wildlife and habitat by the changes to the project, in
accordance with the Endangered Species Act of 1973, the Sikes Act
Amendments of 1974, Executive Order 13112 – Invasive Species, the Fish
and Wildlife Coordination Act of 1958, and the Fish and Wildlife Conservation
Act of 1980. (FAA Order 1050.1E, CHG 1, Appendix A, section 8).
8.15 Other Environmental Permits (Not applicable to this project)
8.16 Technical Meetings
8.17 Quality Assurance/Quality Control
8.18 Supervision
8.19 Coordination
Packet Pg. 608
9 STRUCTURES - SUMMARY AND MISCELLANEOUS TASKS AND DRAWINGS
(Not applicable to this project)
10 STRUCTURES - BRIDGE DEVELOPMENT REPORT (Not applicable to this
project)
11 STRUCTURES - TEMPORARY BRIDGE (Not applicable to this project)
12 STRUCTURES - SHORT SPAN CONCRETE BRIDGE (Not applicable to this
project)
13 STRUCTURES - MEDIUM SPAN CONCRETE BRIDGE (Not applicable to this
project)
14 STRUCTURES - STRUCTURAL STEEL BRIDGE (Not applicable to this project)
15 STRUCTURES - SEGMENTAL CONCRETE BRIDGE (Not applicable to this
16 STRUCTURES - MOVABLE SPAN (Not applicable to this project)
17 STRUCTURES - RETAINING WALL (Not applicable to this project)
18 STRUCTURES – MISCELLANEOUS (Not applicable to this project)
19 SIGNING AND PAVEMENT MARKING ANALYSIS
The CONSULTANT shall analyze and document Signing and Pavement Markings
Tasks in accordance with applicable manuals, guidelines, standards, handbooks,
procedures, and current design memorandums.
19.1 Traffic Data Analysis
The CONSULTANT shall review the approved preliminary engineering
report, typical section package, traffic technical memorandum and proposed
geometric design alignment to identify proposed sign placements and
roadway markings. Perform queue analysis.
19.2 No Passing Zone Study (Not applicable to this project)
Packet Pg. 609
19.3 Reference and Master Design File
The CONSULTANT shall prepare the Signing & Marking Design file to
include necessary design elements and associated reference files.
19.4 Multi-Post Sign Support Calculations
The CONSULTANT shall determine the appropriate column size from the
FDOT’s Multi-Post Sign Program(s).
19.5 Sign Panel Design Analysis
Establish sign layout, letter size and series for non-standard signs.
19.6 Sign Lighting/Electrical Calculations (Not applicable to this project)
19.7 Quantities
19.8 Computation Book
19.9 Cost Estimates
19.10 Technical Special Provisions
19.11 Other Signing and Pavement Marking Analysis (Not applicable to this
project)
19.12 Field Reviews
19.13 Technical Meetings
19.14 Quality Assurance/Quality Control
19.15 Independent Peer Review (Not applicable to this project)
19.16 Supervision
19.17 Coordination
20 SIGNING AND PAVEMENT MARKING PLANS
The CONSULTANT shall prepare a set of Signing and Pavement Marking Plans in
accordance with the Plans Preparation Manual that includes the following.
20.1 Key Sheet
20.2 Summary of Pay Items
20.3 Tabulation of Quantities
Packet Pg. 610
20.4 General Notes/Pay Item Notes
20.5 Project Layout (Not applicable to this project)
20.6 Plan Sheet
20.7 Typical Details (Not applicable to this project)
20.8 Guide Sign Work Sheet(s)
20.9 Traffic Monitoring Site (Not applicable to this project)
20.10 Cross Sections (Not applicable to this project)
20.11 Special Service Point Details (Not applicable to this project)
20.12 Special Details (Not applicable to this project)
20.13 Interim Standards (Not applicable to this project)
20.14 Quality Assurance/Quality Control
20.15 Supervision
21 SIGNALIZATION ANALYSIS (Not applicable to this project)
22 SIGNALIZATION PLANS (Not applicable to this project)
23 LIGHTING ANALYSIS (Not applicable to this project)
24 LIGHTING PLANS (Not applicable to this project)
25 LANDSCAPE ARCHITECTURE ANALYSIS (Not applicable to this project)
26 LANDSCAPE ARCHITECTURE PLANS (Not applicable to this project)
27 SURVEY
The CONSULTANT shall perform survey tasks in accordance with applicable
statutes, manuals, guidelines, standards, handbooks, procedures, and current
design memoranda.
The CONSULTANT shall submit survey notes and computations to document the
Packet Pg. 611
surveys. Field survey work shall be recorded in approved media and submitted to
the COUNTY. Field books submitted to the COUNTY must be of an approved type.
The field books shall be certified by the surveyor in responsible charge of work
being performed before the final product is submitted.
The survey notes shall include documentation of decisions reached from meetings,
telephone conversations or site visits. All like work (such as bench lines, reference
points, etc.) shall be recorded contiguously. The COUNTY may not accept field
survey radial locations of section corners, platted subdivision lot and block corners,
alignment control points, alignment control reference points and certified section
corner references. The COUNTY may instead require that these points be surveyed
by true line, traverse or parallel offset.
