8.5.a.a
Fertilizer requirements may vary for the different plant species. The Contractor shall
place fertilizer in accordance with standard industry practice for each varying species
and size of plant, subject to the approval of the Owner and Engineer. The Contractor’s
work plan shall detail the brand name and manufacturer of the proposed hydrating gel
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
and fertilizer and proposed ratios for both 2-inch and 4-inch planting units. The
Contractor shall include the cost of the hydrating gel and fertilizer within the installed
planting unit bid price.
B. Initial and Maintenance Irrigation
The Contractor will be allowed to “water in” (initially irrigate) and maintenance-irrigate
all newly installed planting units such that the root zone of all newly installed planting
units is thoroughly saturated. The irrigation must be performed in accordance with a
Contractor-prepared and Engineer-approved irrigation schedule within the submitted
watering plan. The watering plan shall detail the proposed number of irrigation events,
irrigation methodology, the equipment, water source, labor, required time, notifications,
and the physical condition(s) of the planting units which signal the need for
maintenance irrigation. The Contractor shall notify the Engineer at least 72 hours prior to
the application of initial or maintenance irrigation. The Contractor shall apply irrigation
to the planting areas utilizing a non-destructive, non-scouring methodology. The
Contractor will be responsible for all aspects of the irrigation, including but not limited to,
compliance with all environmental permits, local beach access regulations, and any
damages arising from initial or maintenance irrigation. The cost of the initial and/or
maintenance irrigation shall be included within the installed planting unit bid price.
C. Irrigation Water
The Contractor will be responsible for obtaining and applying all irrigation water
required. All water shall be fresh and free from injurious amount of oil, acid, alkali salts or
other materials harmful to the growth of the plants. The Contractor shall comply with all
applicable permits and ordinances. No temporary or piped irrigation systems will be
allowed. The Contractor will be responsible for coordinating with local agencies if the
use of local hydrants is proposed.
D. Maintenance Fertilization
The Contractor, if approved by the Engineer, may undertake maintenance fertilizer
during the warranty period at their discretion. The Contractor shall notify the Engineer at
least 72 hours prior to the application of maintenance fertilizer. The Contractor shall not
apply maintenance fertilization within 60 days of the end of the 180-day warranty
period. The Contractor shall include the cost of any maintenance fertilization in the unit
cost schedule that accompanies the Contractor’s bid documents. The Contractor shall
undertake maintenance fertilization, if employed, in a manner that complies with all
environmental permits applicable to the project site.
E. Vehicle Access
Last Revised – 01/09/2013 Page 63
Packet Pg. 413
8.5.a.a
In developing irrigation plans, the Contractor is advised that vehicle access to the
beach and in the dune area is restricted and/or prohibited as outlined in Section 2.2.C
and Section 7.6.
SUCCESS CRITERIA AND REPLANTING
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
3.6
A. Planting Unit Success Criteria
The Engineer will assess the success of the planting effort approximately 180 days after
completion of the planting unit installation (for the entire project) using three criteria:
whole-site survival rate, planting unit survival pattern, and planting unit root penetration.
The Engineer will consider the planting effort a success and acceptable if all three of
the described criteria (Criteria 1 – 3 below) are met at the 80% level. The Engineer will
assess these criteria across the approximately 1,500 to 2,000-feet acceptance sections
documented in the Drawings for the purpose of warranty and payment.
B. Whole-Site Survival Rate (Criteria 1)
A minimum survival rate of 80% of all planting units installed over the site as a whole shall
be achieved. The Engineer will consider plants as surviving if they show clearly vigorous
rhizome and white, turgid roots, even in the absence of vital above ground growth.
C. Planting Unit Survival Pattern (Criteria 2)
A minimum of 80% of the planting width perpendicular to the shoreline shall be
occupied by surviving planting units at all locations. This survival criterion is needed to
minimize the risk of dune over wash during storm events. The Engineer may waive this
success criterion in areas where plant survival has been adversely impacted by
unexpected pedestrian traffic, erosion, overwash or inundation.
