READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — December 31, 2012 — Joint Participation Agreement - Destin Control Tower 423906-2 — reading text
Part 3 of 10. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 73-Joint Participation Agreement - Destin Control Tower 423906-2.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
issued, and shall allow the Department,
or its designee. the CFO or Auditor General access to such records upon request. The Agency shall ensure that the
independent audit working papers are made available to the Department, or its designee, the CFO, or Auditor General
upon request for a period of at least five years from the date the audit report is issued, unless extended in writing by the
Department. Records of costs incurred under the terms of this Agreement shall be maintained and made available upon
request to the Department at all times during the period of this Agreement and for five years after final payment is made.
Copies of these documents and records shall be furnished to the Department upon request. Records of costs incurred
include the Participant's general accounting records and the project records, together with supporting documents and
records, of the contractor and all subcontractors performing work on the project. and all other records of the Contractor
and subcontractors considered necessary by the Department for a proper audit of costs.
7.64 Other Requirements: If an audit discloses any significant audit findings related to any award, including
material noncompliance with individual project compliance requirements or reportable conditions in internal controls of the
Agency, the Agency shall submit as part of the audit package to the Department a plan for corrective action to eliminate
such audit findings or a statement describing the reasons that corrective action is not necessary. The Agency shall take
timely and appropriate corrective action to any audit findings, recommendations, and corrective action plans.
725-030-06
PUBLIC TRANSPORTATION
06/11
Page 7 of 14
7.65 Insurance: Execution of this Joint Participation Agreement constitutes a certification that the Agency has
and will maintain the ability to repair or replace any project equipment or facilities in the event of loss or damage due to
any accident or casualty for the useful life of such equipment or facilities. In the event of the loss of such equipment or
facilities, the Agency shall either replace the equipment or facilities or reimburse the Department to the extent of its
interest in the lost equipment or facility. In the event this Agreement is for purchase of land or for the construction of
infrastructure such as airport runways the Department may waive or modify this section.
8.00 Requisitions and Payments:
8.10 Action by the Agency: In order to obtain any Department funds, the Agency shall file with the Department
of Transportation, District Three Public Transportation Office 1074 Hwy 90 East, Chipley, FL , FL,
32428 its requisition on a form or forms prescribed by the Department, and any other data pertaining to
the project account (as defined in Paragraph 7.10 hereof) to justify and support the payment requisitions.
8.11 Invoices for fees or other compensation for services or expenses shall be submitted in detail
sufficient for a proper preaudit and postaudit thereof.
8.12 Invoices for any travel expenses shall be submitted in accordance with Chapter 112.061, F .5.
The Department may establish rates lower than the maximum provided in Chapter 112.061, F.S.
8.13 For real property acquired, submit;
(a) the date the Agency acquired the real property,
(b) a statement by the Agency certifying that the Agency has acquired said real property, and
actual consideration paid for real property.
(c) a statement by the Agency certifying that the appraisal and acquisition of the real property
together with any attendant relocation of occupants was accomplished in compliance with all
federal laws, rules and procedures required by any federal oversight agency and with all state
laws, rules and procedures that may apply to the Agency acquiring the real property.
8.20 The Department's Obligations: Subject to other provisions hereof, the Department will honor such
requisitions in amounts and at times deemed by the Department to be proper to ensure the carrying out of the project
and payment of the eligible costs. However, notwithstanding any other provision of this Agreement, the Department
may elect by notice in writing not to make a payment on the project if:
8.21 Misrepresentation: The Agency shall have made misrepresentation of a material nature in its application,
or any supplement thereto or amendment thereof, or in or with respect to any document or data furnished therewith or
pursuant hereto;
8.22 Litigation: There is then pending litigation with respect to the performance by the Agency of any of its duties
or obligations which may jeopardize or adversely affect the project, the Agreement, or payments to the project;
8.23 Approval by Department: The Agency shall have taken any action pertaining to the project which, under
this agreement, requires the approval of the Department or has made related expenditures or incurred related
obligations without having been advised by the Department that same are approved;
8.24 Conflict of Interests: There has been any violation of the conflict of interest provisions contained herein;
or
8.25 Default: The Agency has been determined by the Department to be in default under any of the
provisions of the Agreement.
