Okaloosa County BOCC — April 27, 2013 — Construction_CEI_LAPAgreement — reading text
Part 6 of 7. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 121-Construction_CEI_LAPAgreement.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
AND RESPONSIBILITIES
FPN: 428115-1-58-01 & 428115-1-68-01
This exhibit forms an integral part of the Agreement between the State of Florida, Department of Transportation and
Okaloosa County Board of County Commissioners.
PROJECT LOCATION:
The project is X is not on the National Highway System.
The project is X is not on the State Highway System.
PROJECT DESCRIPTION:
th th
This project consists of constructing sidewalk on the south side of 12 Avenue from 12 Street to SR 85 (Eglin Parkway)
in Shalimar.
SPECIAL CONSIDERATIONS BY AGENCY:
The audit report(s) required in the Agreement shall include a Schedule of Project Assistance that will reflect the
Department’s contract number, the Financial Project Number (FPN), the Federal Authorization Number (FAN), where
applicable, the amount of state funding action (receipt and disbursement of funds), any federal or local funding action, and
the funding action from any other source with respect to the project.
The Agency is required to provide a copy of the design plans for the Department’s review and approval to coordinate
permitting with the Department, and notify the Department prior to commencement of any right-of-way activities.
The Agency shall commence the project’s activities subsequent to the execution of this Agreement and shall perform in
accordance with the following schedule:
a) Construction to be completed by December 31, 2013.
If this schedule cannot be met, the Agency will notify the Department in writing with a revised schedule or the project is
subject to the withdrawal of federal funding.
The Agency shall be responsible for verifying that the NEPA document is adhered to for the life of the project.
This project will be constructed within existing right of way.
No work shall begin until a Notice to Proceed is issued by the Department.
SPECIAL CONSIDERATIONS BY DEPARTMENT:
The Cultural Resource Assessment Survey (including coordination with the State Historic Preservation Officer) and all
documentation necessary to support the environmental Class of Action Determination will be the responsibility of the
Department.
The Department will reimburse the Agency for the eligible costs directly related to the construction and construction
engineering inspection(CEI) not to exceed $170,818.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525-010-40
PRODUCTION SUPPORT
LOCAL AGENCY PROGRAM AGREEMENT 09/11
Page
EXHIBIT “B”
SCHEDULE OF FUNDING
AGENCY NAME & BILLING ADDRESS FPN: 428115-1-58-01 & 428115-1-68-01
Okaloosa County B.O.C.C.
1759 South Ferdon Blvd.
Crestview, FL 32536
PROJECT DESCRIPTION
th
Name: 12 Avenue Sidewalk Project Length: 0.944 Miles
Termini: From 12th Street to SR 85 (Eglin Parkway)
FUNDING
(1) (2) (3)
TOTAL AGENCY STATE &
TYPE OF WORK By Fiscal Year PROJECT FUNDS FUNDS FEDERAL FUNDS
Planning FY: 2013
FY: 2014
FY: 2015
Total Planning Cost
Project Development & Environment (PD&E)
FY: 2013
FY: 2014
FY: 2015
Total PD&E Cost
Design FY: 2013
FY: 2014
FY: 2015
Total Design Cost
Right-of-Way FY: 2013
FY: 2014
FY: 2015
Total Right-of-Way Cost
Construction FY: 2013 $153,736 $0.00 $153,736
FY: 2014
FY: 2015
FY: 2016
Total Construction Cost $153,736 $153,736
Construction Engineering and Inspection (CEI)
$17,082 $0.00 $17,082
FY: 2013
FY: 2014
FY: 2015
Total CEI Cost $17,082 $0.00 $17,082
Total Construction and CEI Costs $170,818 $170,818
TOTAL COST OF THE PROJECT $170,818 $170,818
The Department's fiscal year begins on July 1. For this project, funds are not projected to be available until after the 1st of July of
each fiscal year. The Department will notify the Agency, in writing, when funds are available.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525-010-40
PROJECT MANAGEMENT OFFICE
LOCAL AGENCY PROGRAM AGREEMENT 07/09
Page
EXHIBIT “C”
RESTRICTION ON CONSULTANT’S ELIGIBILITY TO COMPETE FOR
DEPARTMENT ASSISTED CONTRACTS
FPN: 428115-1-58-01 & 428115-1-68-01
This exhibit forms an integral part of the Agreement between the State of Florida, Department of Transportation
and the Okaloosa County B.O.C.C.
