D3 TA APPLICATION
2017
Page 1 of 4
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
DISTRICT 3 APPLICATION
TRANSPORTATION ALTERNATIVES (TA) SET-ASIDE
Date: February 9, 2017 TPO (If Applicable): Okaloosa-Walton Transportation Planning Organization
Project Title: 4th Avenue Sidewalk Addition, Shalimar, Florida
Project Sponsor Okaloosa County Board of County Commissioners
According to 23 USC 133(h(4)(B) a project sponsor may be a local government; regional transportation
authority; transit agency; natural resource or public land agency; school district, local education agency, or
school; tribal government; a non-profit entity responsible for the administration of local transportation
safety programs; or other local or regional governmental entity with responsibility for oversight of
transportation or recreational trails (other than a metropolitan planning organization or a state agency) that
the State determines to be eligible, consistent with the goals of this subsection.
Contact Jason T. Autrey, P.E. Title Public Works Director
Address 1759 S. Ferdon Blvd., Crestview, FL 32539
Phone 850-689-5772 Fax 850-689-5715
e-mail address: jautrey@co.okaloosa.fl.us
Priority (relative to other applications submitted by the Project Sponsor) 4 of 6
Name of Applicant (If other than Project Sponsor):
1. Qualifying Transportation Alternatives Activities: (23 USC 101 (1)(a)(29) or former 23 (USC 213(b)(1)
TA Set-Aside projects must benefit the general public (23 CFR 1.23 and CFR 460.2).
Check the Transportation Alternatives Program (TAP) activity that the proposed project will address.
(NOTE: Checking all activities possible does not ensure or increase eligibility. Each activity checked
must meet all criteria required by FHWA.
X Construction, Planning, and Design of on-road and off-road trail facilities for pedestrians,
bicyclists, and other non-motorized forms of transportation including sidewalks, bicycle
infrastructure, pedestrian and bicycle signals, traffic calming techniques, lighting and other
safety-related infrastructure, and transportation projects to achieve compliance with the
Americans with Disabilities Act of 1990
X Construction, planning, and design of infrastructure-related projects and systems that will
provide safe routes for non-drivers, including children, older adults, and individuals with
disabilities to access daily needs
Conversion and use of abandoned railroad corridors for trails for pedestrians, bicyclists, or
other non-motorized transportation users
Construction of turnouts, overlooks, and viewing areas
Community improvement activities, including:
o Inventory, control, or removal of outdoor advertising;
o Historic preservation and rehabilitation of historic transportation facilities;
o Vegetation management practices in transportation rights-of-way to improve roadway
safety, prevent against invasive species, and provide erosion control; and
o Archaeological activities relating to impacts from implementation of a transportation
project eligible under 23 USC.
D3 TAP APPLICATION
2017
Page 2 of 4
Any environmental mitigation activity, including pollution prevention and pollution abatement
activities and mitigation to:
o Address storm water management, control, and water pollution prevention or abatement
related to highway construction or due to highway runoff including activities described in
23 USC 133(b)(3) [as amended under the FAST Act], and 328(a) and 329 of Title 23; or
o Reduce vehicle-caused wildlife mortality or to restore and maintain connectivity among
terrestrial or aquatic habitats.
The Recreational Trails Program under 23 USC 206 – Contact Pamela Lister at Department
of Environmental Protection, Office of Greenways and Trails (850) 245-2065, or email
Pamela.Lister@dep.state.fl.us for further information.
Safe Routes to School Projects – Contact Barbara Lee at (850) 330-1428, or email
Barbara.Lee@dot.state.fl.us for further information.
Planning, designing, or constructing boulevards and other roadways largely in the right-of-way of
former Interstate System routes or other divided highways.
2. Project Description:
Use additional sheets as necessary to respond to the following:
(a) Provide a clear and concise detailed description of the Transportation Alternatives project. For
sidewalks and multi-use paths, include the preferred width and construction material, (i.e.
concrete or asphalt surface). If the project is located parallel to a roadway include which side of
roadway is proposed for the construction, and note any unique or special features that may be
necessary which have been identified (such as boardwalks, bridges, drainage, guardrail, etc.).
(b) What type of work is being proposed? (Check all that apply)
Planning Activities
Project Development and Environmental Studies
X Engineering and Final Plans Preparation Work
Right of Way Acquisition
X Construction
X Construction Engineering and Inspection Activities
(c) Where is the project located (and what is the project length and termini, if appropriate)? Include
location map.
(d) Summarize any special characteristics of project. Provide typical section drawings for
appropriate projects.
(e) Describe the project's existing right of way ownerships. This description shall identify when the
right of way was acquired and how ownership is documented (i.e. plats, deeds, prescriptions,
certified surveys).
(f) Describe any proposed right of way acquisition, including expected matching fund source,
limitations on fund use or availability, and who will acquire and retain ownership of proposed right
of way.
(g) Describe any related project work phases that are already complete or currently underway.
(h) Other specific project information that should be considered.
D3 TAP APPLICATION
2017
Page 3 of 4
3. Project Implementation Information:
Attach documentation as exhibits to this application.
(a) Describe the proposed method of performing (i.e. contract or in-house) and administering (i.e.
local or state) each work phase of the project. If it is proposed that the project be administered
by a governmental entity other than the Department of Transportation, the agency must be
certified to administer Federal Aid projects in accordance with the department’s Local Agency
Program Manual (Procedure No. 525-010-300).
(b) Describe any public (and private, if applicable) support of the proposed project. (Examples
include: written endorsement, formal declaration, petition, resolution, public meetings, financial
donations or other appropriate means).
(c) Describe the proposed ownership and maintenance responsibilities for the project when it is
completed.
(d) Describe source of matching funds and any restrictions on availability.
(e) Other specific implementation information that should be considered.
4. Project Cost:
If a more detailed breakdown of cost estimates is being provided, a sample cost estimates sheet is provided for
your use.
Sample Construction Cost Estimate
For latest cost information go to:
http://www.fdot.gov/programmanagement/estimates/historicalcostinformation/historicalcost.shtm
What is the total estimated cost of the work requested to be funded as a transportation alternative
project through this application?
Planning Activities $ 0.00
Project Development and Environmental Studies $ 0.00
Engineering and Final Plans Preparation Work $ 63,000
Right of Way Acquisition $ 0.00
Construction $ 316,000
Construction Engineering and Inspection Activities $ 57,000
Other (Describe) $ 0.00
TOTAL: $ 436,000
How will the project be funded?
FDOT Transportation Alternative Funds $
436,000 + Local $ 0 = Total $
436,000
FDOT Transportation Alternative Funds 100 % + Local 0 % = 100%
D3 TAP APPLICATION
2017
Page 4 of 4
CERTIFICATION OF PROJECT SPONSOR
I hereby certify that the proposed project herein described is supported by Okaloosa County BOCC ,
(Project Sponsor)
and that said entity will: (1) provide any required funding match; (2) enter into a maintenance agreement with
the Florida Department of Transportation; (3) comply with the Federal Uniform Relocation Assistance and
Acquisition Policies Act for any Right of Way actions required for the project, and (4) comply with the NEPA
process prior to construction, which may require involvement with the State Historic Preservation Officer
(SHPO), and other State and/or Federal agencies, prior to construction, and (5) support other actions
necessary to fully implement the proposed project. I further certify that the estimated costs included herein are
reasonable and agree to follow through on the project once programmed in the Florida Department of
Transportation’s Work Program. I fully understand that significant increases in these costs could cause the
project to be removed from the Florida Department of Transportation work