BOARD OF COUNTY COMMISSIONERS
OKALOOSA COUNTY, FLORIDA
SERVICE AREA: TRANSPORTATION
DEPARTMENT/PROGRAM: TRAFFIC DIVISION
PROGRAM DESCRIPTION: The Traffic Engineering/Operations Division’s mission is to administer,
manage, maintain and operate the Advanced Traffic Control System (ATCS), this includes the safe and efficient
continuous operation of all signalized intersections. A Florida Department of Transportation (FDOT) joint
program assists with the expenses associated with the administration and operations of the ATCS. The Traffic
Divisions will work closely with the public, FDOT, local governments, contractors, and designers to help
manage and provide within our means the safest system and highest level of service for the traveling public.
REVENUE: Traffic Division is funded within the County Transportation Trust Fund. Supporting revenue of
the County Transportation Trust Fund is: fuel tax, intergovernmental revenue, charges for services,
miscellaneous revenues, and transfers. Additional funding for the Traffic division comes from an annual FDOT
joint program.
EXPENDITURES:
Expenditures Budget
FY11 FY12 FY13 FY14
Category Actual $ Actual $ Original $ Approved $
Personal Services 327,100 307,246 310,008 327,592
Operating Expenses 151,886 110,781 167,433 170,594
Capital Outlay 47,115 45,282 32,200 32,200
Reserves 0 0 0 0
Total 526,101 463,309 509,641 530,386
HISTORICAL STAFFING SUMMARY:
Category FY11 FY12 FY13 FY14
Full-time 5 5 5 5
Part-Time 0 0 0 0
Relief 0 0 0 0
Total 5 5 5 5
MAJOR ACCOMPLISHMENTS LAST YEAR:
Managed Traffic Division’s budget and an annual Florida Department of Transportation joint program.
Managed and coordinated traffic signal and vehicle detection operations for the FDOT SR 85 (Eglin
Parkway) resurfacing project.
Assisted the FDOT in the design of US 98/Cody Ave flyover project as related to traffic signal systems.
Provided a list of seventeen county wide locations for intersection operations and safety improvements.
Ensure proper functionality of all components of signalized intersections; maintaining all communications
equipment in both the field and office; and overseeing all construction projects in the County related to any
resurfacing, signal, or utility work.
PROGRAM GOAL:
Traffic Engineering Goals:
Long Range Goal: The engineering division will continue to manage the ATCS and signalized intersections in a
direction encouraging enhancement and upgrades of the existing system via a strategic plan.
Short Range Goals:
1. Follow the mission statement/strategic plan related to Traffic Division and the ATCS.
2. Seek new technologies used in Intelligent Transportation Systems.
3. Manage existing timings and adjust as necessary.
4. Implement these newer technologies in the ATCS.
5. Seek additional video and traffic monitoring capabilities.
6. Improve traffic flow along major arterials with emphasis on peak AM and PM traffic.
7. Plan and design for a traffic operations management center.
Traffic Operations Goals:
Long Range Goal: The operations division will continue providing a high standard of customer service, and
maintenance operations with the strategic plan in mind.
Short Range Goals:
1. Continue working closely with citizens to maintain efficient operations.
2. Continue working closely with contractors and designers.
3. Continue meeting industry standards to maintain a high quality product.
4. Follow a strategic plan for upgrading and integrating newer technologies into the existing ATCS.
5. Improve operations and reduce maintenance costs at critical intersections – a critical intersection is defined
as one that requires law enforcement traffic control during power outages and/or equipment failures that
cause flashing operation.
6. Protect and locate all underground utilities associated with the system (both fiber and copper); ensure proper
functionality of all components of signalized intersections; maintain all communications equipment in both
the field and office; and oversee all construction projects in the County related to any resurfacing, signal, or
utility work.
KEY OBJECTIVES:
1. Ensure budgetary, personnel and purchasing functions comply with County policies and procedures.
2. Provide timely and courteous assistance to citizens.
3. Provide effective and thorough review of all signal design and timing activities.
4. Continue to evaluate more effective alternatives for traffic signal maintenance.
5. Continue to evaluate more effective alternatives for optimizing traffic signal control and systems.
6. Provide timely response to Public works, County Administrator and County Commission and requests.
7. Monitor and assess future needs for Intelligent Transportation System through use of state of the art
technology.
8. Operate and maintain continuously 181 traffic control devices of which 153 are signals and beacons, 212
highway lights and safeguards over 80 miles of underground utilities.
9. Continue the addition of closed circuit cameras for monitoring only traffic conditions and operations.
PERFORMANCE MEASURES:
Actual Estimated Adopted
Performance Measures
FY11/12 FY12/13 FY13/14
Number of Employees 6 6 6
Input
Operating Budget $176,292 $164,000 $170,594
Capital Outlay $40,400 $38,000 $32,200
Routine Intersection Inspections planned 1773 1772 1770
Trouble Calls via Citizen/Sheriff 89 82 80
Emergency Callouts: afterhours flash or dark 61 48 50
Output
Underground Utility Locate Tickets: 5520 5278 5270
Incident, Traffic Equip Damage 11 8 0
Plan review, Project inspections 13 10 10
Routine Intersection Inspections completed 1441 1722 1770
All Trouble Calls addressed 314 290 80
Efficiency
Emergency Callouts: afterhours flash or dark 61 48 50
Locate Tickets Processed 1388 1128 1100
Damaged Equip: response/repaired within 2 days 11 8 0
Effectiveness
Routine Inspections 81% 97% 100%
Funding Ratio FDOT to County 2.15 : 1 1.57 : 1 1.56 : 1