READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — December 31, 2012 — Joint Participation Agreement - Destin Control Tower 423906-2 — reading text
Part 6 of 10. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 73-Joint Participation Agreement - Destin Control Tower 423906-2.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
725-030-06
PUBLIC TRANSPORTATION
06111
Page 14 of 14
Financial Project No( s). 42390629401
----------------------
Contract No.
Agreement Date
IN WITNESS WHEREOF, the parties hereto have caused these presents be executed, the day and year first above written.
AGENCY FOOT
Okaloosa County SOCC See attached Encumbrance Form for date of Funding
AGENCY NAME Approval by Comptroller
DON R. AMUNDS
LEGAL REVIEW
SIGNATORY (PRINTED OR TYPED)
DEPARTMENT OF TRANSPORTATION
SIGNATURE
DEPARTMENT OF TRANSPORTATION
CHAIRMAN
TITLE TITLE
FINANCIAL PROJECT # 42390629401
EXHIBIT"A"
PROJECT DESCRIPTION AND RESPONSIBILITIES
This exhibit fonns an integral part of that certain Joint Participation Agreement
between the State of Florida, Department of Transportation and Okaloosa County Board
of County Commissioners referenced by the above Financial Project Number.
PROJECT LOCATION: Destin-Ft Walton Beach Airport (DTS)
PROJECT DESCRIPTION, SCOPE OF WORK: Construct Air Traffic Control Tower,
Construct Roadway & Construct Site Utilities. Pursuant to FAA Orders 1050.1E,
Environmental Impacts: Policies and Procedures and 5050.4B and NEPA Implementing
Instructions for Airport Actions, an EA detennination is required prior to FAA
appropriating AlP funds for the DTS ATCT project. Further, design and pennit phase
services for an access road, parking lot, security fence, gate modifications, and utility
improvements to accommodate the future Air Traffic Control Tower (ATCT) at the
Destin-Fort Walton Beach Airport.
SPECIAL CONSIDERATIONS BY AGENCY:
The audit report(s) required in paragraph 7.60 of the Agreement shall include a schedule
of project assistance that will reflect the Department's contract number, Financial Project
Number and the Federal Identification number, where applicable, and the amount of state
funding action (receipt and disbursement of funds) and any federal or local funding
action and the funding action from any other source with respect to the project.
SPECIAL CONSIDERATIONS BY DEPARTMENT:
Effective July 1, 2010, Section 215.971, Florida Statutes (F.S.) now requires all new
Joint PartiCipation Agreement (JPA) the Department executes to clearly document
contract deliverables and establish minimum level of services. The JPA scope of
services will be required to clearly divide project tasks into quantifiable,
measurable, and verifiable units of deliverables that must be received and accepted
by the Department, in writing, prior to payment for services. Each deliverable must
specify the required level of service to be performed and the Department's criteria
for evaluating successful completion. Once the following items have been submitted
to and approved in writing by the Department they will be added to this JPA under
Exhibit "A" to meet the deliverable requirements under Section 215.971 F.S.:
Scope of Services
Design Phase
1. A signed copy of the approved scope of services and schedule of values
that are incorporated into an agreement between the Agency and Its third
party consultant. The scope of services must include or incorporate by
reference a schedule of values that will be used to approve and make
payments to the third-party consultant. The scope of services and included
schedule of values must be approved in writing by the Department before
the Agency enters into an agreement with its third-party consultant. The
schedule of values shall be a complete and detailed itemization describing
each subcategory of work and related pay items and their associated total
value, quantity, unit of measurement and unit price/cost. The consultant
should invoice the Agency on a regular basis using the approved schedule
of values and one of the following methods:
a. Percentage Completed. For this method the consultant's invoice should
list a detail description of each task in the approved scope of services and
schedule of values, the dollar value amount for the item, the percentage
competed for the item, and the dollar value for the percentage completed.
b. Completed Tasks. For this method the consultant's invoice should list a
detail description of each task in the approved scope of services and
schedule of values, the dollar value amount for each item, indicate which
task have been completed, and the dollar value for each task completed.
2. The Agency shall sign each invoice submitted to the Department and
certify thereon that the Agency has verified that the percentages of and/or
task completions are correct and that the amounts indicated on the invoice
are correct.