D. Planting Unit Root Penetration (Criteria 3)
A minimum of 24 out of 30 (80%) randomly selected plants within each acceptance
section shall have achieved root penetration of nine inches or greater, as measured
from the top of the root ball down. The Contractor and Engineer, immediately following
plant installation, shall tag the 30 randomly selected plants used to determine this
measure of success. The Engineer may waive this success criterion if lesser root
penetration is otherwise determined to be acceptable or if the lesser penetration was
caused by factors outside the control of the Contractor (e.g., excessive natural rainfall).
E. Replanting of Units
If any of the above success criteria are not met, as determined by the Engineer, the
Contractor shall replant the unsuccessful planting units with viable within-specification
planting units of the same type originally installed. The Contractor will assume sole
responsibility for the replanting of planting units and will complete the replanting at no
cost to the Owner. All warranty and survival provisions and requirements will apply to
replanted planting units. The Contractor will be responsible for properly disposing of all
rejected planting units.
F. Initial Planting Unit Survival
Last Revised – 01/09/2013 Page 64
Packet Pg. 414
8.5.a.a
The Engineer will reject and not consider eligible for payment all planting units that do
not survive for a minimum of 10 days after installation. Within 5 days of notification by the
Engineer that an area of initial planting units did not survive for 10 days, the Contractor
shall install new, within-specification planting units in areas identified by the Engineer.
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
The Contractor shall assume sole responsibility for installing the new replacement
planting units at no cost to the Owner. The Engineer will consider the replacement
planting units eligible for payment as “original” planting units only after they have
survived a minimum of 10 days after installation. The Contractor will be responsible for
properly disposing of all rejected planting units.
PART 4 - SAND FENCE and POST & ROPE INSTALLATION
4.1 MATERIALS
A. The Drawings specify acceptable sand fencing, post and rope materials.
4.2 INSTALLATION
A. The Contractor shall install sand fence along the seaward toe of the existing dune
(seaward planting area limit) as shown in the Drawings. Prior to installation, the
Contractor shall demonstrate the installation technique to be applied for installing the
sand fencing, maintaining proper spacing and attaching the rope. The Contractor, at
the discretion of the Engineer, may be allowed to vary sand fence length and/or
spacing requirements in transition areas (e.g., areas adjacent to dune walkovers,
accesses, etc.). Following sand fencing installation, the Contractor shall attach a single
strand of rope to the seaward sand fencing post as shown in the Drawings to create a
uniform barrier for the dune area. The rope connection shall be threaded through a
hole drilled 3 inches from the top of the post and looped around the post. The rope shall
be stapled or nailed on the landward side to inhibit tampering. The Contractor shall
allow for uniform sag of approximately 12 inches in the rope between sand fence
sections. Where the sand fence terminates at an existing dune walkover, the rope shall
be tied and secured to the walkover at an area and elevation to keep the rope
elevation and length uniform. The rope shall be stapled or nailed to inhibit tampering or
disconnection. Where the sand fence terminates at an existing pathway or beach
access, the Contractor shall install a post and rope system from the seaward toe of the
dune to the landward toe of the dune. The Contractor shall install the posts and rope in
accordance with the Drawings. The posts for the post and rope pathways shall be
minimum 3-inch diameter wood posts, no less than 7 feet in length, comprised of
treated southern yellow pine, spruce or other wood of equal life and strength as may be
approved by the Engineer. The Contractor shall maintain a minimum access width of 6
feet at all major pathways unless otherwise shown in the Drawings or directed by the
Engineer. The Engineer reserves the right to modify or field-determine the number and
location of beach accesses over the dune. The Engineer will attempt to address the
preferences of property owners with respect to access location and size through field
adjustments.
Last Revised – 01/09/2013 Page 65