EXISTING CONSULTANT CONTRACTS:
Existing consultant or professional services contracts shall not be used in the development and delivery of this project,
doing so will federalize the existing contract. All consultant and professional services contracts associated with this
project shall be advertised and selected in accordance with the Consultants Competitive Negotiations Act(CCNA).
Consult the District LAP Administrator for the appropriate federal language that must appear in each consultant contract.
CONSULTANT CEI CONTRACTS:
A consultant firm or its affiliate that was the engineer of record(EOR) on a project shall not be considered for construction
engineering and inspection(CEI) services, as a prime, on the same project.
A consultant firm or its affiliate who was the EOR on a project may only be considered for CEI services as a sub
consultant to the prime CEI firm with the approval of the Department prior to submittal of letters of response.
A consultant firm or its affiliate who was the sub to the EOR on a project may only be considered for CEI services, as
prime, on the same project, with the approval of the Department prior to submittal of letters of response.
The Department’s approval shall be based on the extent of the firm’s involvement in the design of the project or CEI
services, as the case may be, and the potential of hindrance I of any objective decision making.
A consultant or its affiliate who performed geotechnical services for the EOR shall not be considered as a sub to the firm
providing CEI services on the same project, in any capacity.
DESIGN-BUILD CONTRACTS:
The contractor or design professional cannot team, as a prime, with other firms to submit more than one bid per project.
The secondary member (i.e., designer or contractor) of the design-build team cannot change, after award, without the
written approval of the Department.
A professional firm shall not be considered for CEI services, either as a prime or a sub, for a Design-Build contract for
which the same firm or its affiliate is the EOR or is sub to the EOR.
A consultant firm, its affiliate, or sub consultant that is under contract with the Local Agency to develop the RFP for a
Design-Build contract cannot be part of a Design-Build Team proposing on that contract as a prime or a sub consultant. A
consultant firm, its affiliate, or sub consultant that is under contract with the Local Agency to provide CEI services on the
Design-Build contract cannot be part of a Design-Build Team proposing on that contract as a prime or sub consultant.
A consultant or its affiliate, who was the prime EOR on a Design-Bid-Build project, where the project is switched to
Design-Build, may participate on a Design-Build contract with the approval of the Department. The Department shall
consider level of design (% completed) by the EOR, the number of component design plans by different EOR’s, etc.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525-010-40
PRODUCTION SUPPORT
LOCAL AGENCY PROGRAM AGREEMENT 08/06
Page
EXHIBIT “1”
SINGLE AUDIT ACT
Federal Resources Awarded to the Recipient Pursuant to This Agreement Consist of the Following:
Federal Agency: Federal Highway Administration
CFDA #: 20.205 Highway Planning and Construction
Amount: FPID 428115-1-58-01 & 428115-1-68-01…………………………………………………………………$170,818
Compliance Requirement:
Allowable Activities: To be eligible, most projects must be located on public roads that are not functionally classified as
local. The major exceptions are the Highway Bridge Replacement and Rehabilitation Program, which provides assistance
for bridges on and off the federal-aid highways, highway safety activities, bicycle and pedestrian projects, transportation
enhancement activities, the recreational trails program, and planning, research, development, and technology transfer.
Proposed projects meeting these and other planning, design, environmental, safety, etc., requirements can be approved
on the basis of state and local priorities within the limit of the funds apportioned or allocated to each state.
Allowable Costs: Eligible activities and allowable costs will be determined in accordance with Title 23 and Title 49
C.F.R. and the OMB cost principles applicable to the recipient/sub-recipient.
Eligibility: By law, the federal-aid highway program is a federally assisted state program that requires each state to have
a suitably equipped and organized transportation department. Therefore, most projects are administered by or through
State Departments of Transportation