on and turn offs. Maintain the highest standard as it relates to all facets of the customer service
function including new service set up, billing and collections. Insure strict compliance with ALL Federal and
State requirements through periodic sample testing and constant monitoring.
KEY OBJECTIVES:
1. Ensure budgetary, personnel, customer service and purchasing functions comply with County policies and
procedures.
2. Preserve and protect infrastructure to provide quality of service to customers.
3. Maintain and extend the useful life and utility of County facilities.
4. Reduce overall per capita consumption through the promotion and utilization of conservation techniques.
5. Ensure the preservation and safe operation of all work related equipment.
6. Assure water meets all applicable State and Federal drinking water standards.
7. Assure system is operated in such a fashion as to meet peak loads in all service areas.
The following projects are planned for FY2014:
Del Cerro II Well (construction) – install new potable water well in the Mid-County area to increase potable
water supply and reliability of the system.
Brooks Bridge Water Main Repair or Replacement (design & construction) – install a second water supply
line to Okaloosa Island (or repair the broken bore, if at all possible), which would then serve as the primary
water source to Okaloosa Island (and main on bridge would serve as backup).
Newcastle Area Water System Improvements (design & construction) – provide new, larger water mains to
the area and fire hydrants to provide increased fire protection and ensure the reliability of the system. This
project is funded by a Florida Department of Economic Opportunity Community Development Block Grant.
Bob Sikes Elevated Water Tank (design) – a second elevated water tank near the Bob Sikes Industrial Park
would provide for increased storage, reliability, and redundancy for the potable water and fire suppression
systems.
Future Water Supply (planning) – continue with Implementation Plan to ensure the sustainability of a safe,
reliable, and adequate water supply in the future, with efforts focused along the Shoal River for an offline
reservoir. Partnering with the U.S. Army Corps of Engineers on a hydraulic water model of the entire water
system. Seeking funding for land acquisition for property to serve the following purposes: future reservoir,
future water treatment plant, watershed protection, and military buffering.
Planned major maintenance and painting of 2 elevated water tanks (Countryview & Bluewater Bay).
2
PERFORMANCE MEASURES:
Actual Estimated Adopted
Performance Measures
FY11/12 FY12/13 FY13/14
Volume of water processed (millions of gallons) 2,282 2,443 2,443
Input
Output
Number of Backflow Preventers / # of Testers 2,200 / 1 2,200 / 1 2,200 / 1
Number of Meters Read / # of Meter Readers 31,917 / 7 32,071 / 7 32,225 / 7
Efficiency
Number of Wells / # of Water Operators 20 / 3 20 / 3 21 / 3
Number of Tanks / # of Water Operators 19 / 3 19 / 3 19 / 3
Cost per gallon of water processed 0.0051 0.0053 0.0064
Effectiveness
Total square miles of service area 71.5 71.5 71.5
3
BOARD OF COUNTY COMMISSIONERS
OKALOOSA COUNTY, FLORIDA
SERVICE AREA: PHYSICAL ENVIRONMENT
DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/WASTEWATER OPERATIONS
(LIFT STATIONS & PLANTS)
PROGRAM DESCRIPTION: This program is responsible for protecting the public health through the
provision of sanitary sewers for wastewater collection (lift stations), treatment plants, and effluent disposal. It is
responsible for protecting the environment by preventing the introduction of pathogens and excess nutrients into
the ground and surface waters.
REVENUE: The Water & Sewer enterprise fund receives all revenue through monthly customer billings,
capacity expansion charges and related ancillary charges for use of both the Water and Sewer systems within
the Okaloosa County service area. The funds customer base is currently in excess of 36,000 water service and
33,000 sewer service connections both residential and commercial.
EXPENDITURES:
Expenditures Budget
FY11 FY12 FY13 FY14
Category Actual $ Actual $ Original $ Approved $
Personal Services 1,549,324 1,347,157 1,591,929 1,633,647
Operating Expenses 3,769,221 3,686,872 2,327,944 2,208,758
Capital Outlay 363,326 727,223 1,758,203 2,600,969
Debt Service 842,795 879,455 1,903,876 1,840,419
Reserves 0 0 3,457,024 3,838,769
Total 6,524,665 6,640,707 11,038,976 12,122,562
HISTORICAL STAFFING SUMMARY:
Category FY11 FY12 FY13 FY14
Full-time 36 30 28 28
Part-Time 0 0 0 0
Relief 0 0 0 0
Total 36 30 28 28
4
MAJOR ACCOMPLISHMENTS LAST YEAR:
Main Island Lift Station (construction) – a new lift station was needed to replace the aging, failing, lift
station servicing all of Okaloosa Island. This project provides greater capacity and reliability to the Island
sewer system.
Duke Field Force Main & Lift Station (construction) – provided sewer service to Duke Field via a master
lift station “inside the fence” and approximately 7 miles of piping.
Meigs-Seminole Lift Station (design) – replace the aging and undersized Meigs-Seminole Lift Station,
which pumps all the wastewater from Bluewater Bay to the Niceville-Valparaiso Regional Sewer Plant.
Maintained 24/7 standby coverage on all program components, Lift Stations / Water Wells.
Transported biosolids from all 3 wastewater reclamation facilities (WRFs) off site to be used as fertilizer.
Operated and maintained compliance with FDEP permits on all 3 WRFs.
Maintained 144 Lift Stations in our collection system.
Maintained 225 acres of RIBs for effluent disposal at the Arbennie Pritchett WRF.
Operated and maintained Public Access Reuse System for the City of FWB.
Implementation of Pretreatment Program for Industrial Users.
Operated and maintained a State Certified Lab at the Arbennie Pritchett WRF.
Maintain 48 stationary / portable generator sets
Provided electronic/mechanical support on 19 potable water wells and 20 tanks
Operations staff provides 24/7 customer service, monitors alarms & notifications for entire water &
wastewater systems.
PROGRAM GOAL:
Protect public health by providing sanitary sewers for wastewater collection (lift stations), treatment plants, and
effluent disposal. Provide seamless addition of new sewer customers. Repair and maintain 144 sewage lift
stations, 3 water reclamation facilities (WRFs) and all other portions of the infrastructure. Maintain the highest
standard as it relates to all facets of the customer service function including new service set up, billing and
collections. Insure strict compliance with ALL Federal and State requirements through compliance sample
testing and constant monitoring.
KEY OBJECTIVES:
1. Ensure budgetary, personnel, customer service and purchasing functions comply with County policies and
procedures.
2.