READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — April 9, 2013 (meeting #1123) — reading text
Part 16 of 25. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 01-Agenda Packet.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Attachment: Budget Policy Document FY14 (1578 : Budget Policy Document)
Holt Park – $200,000 (Unincorporated)
• Laurel Hill Rails to Trails (Old railroad right-of-way) - $10,000 - upgrade railroad bed for walking trail,
benches, trail head parking and port-o-let (Unincorporated)
The Florida Boating Improvement Program (FBIP) continues to be a source of funding to provide water
recreation facilities. This revenue funds replacement of “No Wake Zone” signs and pilings, repair and
maintenance of boat ramps, and support facilities. In addition, it provides funding for the Derelict Vessel
Removal Program. FBIP can also provide allocations up to $15,000 for local municipalities within Okaloosa
County for various approved projects.
Solid Waste Program Public Works’ challenge in Fiscal Year 2014 will be to continue monitoring two solid
waste contracts, increase recycling participation, and work toward the goal of reducing long-term care and
maintenance costs for the three closed landfills, which totals approximately $875,000 annually. In Fiscal Year
2013, Public Works moved forward with a plan to expand its control over the municipal solid waste stream in
unincorporated Okaloosa County by conducting a public hearing giving notice of its intent to franchise
commercial garbage collection in the year 2016. This would provide Okaloosa County control of
approximately 50 percent of the waste stream, thereby positioning the County to competitively bid all solid
waste services to begin upon termination of the existing contracts on March 31, 2016. This bid will include
enhanced recycling, commonly called “1-1-1”, for all residents within the County’s five franchise areas. The
ultimate goal is to increase recyclable collections from the residential and commercial waste stream in an effort
to comply with the State mandated recycling goal of 75 percent by 2020.
Additionally in Fiscal Year 2014, the County will explore opportunities to encourage recycling within the
school district and the construction and demolition debris disposal industry. Yard trash operations will continue
to be managed in-house with the addition of contract grinding at the Wright Yard Trash Facility versus the
replacement ($850,000) of an existing grinder that is in the county inventory. Solid waste and recycling
budgets will be combined into one budget to reduce the administrative duplication of managing two divisions
instead of one. Staff will continue to explore ways to expand household hazardous waste services for local
residents in order to make the service more convenient for residents to dispose of household chemicals. This
may necessitate the creation of two technician positions to operate these services on a full time basis in Fiscal
Year 2015.
Fiscal Year 2013 was a transitional period for the active remediation systems at Baker Landfill (BLF) and
Wright Landfill (WLF). BLF and WLF infrastructure changes made to comply with remedial systems
modifications began in Fiscal Year 2012 and will be completed in Fiscal Year 2013. Cost reductions from these
infrastructure changes will be realized in the Fiscal Year 2014 budget. A slight increase in operation and
Page 28
Packet Pg. 35
1.b
maintenance costs associated with the remediation systems infrastructure changes is projected in order to
achieve cleanup and operational goals. A reduction in reporting requirements will further reduce the cost of
Long-Term-Care at BLF and WLF.
Private property access continues to be an issue at BLF. The County has groundwater monitoring infrastructure
on four privately owned parcels. Of the four, only one is covered by an access agreement. Two of the
remaining three changed owners in 2012-2013 and the County is actively pursuing access agreements. The
remaining parcel owner is currently in active negotiations with the County for long-term access. If access to
property agreements cannot be secured in Fiscal Year 2013, the County may be forced to abandon six
monitoring wells located on private property and reinstall the wells in a County easement.
Attachment: Budget Policy Document FY14 (1578 : Budget Policy Document)
Real estate agreements for Niceville Landfill (NLF) and WLF on United States Air Force (USAF) property are
projected to be in place by the end of Fiscal Year 2013. Individual agreements have been approved by the
Board and are awaiting signatures from the USAF. No additional costs will be incurred by the County in the
new agreements. In lieu of property use fees, landscaping and yard debris generated in the USAF cantonment
area at Eglin are processed and repurposed by the County at no cost to the USAF.
The field activities associated with the NLF remediation pilot study will be complete in Fiscal Year 2013. All
costs associated with field operations have been captured in the Fiscal Year 2013 budget. However, reporting
activities and costs could extend into the next fiscal year. County staff was successful in securing a passive
remediation strategy at NLF and the active pilot study remediation system will subsequently be
decommissioned at the end of the test. The passive remediation strategy is Monitored Natural Attenuation
(MNA). MNA has no active environmental cleanup infrastructure. Cleanup goals are achieved by allowing
natural environmental processes to reduce the concentration of contaminants. The County will continue to
assess the existing monitoring well network to validate the reduction in chemical concentrations. Three
additional monitoring wells have been budgeted to be installed in Fiscal Year 2013. However, the installation
of the wells is dependent on an in-place real estate agreement. If the USAF does not execute the real estate
agreement by September 2013, the cost of the well installations will be reflected in the Fiscal Year 2014 budget.
