Approve Contract with Environmental Management Resources of — agenda request — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: May 17, 2016
TO: Honorable Chairman and Members of the Board
FROM: Tracy Stage
SUBJECT: Approve Contract with Environmental Management Resources of
Washington, Inc.
DEPARTMENT: Airport
BCC DISTRICT: 2
STATEMENT OF ISSUE: The Airports Department requests the Board of County
Commissioners approve the contract with Environmental Management Resources of
Washington, Inc. (EMR) for the construction of the Eglin Air Force Base Aircraft Rescue and
Firefighting (ARFF) Development Facility at the Destin-Fort Walton Beach Airport (VPS) in the
amount of $3,681,246.47 (RFB AP 101-15).
BACKGROUND: On April 5, 2016, the Board of County Commissioners approved the request
presented by the Airport to award EMR, Inc., the contract for the construction of the Eglin AFB
ARFF Development Facility at the Destin-Fort Walton Beach Airport in the amount of
$3,681,246.47 (RFB AP 101-15). On April 19, 2016, the Board also approved a Site Work
Agreement between Okaloosa County and Eglin Air Force Base's 96th Civil Engineer Group for
the construction of the Taxiway H Water Main Extension project, which supports the ARFF.
Staff has prepared the contract which has been coordinated per Okaloosa County policies and
procedures.
Funding for the project will be as follows: Florida Department of Transportation (FDOT)
$150,000.00; Federal Aviation Administration (FAA) $3,155,055.00; approved Passenger
Facility Charges (PFCs) $155,236.00 and Local Match $220,955.47.
Previous Board action in support of the Eglin ARFF Development Facility:
April 16, 2013 Board approved TO#22 with Avcon to design through bid for the ARFF
April 16, 2013 Board approved Airport Staff to enter into lease negotiations to amend our current Long-Term
Lease and Joint-Use Agreement with the DOD, Department of the Air Force, 96 th Civil
Engineering Group, and Eglin AFB for the design through construction of an ARFF
July 16, 2013 Board approved Amend No. 1 to Lease No. AFMC-EG-1-07-003 extending the current
lease 5 years to expire in 2038
August 6, 2013 Board approved Chairman’s signature on an FAA Grant Application for the ARFF Facility
September 3, 2013 Board approved FDOT JPA for the ARFF Construction
December 17, 2013 Board approved the negotiated lease agreement and Operating Agreement with the Air
Force and approval to award the construction contract to Birkshire Johnstone, LLC
February 18, 2014 Board approved the request for the Chairman to sign the contract to Birkshire Johnstone, LLC
April 1, 2014 Board approved the Request to Solicit Requests for Qualifications for the ARFF Construction
Administration and the RFQ Review Committee
June 17, 2014 Board approved to negotiate a contract with AVCON for Construction Administration for the
ARFF Station
October 7, 2014 Board approved the request Re-solicit Request For Bids for construction of the ARFF Station
December 16, 2014 Board approved and authorized for the Chairman to sign the contract with AVCON for
administration of the ARFF
November 3, 2014 Board approved the FAA grant amendment for additional funds to assist with the extension of
the Air Force water line
April 5, 2016 Board approved the bid for Eglin AFB ARFF to EMR, Inc
OPTIONS: Accept, Reject, or Table.
RECOMMENDATIONS: It is Staff’s recommendation that the Board approve the contract
with EMR, Inc. for the construction of the Eglin ARFF Development Facility at the Destin-Fort
Walton Beach Airport in the amount of $3,681,246.47.
RECOMMENDED BY:
APPROVED BY:
John Hofstad, County Administrator