8.26 Federal Participation (If Applicable): Any federal agency providing federal financial assistance to the
project suspends or terminates federal financial assistance to the project. In the event of suspension or termination of
federal financial assistance, the Agency will reimburse the Department for all disallowed costs, including any and all
federal financial assistance as detailed in Exhibit "B."
725-()~
PUBLIC TRANSPORTATION
06/11
Page 8 of 14
8.30 Disallowed Costs: In determining the amount of the payment, prior to receipt of annual notification of funds
availability, the Department will exclude all projects costs incurred by the Agency prior to the effective date of this
Agreement, costs which are not provided for in the latest approved budget for the project, and costs attributable to goods
or services received under a contract or other arrangements which have not been approved in writing by the Department
and costs invoiced prior to receipt of annual notification of fund availability.
8.40 Payment Offset: If, after project completion, any claim is made by the Department resulting from an audit
or for work or services performed pursuant to this agreement, the Department may offset such amount from payments
due for work or services done under any public transportation joint participation agreement which it has with the Agency
owing such amount if, upon demand, payment of the amount is not made within Sixty (60) days to the Department.
Offsetting amounts shall not be considered a breach of contract by the Department.
9.00 Termination or Suspension of Project:
9.10 Termination or Suspension Generally: If the Agency abandons or. before completion, finally discontinues
the project; or if, by reason of any of the events or conditions set forth in Sections 8.21 to 8.26 inclusive. or for any other
reason. the commencement, prosecution, or timely completion of the project by the Agency is rendered improbable,
infeasible, impossible, or illegal. the Department will, by written notice to the Agency, suspend any or all of its
obligations under this Agreement until such time as the event or condition resulting in such suspension has ceased or
been corrected, or the Department may terminate any or all of its obligations under this Agreement.
9.11 Action Subsequent to Notice of Termination or Suspension. Upon receipt of any final termination or
suspension notice under this paragraph, the Agency shall proceed promptly to carry out the actions required therein
which may include any or all of the following: (1) necessary action to terminate or suspend, as the case may be, project
activities and contracts and such other action as may be required or desirable to keep to the minimum the costs upon the
basis of which the financing is to be computed; (2) furnish a statement of the project activities and contracts. and other
undertakings the cost of which are otherwise includable as project costs; and (3) remit to the Department such portion of
the financing and any advance payment previously received as is determined by the Department to be due under the
provisions of the Agreement. The termination or suspension shall be carried out in conformity with the latest schedule.
plan. and budget as approved by the Department or upon the basis of terms and conditions imposed by the Department
upon the failure of the Agency to furnish the schedule, plan. and budget within a reasonable time. The approval of a
remittance by the Agency or the closing out of federal financial participation in the project shall not constitute a waiver of
any claim which the Department may otherwise have arising out of this Agreement.
9.12 The Department reserves the right to unilaterally cancel this Agreement for refusal by the contractor
or Agency to allow public access to all documents. papers, letters, or other material subject to the provisions of Chapter
119. F .S. and made or received in conjunction with this Agreement.
10.00 Remission of Project Account Upon Completion of Project: Upon completion of the project. and after
payment. provision for payment, or reimbursement of all project costs payable from the project account is made, the
Agency shall remit to the Department its share of any unexpended balance in the project account.
11.00 Audit and Inspection: The Agency shall permit, and shall require its contractors to permit, the
Department's authorized representatives to inspect all work, materials, payrolls, records; and to audit the books, records
and accounts pertaining to the financing and development of the project.
12.00 Contracts of the Agency:
12.10 Third Party Agreements: Except as otherwise authorized in writing by the Department, the Agency shall
not execute any contract or obligate itself in any manner requiring the disbursement of Department joint participation
funds, including consultant, construction or purchase of commodities contracts or amendments thereto, with any third
party with respect to the project without the written approval of the Department. Failure to obtain such approval shall be
sufficient cause for nonpayment by the Department as provided in Section 8.23. The Department speCifically reserves
unto itself the right to review the qualifications of any consultant or contractor and to approve or disapprove the
employment of the same.