READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — September 16, 2014 — Okaloosa Admin Building - GMP Proposal - 9-16-2014 — reading text
Part 2 of 3. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 252-Okaloosa Admin Building - GMP Proposal - 9-16-2014.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
SH1370 Trim Out Soffit/Flashing 5 06-Feb-15 13-Feb-15 150 Trim Out Soffit/Flashing 13-Feb-15
SH1260 Install Exterior Windows 10 30-Apr-15 14-May-15 56 Install Exterior Windows 14-May-15
SH1290 Install Exterior Doors 8 30-Apr-15 12-May-15 58 Install Exterior Doors 12-May-15
SH1390 Install Building Signage 5 30-Apr-15 07-May-15 97 Install Building Signage 07-May-15
SH1380 Punchout Exterior 5 14-May-15 21-May-15 92 Punchout Exterior 21-May-15
Building B ( Single Floor) 145 23-Sep-14 21-Apr-15 114 21-Apr-15, Building B
SH2000 F/R/P Spread/Continuous Footings 20 23-Sep-14 21-Oct-14 57otings 21-Oct-14
SH2020 Rough-in U/G MEP 10 22-Oct-14 04-Nov-14 57 U/G MEP 04-Nov-14
SH2050 Backfill / Compact 10 05-Nov-14 18-Nov-14 57 l / Compact 18-Nov-14
SH2060 Erect Structural Steel 5 24-Dec-14 02-Jan-15 32ect Structural Steel 02-Jan-15
SH2080 Frame Roof 10 02-Jan-15 16-Jan-15 32 Frame Roof 16-Jan-15
SH2090 Deck roof 5 16-Jan-15 26-Jan-15 32 Deck roof 26-Jan-15
SH2200 Frame Exterior Walls 10 26-Jan-15 09-Feb-15 32 Frame Exterior Walls 09-Feb-15
SH2180 Sheath Exterior Walls 10 09-Feb-15 24-Feb-15 32 Sheath Exterior Walls 24-Feb-15
SH2160 Lay Up Brick Veneer 20 24-Feb-15 24-Mar-15 32 Lay Up Brick Veneer 24-Mar-15
SH2150 Lay Pre-cast 5 17-Mar-15 24-Mar-15 32 Lay Pre-cast 24-Mar-15
SH2210 Install Breezeway Store Fronts 20 24-Mar-15 21-Apr-15 114 Install Breezeway Store Fronts 21-Apr-15
SH2170 Install Exterior Windows 10 24-Mar-15 07-Apr-15 32 Install Exterior Windows 07-Apr-15
SH2190 Install Exterior Doors 5 24-Mar-15 31-Mar-15 129 Install Exterior Doors 31-Mar-15
Interior Build
Build-out - Building A 143 12-Dec-14 09-Jul-15 59 09-Jul-15,
1st Floor 136 12-Dec-14 29-Jun-15 66 29-Jun-15, 1
Working Area
A 110 12-Dec-14 21-May-15 92 21-May-15, Work
BA1000 Rough-in MEP 40 12-Dec-14 11-Feb-15 59 Rough-in MEP 11-Feb-15
BA1020 Frame Interior Partitions 15 29-Dec-14 21-Jan-15 177 e Interior Partitions 21-Jan-15
BA1050 Hang/Finish Drywall 20 11-Feb-15 12-Mar-15 59 Hang/Finish Drywall 12-Mar-15
BA1070 Prime/1st Coat Paint 5 12-Mar-15 19-Mar-15 59 Prime/1st Coat Paint 19-Mar-15
BA1180 Trimout / Finishes 40 19-Mar-15 14-May-15 59 Trimout / Finishes 14-May-15
A1030 Punchout 1st Floor 5 14-May-15 21-May-15 59 Punchout 1st Floor 21-May-15
Rest Rooms
Roo 53 15-Dec-14 04-Mar-15 110 04-Mar-15, Rest Rooms
BA1240 Block Filland Prime 5 15-Dec-14 22-Dec-14 110ock Filland Prime 22-Dec-14
