Execution Plan - West Hangar Area improvement Project at Bob Sikes Airport (1327 : West Hangar Area Improvement
8.3.b.a
Packet Pg. 320
Attachment: Project Execution Plan - West Hangar Area improvement Project at Bob Sikes Airport (1327 : West Hangar Area Improvement
Emerald Coast Aviation
Conceptual Rendering of Proposed FBO Terminal
8.3.b.b
Packet Pg. 321
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
8.3.b.b
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
Project Execution Plan
for
Proposed FBO Terminal &
Parking Improvements
Emerald Coast Aviation
& Okaloosa County
Packet Pg. 322
April 2011
Bob Sikes Airport
Taxiway A Widening and Stormwater Improvements
8.3.b.b
Packet Pg. 323
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
December 2011
Bob Sikes Airport
Taxiway A Widening and Stormwater Improvements
8.3.b.b
Packet Pg. 324
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
April 2012
Bob Sikes Airport
Taxiway A Widening and Stormwater Improvements
8.3.b.b
Packet Pg. 325
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
and
Widening
April 2012
Taxiway A
Stormwater
Improvements
Bob Sikes Airport
8.3.b.b
Packet Pg. 326
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
July 2012
Bob Sikes Airport
Taxiway A Widening and Stormwater Improvements
8.3.b.b
Packet Pg. 327
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
Bob Sikes Airport
Taxiway A Widening and Stormwater Improvements
8.3.b.b
Packet Pg. 328
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
8.3.b.b
Packet Pg. 329
Attachment: Powerpoint presentation for Project Execution Plan (1327 : West Hangar Area Improvement
8.4.a
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: February 5, 2013
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Task Order 46 - Baker Landfill - 2013 Environmental Restoration
DEPARTMENT: Public Works
BCC DISTRICT: All
STATEMENT OF ISSUE: Professional services are required for compliance with Florida
Department of Environmental Protection (FDEP) Permit/Certification #0075982-004-SF which
addresses long term care and remediation of Baker Landfill. Professional services are also
required to comply with the FDEP Remedial Action Modification Approval Order dated
December 7, 2011.
BACKGROUND: Baker Landfill has two FDEP regulated environmental interests - Long Term
Care (LTC) and Corrective/Remedial Action. LTC is an FDEP permitted activity that requires
monitoring of groundwater from a designated network of sampling locations. The County has
been performing this compliance monitoring since the landfill was closed to land filling activities
in 1998 and was permitted for LTC status in 2003. Since that time the County has complied with
the permit through sampling of the monitoring network. SCS Engineers has been contracted to
perform these activities since 2007.
FDEP directed the County to initiate Corrective Actions in 1989 due to the detection of chemical
constituents in the groundwater exceeding FDEP water quality standards. FDEP approved the
County’s Contamination Assessment Report in 1993 and the County began the design of a
Remedial Action Plan in 1994. Several iterations of the Remedial Action Plan were produced
over the next few years and FDEP approved the County’s remediation plans in 2002. The
remedial action system became operational in 2004. Based on operational observations, the
remediation system has been slightly modified from the original design. After two years of
operation, the remediation system was shut down in September 2006 to address a compromise of
the liner system in one of the treatment ponds. The remediation system was not reactivated until
August 2008. Due to lack of maintenance, the remediation system was not operating fully until
May 2009. Operational characteristic assessments of the system indicated that the system was
not performing to design specifications for a variety of reasons. A Remedial Action Plan
Modification (RAPMod) was solicited from the FDEP and approved in December, 2011.
Construction of the RAPMod infrastructure was completed in 2012. The RAPMod also included
revisions to the environmental sampling scheme.
Both Long Term Care Semi-Annual Compliance and Remedial Action Assessment monitoring
are budgeted activities. The activities in this Task Order address services to be performed in
Packet Pg. 330
8.4.a
2013. In order to meet LTC Permit and Remedial Action requirements, the LTC and RAP Mod
requires two monitoring events for an amount not to exceed $102,200.
OPTIONS: Approve / Disapprove
RECOMMENDATIONS: Approve the scope and fee with SCS Engineers not to exceed value
of $102,200.
RECOMMENDED BY:
APPROVED BY:
James D. Curry, County Administrator
Packet Pg. 331
8.4.a.a
Packet Pg. 332
Attachment: Baker Landfill - SCS Task Order 46 (1316 : Task Order 46 - Baker Landfill - 2013 Environmental Restoration)
8.4.a.a
Environmental Consultants 3298 Summit Boulevard 850 432-6211
and Contractors Suite 31-A FAX 850 432-6220
Pensacola, FL 32503 www.scsengineers.com
January 16, 2013
Attachment: Baker Landfill - SCS Task Order 46 (1316 : Task Order 46 - Baker Landfill - 2013 Environmental Restoration)
File No. 090029213
Mr. Scott Henson
Okaloosa County Public Works Department
Environmental Services Division
1759 South Ferdon Blvd
Crestview, FL 32536
Subject: Proposal to Perform 2013 Semi-Annual Compliance and Remedial Action Plan
Modification Sampling and Reporting for the Baker Landfill
Dear Scott:
SCS Engineers (SCS) is pleased to provide Okaloosa County Environmental Services Division
(County) with this proposal to perform 2013 semi-annual compliance and remedial action
sampling and reporting for the Baker Landfill. This proposal includes SCS’ services to continue
ongoing semi-annual and annual compliance monitoring and reporting and continue remedial
action sampling modified in accordance with the 2008 RAPMOD – 2011 Addendum
(RAPMOD) prepared by SCS, dated August 1, 2011, and approved by the Florida Department of
Environmental Protection (FDEP) on December 7, 2011. This proposal provides SCS’ scope of
services, schedule, and estimated fee to perform the semi-annual compliance and RAPMOD
sampling, evaluation, and reporting.
SCOPE OF SERVICES
In accordance with the closure permit for Baker Landfill (Permit No. 0075982-004-SF), as
modified April 19, 2010, and the RAPMOD approved by FDEP on December 7, 2011, semi-
annual reports for compliance and remedial action sampling are due by May 1 and November 1
of each year. To meet this schedule and the reporting schedule