Preliminary plans have been completed concerning the need for and location of the proposed
tank and connecting water main. As soon as grant funds are awarded, final design and plans will
be completed. Project will be ready for bid within 90 days of grant award agreement date, with
bids taken within another 45 days. Project will be awarded within 45 more days and project will
be scheduled for completion within 500 days, for a total time from grant award to project
completion of 680 days, well within the 24 months allowed for projects utilizing this grant funding.
b) Provide milestones and projected start and
completion dates for each task. Please provide projected dates for tasks such as planning,
design, permitting, construction, and project completion. Estimated start and completion
dates should be designated by month from contract initiation (e.g. “Month 1,” “Month 2,” etc.).
Task Start Date Completion Date
Cooperative Agreement with District | Jan 2014 2/14/14
Final Design and Bid Doc Preparation 2/15/14 5/16/14
Project Bid Process 5/17/14 6/30/14
Project Award 7/1114 8/14/14
Project Construction 8/14/14 12/27/15
Final Project Summary Report 1/31/16
Financial/ Expenditure Documentation 1/31/16
C) Describe project deliverables. Deliverables
must include a final project summary report and financial/expenditure documentation, as well
as other items as appropriate for the given project.
Final bid documents, all required permits, design documents for connecting water main,
advertisement for bid, award recommendation to Board of Commissioners, notice of award to
Contractor, project contract, final project summary report and financial/expenditure
documentation
Community Assistance Initiative Application Page 9
Submit this application with any supporting information to:
Paul Thorpe
Northwest Florida Water Management District
81 Water Management Drive
Havana, FL 32333
Paul. Thorpe@nwfwmd.state.fl.us
Applications may be submitted by mail or electronic mail. It is strongly recommended that
applications be sent with read receipt enabled (if electronic submittal) or with return receipt
required (if sent by mail).
Applications must be received at District Headquarters by Thursday,
October 31, 2013.
Any questions may be directed to Paul Thorpe at the e-mail address listed above or by
calling (850) 539-5999
Community Assistance Initiative Application Page 10