READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — October 15, 2013 — Task Order#13_ATCT Design-Bidding-Permitting Services — reading text
Part 3 of 3. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 78-Task Order_13_ATCT Design-Bidding-Permitting Services.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Requests
For Additional Information received from the FDEP. Upon completion of the project, RS&H shall prepare the
Certification of Completion packages for both the water and sewer permits to turn the systems over for
operation.
Task B.2.5 National Pollutant Discharge Elimination System Permitting (NPDES): RS&H will prepare the
stormwater Pollution Prevention Plan (SWPPP) and the Notice of Intent (NOI) application as required by DEP
for NPDES permitting.
Task B.2.6 US Army Corp of Engineers Section 404 Permit: RS&H will prepare and submit an application
for a Section 404 with the USACE for wetlands. The permit set will contain plans and details necessary for the
horizontal improvements proposed.
Task B.3.0 Wetland Mitigation and Permitting Assistance
Task B.3.1 Wetland Mitigation Identification / Flag Wetland in Project Area. RS&H will perform site
investigation to review potential mitigation areas and flag wetland jurisdictional line within project limits. The
A/E will investigate existing on-Airport wetlands for use as mitigation.
Task B.3.2 NWFWMD Field Review Meeting. RS&H will meet individually onsite with the NWFVWMD to
review project area and coordinate mitigation area.
Task B.3.3 USACE Field Review Meeting. RS&H will meet individually onsite with the USACE to review
project area and coordinate mitigation area.
Task B.3.4 Request For Additional Information (RAI) Response. RS&H shall respond to one Request for
Additional Information (RAls) for USACE 404 Permit and NWFWMD Environmental Resource Permit.
Project Team:
The project team is comprised of these firms and their role:
1. RS&H- Prime Architect/Engineer
2. Air Traffic Consulting Service — Air Traffic Control Tower (ATCT) Specialist
3. NOVA Engineering and Environmental ~- Geotechnical Investigation
4. Gustin, Cothern & Tucker, Inc. ~ Surveying and Utility Locates
Meetings:
The AVE will prepare for and attend the following meetings (all meeting are in Destin except as noted):
1. Design Kickoff Meeting
2. Design Development (60% CD) Review Meeting
3. Construction Document (90% CD) Review Meeting
4. Pre-Bid Meeting
5. Bid Opening
6. Pre-Application Permit meeting with City of Destin
7. Pre-Application Permit meeting with USACOE
8. Pre-Application Permit meeting with NWFWMD '
9. Field Meeting with USACE
10. Field Meeting with NWFWMD
Destin Airport Air Traffic Control Tower
Design, Bidding and Permitting Services Page 6
Deliverables:
The AVE will provide the following deliverables:
1. Six paper copies of the following packages:
« Schematic Design Package
e Design Development Package
e Construction Documents
7460 / Tower Communications Package
Wetland Mitigation Plan with Boundary Survey Drawing
Permits with City of Destin, USACE, NWFWMD, FDEP, NPDES
One electronic copy of each Deliverable in a *.pdf or *.dwg format:
Minutes of all meetings
OaArAN
Proposed Schedule:
NTP from Okaloosa County
Design Kickoff (month 1)
Complete Geotechnical Investigation (month 2)
Complete Survey (month 2)
Submit Programing Study/Estimate (month 3)
Submit Design Development Plans (60% CD)/Specs/Estimate (month 6)
Design Development Review Meeting (month 6)
Submit 7460 to Obtain FCC Frequencies (month 6)
Submit Tower Communications Package (month 6)
Submit Stormwater Permit (month 6)
Submit 90% Construction Document Plans /Specs/Estimate (month 10)
Construction Document Review Meeting (month 10)
Submit Bid Plans (month 11)
Pre-Bid Meeting (month 11)
Bid Opening (month 12)
End of Proposal
Destin Airport Air Traffic Control Tower
Design, Bidding and Permitting Services Page 7
RSH
HUPROVING YOUR WORLD
Reynolds, Smith and Hills, Inc,
Proposed ATCT Location Propose Access Road
CARINE Te FUTILE A
aber (eames Leah
_ . raven ells)
Hutu pet 8 a mudauater v
FUTURE AIR RAFF —.
coeiyeoR HOTA B
NEM EGEATION
HATE AD oat
———— BONE AIC
cn Bp Kone
Seinen .
a
Exhibit 1: Site Plan
RS‘ DESTIN AIRPORT
. AIR TRAFFIC CONTROL TOWER
IMPROVING YOUR WORLD
TASK ORDER 13
PERMITTING, DESIGN AND BIDDING SERVICES
SUMMARY
BASIC SERVICES Totals
A. SCHEMATIC DESIGN
Basic Services $68,280
Subconsultant Services $19,175
Subtotal $87,455
A.2. DESIGN DEVELOPMENT
Basic Services $83,274
Subtotal $83,274
A.3 CONSTRUCTION DOCUMENTS
Basic Services $143,441
Subtotal $143,441
A4 BIDDING
Basic Services $22,742
Subtotal $22,742
BASIC SERVICES - TOTAL $336,913
SPECIAL SERVICES
B.1. AIR TRAFFIC CONTROL TOWER SPECIALIST
Subconsultant Services $30,000
Subtotal $30,000
B.2. PERMITTING SERVICES - SITE AND UTILITIES
Basic Services $41,637
Subtotal $41,637
B.3. PERMITTING SERVICES - WETLAND MITIGATION
Basic Services $15,653
Subtotal $15,653
SPECIAL SERVICES ~ TOTAL $87,290
GRAND TOTAL LUMP SUM FEE $424,203