contractor shall attach a single strand of rope to the seaward sand
fencing post as shown in the drawings to create a uniform barrier for the
dune area. The rope connection shall be threaded through a hole drilled
3 inches from the top of the post and looped around the post. The rope
Last Revised – 01/09/2013 Page 49
Packet Pg. 399
8.5.a.a
shall be stapled or nailed on the landward side to inhibit tampering. The
contractor shall allow for uniform sag of approximately 12 inches in the
rope between sand fence sections. Where the sand fence terminates at
an existing dune walkover, the rope shall be tied and secured to the
walkover at an area and elevation to keep the rope elevation and length
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
uniform. The rope shall be stapled or nailed to inhibit tampering or
disconnection. Where the sand fence terminates at an existing pathway
or beach access, the contractor shall install a post and rope system from
the seaward toe of the dune to the landward toe of the dune. The
contractor shall install the posts and rope in accordance with the
drawings. The posts for the post and rope pathways shall be minimum 3-
inch diameter wood posts, no less than 7 feet in length, comprised of
treated southern yellow pine, spruce or other wood of equal life and
strength as may be approved by the Engineer. The contractor shall
maintain a minimum access width of 6 feet at all major pathways unless
otherwise shown in the drawings or directed by the Engineer. The
engineer reserves the right to modify or field-determine the number and
location of beach accesses over the dune. The Engineer will attempt to
address the preferences of property owners with respect to access
location and size through field adjustments.
4.3 WARRANTY
A. The contractor shall warrant the installed sand fence, posts and rope
against deterioration and decay for 12 months following final
acceptance. The contractor will not be responsible for warranting
materials damaged during extreme storm events.
PART 5 – SIGNAGE
5.1 SIGNAGE
A. Materials – The signage shall be constructed of 80-gage aluminum or
better, shall have minimum dimensions of 12 inches & x 12 inches, and
shall have white reflective coating and black lettering capable of
withstanding the harsh beach environment. The signs shall read “Please
Keep Off – Dune Restoration in Progress” and “Dune Vegetation Protected
– Florida Statue Ch. 161” in accordance with the drawings. The
contractor may propose alternative signage materials for approval by the
Engineer. The contractor must submit proper documentation for
proposed materials and outline the advantages of such materials.
Signage posts shall be minimum 3-inch diameter wood posts, no less than
8 feet in length, comprised of treated southern yellow pine, spruce, or
other wood of equal life and strength as may be approved by the
Engineer. The Contractor’s Work Plan shall include the proposed sign and
post details (material type, size, text, etc.).
B. Installation – The contractor shall install signage designating the newly
vegetated dune areas in accordance with the construction drawings.
The contractor shall install signage posts with a minimum 3-foot
embedment into the existing grade. Embedment shall not exceed 4-feet
and shall be uniform across the project area. Signage shall be installed at
the seaward dune toe immediately landward of the sand fencing and
atop the dune crest immediately adjacent to existing dune walkovers and
Last Revised – 01/09/2013 Page 50
Packet Pg. 400
8.5.a.a
foot pathways as depicted in the drawings. Signage installed near the
seaward dune toe shall be attached to the seaward face of the timber
post and face the offshore direction (south) to be viewed from the beach
looking landward. Signage installed near the dune crest adjacent to
walkways and foot paths shall be placed on both the seaward and
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
landward side of the timber post and face both the offshore (south) and
landward (north) directions. Signage shall be attached to the timber
posts with stainless steel bolts and nuts or tamper-proof steel screws and
plastic washers. The signs shall be placed at the general spacing
depicted in the drawings and in close proximity to and in full view of the
footpaths and dune walkovers.
C. Warranty – The contractor shall warrant the installed signage against
deterioration and decay for twelve months following final acceptance.
The contractor will not be responsible for warranting materials damaged
during extreme storm events.
PART 6 – REPORTING
6.1 REPORTING
A. The contractor shall prepare a daily progress report for submittal by fax or
electronic mail to the Owner & Engineer. At least five (5) days prior to
commencement of the work, the contractor shall submit a sample
progress report to the Engineer for review and approval. The daily
progress shall include, at a minimum:
1. Project Name
2. Contractor’s name & contact information
3. Date of report
4. Weather conditions
5. Work performed (alongshore limits of work referencing baseline
stationing
6. Quantity of materials installed, staged, etc.
7. Problems/delays/issues
8. Instructions given/received
9. Deviations from the drawings and/or specifications
10. Certification statement by the contractor with the contractor’s
signature verifying the reported information.
PART 7 – ENVIRONMENTAL PROTECTION
7.1 GENERAL
Last Revised – 01/09/2013 Page 51
Packet Pg. 401
8.5.a.a
A. The contractor shall conduct all work related activities in a manner so as
to minimize or avoid disturbance to the existing beach and dune
environment. The contractor shall comply with all marine nesting turtle,
beach mice, and shorebird protection requirements as specified in the
Florida Department of Environmental Protection Permit #0286575-001-JC,
Attachment: Request for Bids (1264 : Approval of Bid - Dune Planting Projects (Okaloosa Island & Western Destin))
U. S. Army Corps of Engineers Permit #SAJ-2008-00895, and referenced
documents. The contractor and subcontractors are responsible for
becoming intimately familiar with the permitting requirements and
referenced documents and their potential impact on the proposed work.
The regulations, requirements, conditions of these regulatory
authorizations are considered a part of the contract and shall be
complied with by the contractor and subcontractors. The contractor is
responsible for informing its personnel and all subcontractor(s) of the
permit requirements and the measures needed to maintain compliance
with these requirements.
7.2 FUELDING OPEATIONS
A. The contractor will not be permitted to dispense fuel on the dune of sandy
beach areas. The contractor shall take all responsibility precautions to
prevent fuel spills or contamination of the ground with fuel. Should any
fuel spills occur, the contractor shall immediately notify the Owner,
Engineer, and any other required parties and immediately recover the
contaminated ground and dispose of it offsite at an approved facility.
7.3 DAILY TURTLE NEST SURVEYS
A. Beginning May 1, Okaloosa County shall conduct daily marine turtle nest
surveys of the beach within work area prior to 9:00 a.m. (local time). The
contractor will be required to coordinate with the designated turtle
monitoring personnel prior to commencing any vehicular activity on the
beach to determine the location of any tests detected. The turtle monitor
shall clearly mark, with stakes and flagging indicating a 3-foot (minimum)
buffer radius, any nest discovered. The contractor shall document and
verify all daily communication with the turtle monitor in the daily report. If
the contractor finds an unmarked nest, the contractor shall prohibit any
work within 10 feet of the nest and notify the Owner, Engineer, and turtle
monitor immediately. Nests that interfere with the contractor’s