3. Any change(s) to the approved scope of services or schedule of values will
require a change order approved by the Department, and signed by the
Agency and the third-party consultant. Invoices Incorporating unapproved
changes cannot be submitted by the Agency or paid by the Department.
Construction Phase
4. A signed copy of the approved scope of services and schedule of values
that are incorporated into an agreement between the Agency and its
construction contractor. The scope of services must include or incorporate
by reference a schedule of values that will be used to approve and make
payments to the contractor. The scope of services and included schedule of
values must be approved in writing by the Department before the Agency
enters into an agreement with its contractor. The schedule of values shall
be a complete and detailed itemization describing each subcategory of
work and related pay items and their associated total value, quantity, unit
of measurement and unit price/cost. The contractor should invoice the
Agency on a regular basis using the approved schedule of values and one of
the following methods:
a. Percentage Completed. For this method the contractor's invoice should list
a detail description of each task in the approved scope of services and
schedule of values, the dollar value amount for the item, the percentage
competed for the item, and the dollar value for the percentage completed.
b. Completed Tasks. For this method the contractor's invoice should list a
detail description of each task in the approved scope of services and
schedule of values, the dollar value amount for each item, indicate which
task have been completed, and the dollar value for each task completed.
5. The contractor should submit their pay request to the Agency's project
inspector for approval using the standard It Application and Certificate for
Payment" form. The Agency's project inspector will review and approve
the contractor's pay request certifying the percentage of completion
and/or quantities are correct.
6. The Agency shall sign each invoice submitted to the Department and
certify thereon that the Agency has verified that the percentages of and/or
task completions are correct and that the amounts indicated on the invoice
are correct.
7. Any change(s} to the approved scope of services or schedule of values will
require a change order approved by the Department, and signed by the
Agency and the contractor. Invoices incorporating unapproved changes
cannot be submitted by the Agency or paid by the Department.
FINANCIAL PROJECT NO. 42390629401
EXHIBIT "B"
PROJECT BUDGET
This exhibit fonns an integral part of that certain Joint Participation Agreement between
the State of Florida, Department of Transportation and the Okaloosa County Board of County
Commissioners referenced by the above Financial Project Number.
I. ESTIMATED PROJECT COST: $1,250,000.00
TOTAL ESTIMATED PROJECT COST: $1,250,000.00
II. PARTICIPATION:
Maximum Federal Participation
FAA-Funding Direct to Agency $0.00
Agency Participation
Cash $250,000.00
Maximum Department Participation,
Primary
(DS)(DDR)(DPTO)(GMR) $1,000,000.00
TOTAL ESTIMATED PROJECT COST $1,250,000.00
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 725-040-15
AVIATION
EXHIBIT "C" OGC-03l09
Page 1 of9
AVIATION PROGRAM ASSURANCES
FINANCIAL PROJECT NO.: ,;;:::42::.::3;.:.90.:.::6=2=94~O:..:.1_ _ _ __
EFFECTIVE DATE: _ _ _ _ _ _ _ _ _ __
A. General
1. The assurances herein shall form an integral part of the Joint Participation Agreement (Agreement) between the
State of Florida, Department of Transportation (Department) and the airport sponsor, whether county or municipal
government body or special district, such as an Airport Authority (herein, collectively referred to as "Agency").
2. These assurances delineate the obligations of the parties to this Agreement to ensure their commitment and
compliance with specific provisions of Exhibit A, "Project Description and responsibilities" and Exhibit B, "Project
Buqget", as well as serving to protect public investment in public-use airports and the continued viability of the Florida
Aviation System.
3. The Agency shall comply with the assurances as specified in this Agreement.
4. The terms and assurances of this Agreement shall remain in full force and effect throughout the useful life of a
facility developed; equipment acquired; or project items installed within a facility for an airport development or noise
compatibility program project, but shall not exceed 20 years from the effective date of this Agreement.
5. There shall be no limit on the duration on the terms and assurances of this Agreement regarding Exclusive Rights
and Airport Revenue so long as the property is used as a public airport.
6. There shall be no limit on the duration of the terms