BA1110 Rough-in Plumbing 10 22-Dec-14 07-Jan-15 110Rough-in Plumbing 07-Jan-15
Remaining Level of Effort Milestone Page 3 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
BA1100 Hang / Finish Drywall 10 07-Jan-15 22-Jan-15 110Hang / Finish Drywall 22-Jan-15
BA1340 Prime/1st Coat 3 22-Jan-15 27-Jan-15 110 Prime/1st Coat 27-Jan-15
BA1350 Trimout / Finishes 25 27-Jan-15 04-Mar-15 110 Trimout / Finishes 04-Mar-15
Elevator Equipment
E 0 0
Mech/Elec Rooms 135 15-Dec-14 29-Jun-15 66 29-Jun-15, M
BA1250 Block Fill and Prime 5 15-Dec-14 22-Dec-14 125 ck Fill and Prime 22-Dec-14
BA1200 Rough-in MEP 25 22-Dec-14 29-Jan-15 125 Rough-in MEP 29-Jan-15
BA1490 Commission Fire Pumps/Sprinklers 5 29-Jan-15 05-Feb-15 128 Fire Pumps/Sprinklers 05-Feb-15
BA1500 Install Lighting 5 29-Jan-15 05-Feb-15 125 Install Lighting 05-Feb-15
BA1630 Pull Main Feed to Transformer (Rm 107) 5 29-Jan-15 05-Feb-15 161 Transformer (Rm 107) 05-Feb-15
BA1510 Trim Out Lights 3 05-Feb-15 10-Feb-15 125 Trim Out Lights 10-Feb-15
BA1590 Mount AHU-4 5 19-Mar-15 26-Mar-15 91 Mount AHU-4 26-Mar-15
BA1600 Pipe AHU-4 5 26-Mar-15 02-Apr-15 91 Pipe AHU-4 02-Apr-15
BA1530 Mount Chiller (Exterior) 3 30-Apr-15 05-May-15 54 Mount Chiller (Exterior) 05-May-15
BA4000 Land Chillers 5 30-Apr-15 07-May-15 61 Land Chillers 07-May-15
BA1550 Tie-in HVAC Piping 10 05-May-15 19-May-15 94 Tie-in HVAC Piping 19-May-15
BA1640 Pull distribution to Main Feed (Rm 107) 5 07-May-15 14-May-15 97ull distribution to Main Feed (Rm 107) 14-May-15
BA4010 Pipe Chillers To Mechanical Room 5 07-May-15 14-May-15 61 Pipe Chillers To Mechanical Room 14-May-15
BA1660 Energize Building 5 14-May-15 21-May-15 56 Energize Building 21-May-15
BA1570 Commission HVAC Units 10 08-Jun-15 22-Jun-15 45 Commission HVAC Units 22-Jun-15
BA1580 Test and Balance Ventillation 5 22-Jun-15 29-Jun-15 45 Test and Balance Ventillation 29-Jun-15
Stairwells 0 0
2nd Floor 113 06-Jan-15 17-Jun-15 74 17-Jun-15, 2n
Working Area
A 113 06-Jan-15 17-Jun-15 74 17-Jun-15, W
BA1850 Rough-in MEP 45 06-Jan-15 12-Mar-15 41 Rough-in MEP 12-Mar-15
BA1830 Frame Interior Partitions 15 21-Jan-15 11-Feb-15 162 ame Interior Partitions 11-Feb-15
BA1800 Hang / Finish Drywall 25 12-Mar-15 16-Apr-15 41 Hang / Finish Drywall 16-Apr-15
BA1780 Prime/1st Coat Paint 8 16-Apr-15 28-Apr-15 41 Prime/1st Coat Paint 28-Apr-15
BA1740 Trmiout / Finishes 30 28-Apr-15 10-Jun-15 41 Trmiout / Finishes 10-Jun-15
BA2570 Punchout 2nd Floor 5 10-Jun-15 17-Jun-15 41 Punchout 2nd Floor 17-Jun-15
Rest Rooms
Roo 53 06-Jan-15 24-Mar-15 96 24-Mar-15, Rest Rooms
Remaining Level of Effort Milestone Page 4 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle