READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 11, 2013 — Task Order #22 EAFB ARFF Development — reading text
Part 2 of 2. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 103-Task Order _22 EAFB ARFF Development.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
90% Design Review Meeting with County: AVCON shall conduct a design review
meeting with County staff to discuss the features of the 90% design documents. AVCON will
incorporate one round of review comments from this meeting into the 90% design drawings. The 90%
design drawings shall be approved by the County prior to proceeding to 100% design drawings
Prepare Engineer’s Report: AVCON shall prepare an Engineer’s Report in accordance with federal
guidelines for submittal to funding agencies. The report shall summarize the features of the project
with justification for key design decisions and deviations to standards, if applicable.
Identify Pay Items and Prepare Bid Forms/Schedule: AVCON shall identify proposed project pay
items and shall prepare bid forms and bid schedules for the work. Based on the nature of the work, the
bid forms shall represent a unit price contract.
Page 3 of 7
SCOPE OF SERVICES - AVCON, INC.
Eglin Air Force Base ARFF Development
20.
21.
22.
23.
24,
Prepare Front-End Documents: AVCON shall prepare front-end bidding documents including
appropriate certifications, submittals, and general conditions. Front-end documents shall include the
draft contract and certifications consistent with standards for applicable design elements.
Prepare Opinion of Probable Construction Cost: AVCON shall prepare an opinion of probable
construction cost based on the 90% design drawings. Task shall include updating the opinion
following preparation of the final bidding documents.
Perform QA/QC Review of 100% Design Documents and Update: AVCON shall perform and
document an internal review of the technical elements and bidding format of the 100% design
documents. The design documents shall be updated in accordance with the review results prior to
submittal to the County and Eglin Air Force Base.
Prepare and Submit 100% Design Documents to County: AVCON shall prepare and submit three
(3) sets of the updated 100% design documents to the County for review and coordination with
funding agencies as a condition of receiving approval for advertising the project. Each set shall
include:
Front-end documents
Bid forms and schedules
Technical Specifications
100% design drawings
Engineer’s report
Opinion of probable construction cost
eae oe
ahi
Prepare and Submit 100% Design Documents to Eglin Air Force Base Planning and
Programming for Review: AVCON shall prepare and submit the following packages to the Eglin
Air Force Base Planning and Programming department for distribution through the Planning and
Programming Department:
a. Prepare and submit Development Package for Eglin Air Force Base Planning and
Programming for Review: AVCON shall prepare and submit the Development Package to
Eglin Air Force Base Planning and Programming for review. AVCON shall attend one (1)
submittal coordination meeting with Eglin Air Force Base Planning and Programming
Department.
b. Prepare and submit Eglin Air Force Base Stormwater Department Submittal Package:
AVCON shall prepare and submit Eglin Air Force Base Stormwater Department submittal
package for review.
c. Prepare and submit Eglin Air Force Base Civil Engineering Department Submittal
Package: AVCON shall prepare the Eglin Air Force Base Civil Engineering Department
submittal package.
d. Prepare and submit Eglin Air Force Base Water and Sewer Department Submittal
Package: AVCON shall prepare and submit the package for review by Eglin Air Force Base
Water and Sewer Department.
Page 4 of 7
SCOPE OF SERVICES - AVCON, INC.
Eglin Air Force Base ARFF Development
25.
26.
27.
28.
e. Prepare and submit Fire Inspection package: AVCON shall provide a package for the
Eglin Air Force Base Fire Inspection to review as part of the approval process.
f. Prepare and submit airport package: AVCON shall prepare and submit the airport package
consisting a one (1) set of construction drawings and a copy of the development order
application.
Coordinate Comments with Eglin Air Force Base Departments: AVCON shall respond to up to
two rounds of questions and RAIs from Eglin Air Force Base Departments.
Prepare and Submit Northwest Florida Water Management District (NWFWMD)
Environmental Resource Permit (ERP): AVCON shall prepare and submit the ERP permit to the
NWFWMD including supporting documentation, calculations, and Stormwater Management Report.
Coordinate Comments with NWFWMD: AVCON shall respond to up to two rounds of questions
and comments from the NWFWMD.
Incorporate Comments and Prepare and Submit Release for Bid Documents to the County:
AVCON shall incorporate permit review comments into the Release for Bid documents and submit
five (5) copies to the County.
Task II: Bidding and Award (Lump Sum)
1.
Prepare and Coordinate Advertisement: AVCON shall prepare an advertisement summarizing
project elements and bid proposal requirements for County use in providing public notification of the
project.
Attend Pre-Bid Conference and Prepare Minutes: AVCON shall participate in a Pre-Bid
Conference to present and discuss specific project issues, specific construction features, operational
phasing, special airfield construction limitations, and other applicable requirements. AVCON shall
provide and distribute meeting minutes for the Pre-Bid Conference to participants and funding
agencies.
Distribute Bid Documents and Maintain Plan-Holder List: AVCON shall prepare copies of the
bidding documents and shall distribute documents to prospective bidders upon request. AVCON shall
maintain a current list identifying all bid plan holders. Bid documents shall be provided to prospective
bidders at a nominal fee to cover reproduction and handling costs. Contractor shall contact local plan
rooms and shall provide up to three (3) sets of bid documents at no charge for public review.
Prepare and Distribute Addenda and Responses to Questions: AVCON shall prepare formal
responses to questions by potential bidders as provided during the Pre-Bid Conference and during the
specified period prior to the project bid opening. AVCON shall prepare and distribute addenda to
bidding documents as required to address any revisions resulting from bidder’s concerns or from
design modifications for items designed by AVCON.
Attend Bid Opening: AVCON shall attend the bid opening for the proposed project and receive
copies of the bid proposals from the County for review.
Page 5 of 7
SCOPE OF SERVICES — AVCON, INC.
Eglin Air Force Base ARFF Development
6. Prepare Bid Tabulation and Recommendation of Award: AVCON shall review all bids received
and shall prepare tabulation of the bids, including the Engineer’s estimate. Based on the review,
AVCON shall provide a formal recommendation of the award for Okaloosa County.
7. Prepare Conformed Construction Documents: AVCON shall prepare and submit conformed plans
and specifications that incorporate addendums to serve as the “Release for Construction” set. A total
of five sets of conformed documents shall be provided to the Owner.
Task III: Sub-Consultant Services (Not-To-Exceed)
All services performed under this task shall be performed by a qualified subconsultant. The anticipated
subconsultant work includes the following:
1. Architectural design
2. Design topographic survey (Nobles Consulting Group)
3. Design geotechnical investigation (NOVA Engineering and Environmental)
SECTION C: DELIVERABLES
The following deliverables to the County are anticipated:
Task I — Design Documents and Permitting Services
1. Three (3) 10% Concept Design Layout for Review
Minutes from 10% Concept Design Layout Review Meeting
Three (3) 90% sets of Design Drawings for Review
Minutes from 90% Design Review Meeting
Three (3) Copies of Engineer’s Report
Opinion of Probable Construction Cost
Notes from QA/QC Review of 100% Design Documents
Three (3) copies of 100% Design Documents
Five (5) copies of Release for Bid Documents
AD! 09 SY Oy (Gy Go:
Task II — Bidding and Award
1. Minutes from Pre-Bid Conference
2. One (1) copy of Bid Tabulation and Recommendation of Award
3. Five (5) sets of Conformed Documents
SECTION D: SCHEDULE
A schedule of 120 calendar days is anticipated from the date of the project Notice-To-Proceed (NTP) to
accomplish the work required to submit 100% documents to the permitting agencies. For any unreasonable
delays in obtaining required materials or reviews to be provided by others, the anticipated 120-day design
schedule shall be extended an equivalent number of days.
Page 6 of 7
SCOPE OF SERVICES — AVCON, INC.
Eglin Air Force Base ARFF Development
SECTION E: ASSUMPTIONS AND EXCLUSIONS
od
10.
11.
12.
13.
All coordination with Eglin Air Force Base shall be as directed by Tracy Stage.
All applicable permitting and impact fees shall be provided by Okaloosa County.
Effort included in Task I, Items 26 through 28 assumes work typically required by Eglin Air Force
Base and the NWFWMD for development approvals.
All existing variances, easements, or special conditions on property to be provided to AVCON by
Owner at commencement of project.
Additional services may be separately authorized at rates indicated in Exhibit “B.”
Landscaping shall be limited to minimum required for permit compliance. Irrigation design shall be
performed by the Contractor and shall be included in their bid.
Building security system is not included and shall be considered an additional service.
All environmental permitting will be performed by others.
Mitigation for existing environmental hazards shall be performed by others.
Access to the site will be approved by Eglin Air Force Base.
Construction phase services are not a part of this scope.
No LEED (or similar sustainable design) certifications are included in this scope.
No furnishings will be specified for the building.
END OF SCOPE
Page 7 of 7