Transportation Okaloosa County maintains 201 miles of dirt roads, 74 miles of cold mix base stabilized roads,
666 miles of paved roads, and 73 bridges and large box culverts. The County accepted approximately 2 miles
of paved roads into the maintenance system in Fiscal Year 2013. The current revenue allocated for capital
transportation projects, including resurfacing and dirt to pave programs, is acquired through the Constitutional
Gas Tax (CGT) and the Local Option Gas Tax (LOGT). Average revenue from these sources in previous years
totaled approximately $3,500,000 per year.
The annual projection for resurfacing has been restructured to reflect pavement preservation and pavement
management techniques. These diverse methods stretch the County’s funding dollars to allow the maximum
benefit per dollar expended. Current funding is $500,000 per year, of which $20,000 per district is available for
other transportation-related expenses to the five districts. The remaining $400,000 allows staff to implement
pavement preservation techniques on roadways throughout the unincorporated areas of the County.
For Fiscal Year 2014, Public Works is planning to resurface over 4 miles of asphalt roads (under a pavement
management/pavement preservation strategy); provide further stabilization and or surface preservation
treatments to existing cold mix stabilized roads, continue the road striping program (under a pavement marking
management structure); and continue with the dirt-to-pave hot mix asphalt program.
Page 29
Packet Pg. 36
1.b
Existing dirt roads being considered for dirt-to-pave hot mix asphalt paving include Davis Road in Laurel Hill,
Hare Street and Taylor Road in Crestview, and Riley Barnhill Road in Baker. Aging cold mix stabilized roads
that are planned for further preservation and stabilization include Robin Road, Batten Road, Bear Head Road,
Bluebird Lane, and Perry Smith Road. The remaining dirt portion of Fairchild Road in Crestview is currently
under design as a dirt-to-pave project with construction scheduled to begin in Fiscal Year 2014.
Martin Luther King, Jr. and Green Acres Boulevards are being designed for mill and resurface with full depth
reclamation along with various drainage improvements. Mount Olive Road is also being considered for a mill
and resurfacing project. Completion of these projects depends upon gas taxes and will be completed based
upon revenue availability.
Attachment: Budget Policy Document FY14 (1578 : Budget Policy Document)
For Fiscal Year 2014, the Bridge Section will budget to convert two short length wood bridges (Trawick Creek
at Wilkerson Bluff Road and Turkey Hen Creek at Antioch Road tentatively) to concrete spans. Material costs
to reconstruct both bridges will be budgeted for a total of $200,000 to continue the 20-year program to convert
all wooden bridges to concrete.
During Fiscal Year 2013, Public Works was able to accomplish several much needed roadway improvement
projects. Projects completed during the year include the full depth reconstruction of Antioch Road (from
Brodie Lane to Wilks Drive) and the paving of the remaining dirt portion of Keyser Mill Road (from Skeeter
Lane to Galiver Cutoff). Clear Creek Road and West Plympton Road are dirt-to-pave projects that were also
completed.
From a planning and design perspective, Okaloosa County continues to develop improvement plans for both
Okaloosa Lane and P.J. Adams Parkway. The Federal Highway Administration has received the final review
package from the County, as approved by the Florida Department of Transportation (FDOT), for the Project
Development & Environment (PD&E) Study of P.J. Adams Parkway/Antioch Road from SR 85 to US 90.
Once approved, it is hoped that this study will lead the way for future design improvements and funding
alternatives. As construction is being performed along Martin Luther King Jr. Boulevard and Fairchild Road,
efforts to acquire the necessary right of way and finalize the design drawings for improvements to the unpaved
portion of Okaloosa Lane and the adjacent Holley Drive are being performed. As soon as right of way is
acquired, paving the final section of Okaloosa Lane will commence.
Though these projects are not controlled by Okaloosa County, Public Works staff is heavily involved with the
design and construction of the interchange between Cody Avenue and US 98 at the Hurlburt Field main gate.
Recently, the Governor’s office announced that funding for the widening of SR 123 has been approved and staff
will continue to participate in the development of that project. It is also anticipated that FDOT will provide
funding through Local Agency Program (LAP) agreements for safety improvements to Airport Road in the
Crestview area and Sidewalks along 12th Street in the Shalimar area. Along with periodic “push-button”
projects, it is estimated that approximately $70 million in construction projects will be active in Okaloosa
County through FDOT activities during Fiscal Year 2014.
Stormwater The Stormwater staff is tasked with addressing all stormwater construction, failures, maintenance,
regulatory compliance, and development of a future funding needs list. The Board made a commitment to
pledge $400,000 for Fiscal Year 2013 to address stormwater needs.