27.1 Horizontal Project Control (HPC)
Establish or recover HPC, for the purpose of establishing horizontal control
on the Florida State Plane Coordinate System or datum approved by the
COUNTY Surveyor (DS) or COUNTY Location Surveyor (DLS); may include
primary or secondary control points. Includes analysis and processing of field
collected data, and preparation of forms.
27.2 Vertical Project Control (VCP)
Establish or recover VCP, for the purpose of establishing vertical control on
datum approved by the COUNTY Surveyor (DS) or the COUNTY Location
Surveyor (DLS).; may include primary or secondary vertical control points.
Includes analysis and processing of field collected data, and preparation of
forms.
27.3 Alignment and/or Existing Right of Way Lines
Establish, recover or re-establish project alignment. Also includes analysis
and processing of field collected data, existing maps, and/or reports for
identifying mainline, ramp, offset, or secondary alignments. Depict alignment
and/or existing R/W lines (in required format) per COUNTY R/W Maps,
platted or dedicated rights of way.
27.4 Aerial Targets (Not applicable to this project)
27.5 Reference Points
Reference HPNC points, project alignment, vertical control points, section,
¼ section, center of section corners and G.L.O. corners as required.
27.6 Topography/DTM (3D)
Locate above ground features and improvements for the limits of the project
by collecting the required data for the purpose of creating a DTM with
sufficient density. Shoot break lines, high and low points. Effort includes field
Packet Pg. 612
edits, analysis and processing of field collected data, existing maps, and/or
reports.
27.7 Planimetric (2D) (Not applicable to this project)
27.8 Roadway Cross Sections/Profiles
Perform cross sections or profiles. May include analysis and processing of
field-collected data for comparison with DTM.
27.9 Side Street Surveys (Not applicable to this project)
27.10 Underground Utilities (Not applicable to this project)
27.11 Outfall Survey (Not applicable to this project)
27.12 Drainage Survey (Not applicable to this project)
27.13 Bridge Survey (Minor/Major) (Not applicable to this project)
27.14 Channel Survey
Locate topographic features and improvements for the limits of the project by
collecting the required data. Includes field edits, analysis and processing of
field collected data, maps, and/or reports.
27.15 Pond Site Survey
Refer to tasks of this document as applicable.
27.16 Mitigation Survey (Not applicable to this project)
27.17 Jurisdiction Line Survey
Perform field location (2-dimensional) of jurisdiction limits as defined by
respective authorities, also includes field edits, analysis and processing of
field collected data, preparation of reports.
27.18 Geotechnical Support
Perform 3-dimensional (X,Y,Z) field location, or stakeout, of boring sites
established by geotechnical engineer. Includes field edits, analysis and
processing of field collected data and/or reports.
Packet Pg. 613
27.19 Sectional/Grant Survey (Not applicable to this project)
27.20 Subdivision Location (Not applicable to this project)
27.21 Maintained R/W (Not applicable to this project)
27.22 Boundary Survey (Not applicable to this project)
27.23 Water Boundary Survey (Not applicable to this project)
27.24 Right of Way Staking / Right of Way Line (Not applicable to this project)
27.25 Right of Way Monumentation
Set R/W monumentation as depicted on final R/W maps for corridor and
water retention areas.
27.26 Line Cutting
Perform efforts required to clear vegetation from the line of sight.
27.27 Work Zone Safety
Provide work zone as required by COUNTY standards.
27.28 Miscellaneous Surveys
Refer to tasks of this document, as applicable, to perform surveys not
described herein. The percent for Supplemental will be determined at
negotiations. This item can only be used if authorized in writing by the
COUNTY Surveyor (DS), COUNTY Location Surveyor (DLS) or their
representative.
27.29 Supplemental Surveys
Supplemental survey days and hours are to be approved in advance by CLS.
Refer to tasks of this document, as applicable, to perform surveys not
described herein.
27.30 Document Research
Perform research of documentation to support field and office efforts
involving surveying and mapping.
27.31 Field Review
Perform verification of the field conditions as related to the collected survey
data.
Packet Pg. 614
27.32 Technical Meetings
Attend meetings as required and negotiated by the Surveying and Mapping
COUNTY.
27.33 Quality Control/Quality Assurance
Establish and implement a QAQC plan. Also includes subconsultant review,
response to comments and any resolution meetings if required, preparation
of submittals for review, etc.
27.34 Supervision
Perform activities required to supervise and coordinate project. These
activities must be performed by the project supervisor, a Florida P.S.M. or
their delegate as approved by the District Surveying Office.
27.35 Coordination
Coordinate survey activities with other disciplines. Unit is based on 3 percent
of office support hours from tasks 1 through 28, where applicable.) These
activities must be performed by the project supervisor, a Florida P.S.M. or
their delegate as approved by the District Surveying Office.
28 PHOTOGRAMMETRY (Not applicable to this project)
29 MAPPING (Optional Service)
The CONSULTANT will be responsible for the preparation of control survey maps,
right of way maps, maintenance maps, sketches, other miscellaneous survey maps,
and legal descriptions as required for this project in accordance