uncompleted work, shall be left in place and the contractor shall be
relieved of installation any materials within 10 feet of the nest site.
7.4 IRRIGATION/FERTILIZER
A. The contractor is not permitted to irrigate or fertilize within 10 feet or
upslope of any marked nest.
7.5 LIGHTING
A. Lighting of the beach and/or work area is prohibited.
7.6 BEACH DRIVING
A. The contractor is specifically advised that vehicle driving or parking on the
beach is prohibited, expecting lightweight all-terrain vehicles with ground
Last Revised – 01/09/2013 Page 52
Packet Pg. 402
8.5.a.a
pressure of 10 psi or less. The contractor shall obtain beach driving permits
from the Owner for each vehicle used on the beach. Permits shall remain
with each vehicle and be displayed in the driver’s side windshield.
Vehicle access shall only be through access points designated on the
Construction Drawings. The Contractor is advised the proposed work
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
area is soft sand, and only appropriate vehicles shall be utilized in support
of the work.
The contractor will be responsible for filling or leveling any alteration of the
beach topography (e.g., tire ruts, vehicle tracks, etc.) resulting from
vehicular activity. The contractor will not be permitted to store any
equipment or materials on the beach. The contractor shall store all
equipment and materials not installed/used during the workday in the
staging areas show on the drawings.
PART 8 – MEASUREMENT & PAYMENT
8.1
A. PAYMENT – Payment shall be in accordance with the unit prices specified
for the work and shall be based on the total number of installed and
accepted units as described below and within these specifications and
the contract documents. The contractor may submit partial payment
requests upon completing the approximate 1,500 to 2,000-feet
acceptance sections shown in the Construction Drawings.
1. Dune Vegetation – Payment for the number of planting units
installed and accepted.
2. Sand Fencing – Payment for the lineal feet of sand fencing
installed and accepted. Sand fencing units will also include the
rope placed along the seaward boundary of the fence.
3. Signage – Payment for the number of signs and sign post installed
and accepted.
4. Post & Rope Access Enhancements – Payment for the lineal feet of
post and rope installed and accepted.
5. Additional payment for items in excess of that indicated on the
Drawings and requested by the Owner will be calculated at unit
prices stated in the contract.
6. Unit prices are to include labor, materials, tools, equipment, and
incidentals for the installation of all work components as listed
herein and on the Drawings.
7. No payment will be made for rejected items, items that do not
comply with applicable sections of these specifications, and those
items that are defective or damaged during handling or
placement.
8. No payment will be made for re-planting or other activities to
conform to the warranty and success criteria provisions stipulated
within these specifications.
Last Revised – 01/09/2013 Page 53
Packet Pg. 403
8.5.a.a
PART 9 – PUBLIC SAFETY & CONFLICTS
9.1 PUBLIC SAFETY
A. Public Safety – The contractor shall at all times protect the safety of the
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
general public utilizing the beach and access areas, as well as recreating
along the shoreline, within the adjacent to the proposed installation areas.
The contractor shall notify the Owner and Engineer immediately of any
concerns or issues relating to potential conflicts between work activities
and residents or the general public.
9.2 CONFLICTS
A. Conflicts – The contractor is advised that construction work by other
contractors may be occurring at the same time as plant installation. The
contractor shall direct all concerns or issues relating to potential work
conflicts to the Owner and Engineer.
Last Revised – 01/09/2013 Page 54
Packet Pg. 404
8.5.a.a
ATTACHMENT “B”
OKALOOSA ISLAND DUNE FLORA RESTORATION
& BEACH ACCESS MANAGEMENT PROJECT
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
CONSTRUCTION DRAWINGS AND SPECIFICATIONS
TECHNICAL SPECIFICATIONS FOR THE
OKALOOSA ISLAND DUNE FLORA RESTORATION
AND BEACH ACCESS ENHANCEMENT PROJECT
PART 1 - GENERAL
1.1 SUMMARY
A. These specifications include requirements for the furnishing of labor, materials,
equipment and performing all operations in connection with dune vegetation, sand
fencing, signage, and post and rope installation as indicated on the Construction
Drawings (Drawings) and specified herein.
B. The Contractor is informed that Okaloosa County has made a request to the Florida
Department of Environmental Protection (FDEP) for a Coastal Construction Control Line
(CCCL) Permit exemption as the project does not cause an adverse impact to the
coastal system. The Contractor shall be aware that the FDEP may require additional
permitting requirements beyond those stated in these specifications. The Contractor
shall familiarize themselves with FDEP permitting requirements for dune restoration and
beach access management projects as they relate to the proposed work.
1.2 DEFINITIONS
A. Nomenclature: The scientific and common names of plants herein specified conform to
the approved names given in Hortus Third (1976) by Liberty Hyde Bailey Hortorium.
B. Planting Unit: For the purposes of this project, the term “planting unit” refers to
vegetative material of an individual, viable, nursery-grown plant installed within a single
hole created on the beach or dune system. Planting unit species and size vary in
accordance with these Specifications and Contract Documents.
C. Engineer: The Owner’s representative responsible for construction observation and
project certification.
1.3 SUBMITTALS
The following shall be submitted for Owner and Engineer approval:
A. Work Plan: As part of the bid package, the Contractor shall submit to the Engineer a
detailed work plan for the dune vegetation, sand fence, signage, and post and rope
installation. The plan shall include the construction schedule (including plant
propagation through installation), propagation method, types of hydrating gel and
Last Revised – 01/09/2013 Page 55
Packet Pg. 405
8.5.a.a
fertilizer to be used (including the required manufacturers information), proposed
materials, staging areas and access requirements, work force and equipment, and the
qualifications of supervisor(s). The Contractor shall provide with the work plan
documentation as to the source of the planting units to be installed, including collection
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
permits and any other required permits or documentation.
B. Watering Plan: As part of the bid package, the Contractor shall furnish to the Engineer a
plan for watering the plants and an itemized list of equipment that will be used during
watering operations. The watering plan shall detail the proposed number of irrigation
events, irrigation methodology, equipment, water source, labor, required time,
notifications, and the physical condition(s) of the planting units that signal the need for
maintenance irrigation. The plan shall also include details regarding the hydrating gel
requirements and any additional soil amendments (fertilizer) that may be included
during the irrigation.
C. Certificates of Compliance: Before delivery of planting materials, the Contractor shall
submit to the Engineer certificates of compliance and/or documentation certifying that
the planting materials meet all of the requirements (plant source, plant size, plant age,
plant grade, etc.) for this specification.
D. Notice of Commencement: The Contractor shall notify the Engineer at least 3 days
before initiating the work, including mobilization, staging, and/or field work.
E. Notice for Inspection: The Contractor shall notify the Engineer at least 10 days before
the scheduled 180-day inspection that the