READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — August 24, 2013 — RON Apron Hi Mast Lighting - VPS_Final Change Order No. 2 — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 11-RON Apron Hi Mast Lighting - VPS_Final Change Order No. 2.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
CHANGE ORDER NO. 2
RON Apron High Mast Lighting project *#* BINAL ***
Northwest Florida Regional Airport
CHANGE ORDER NO: Two (2)
CONTRACTOR: Bill Smith Electric, Inc.
CONTRACT DESCRIPTION: RON Apron High Mast Lighting Project, NWFRA, County Contract Number C12-1988-AP
CONTRACT DATE: October 3, 2012
C.O. ISSUE DATE: July 9, 2013
NO WORK COVERED BY THIS CHA NGE ORDER MAY PROCEED UNTIL CONTRACTOR IS IN RECEIPT OF A COPY FULLY EXECUTED BY
THE CONTRACTOR, THE OWNER AND THE ENGINEER. IF CONTRACTOR IS IN AGREEMENT WITH THIS CHANGE, HE SHOULD EXECUTE
ALL COPIES AND RETURN ALL COPIES TO THE ENGINEER WITHIN SEVEN (7) CALENDAR DAYS. THIS CHANGE WILL INCREASE OR
DECREASE THE CONTRACT AMOUNT AND TIME TO COMPLETE BY THE AMOUNT SHOWN BELOW. THE GENERAL, SUPPLEMENTARY
AND OTHER CONDITIONS OF THE CONTRACT SHALL APPLY TO THIS CHANGE ORDER UNLESS EXPRESSLY MODIFIED BY THIS CHANGE
ORDER.
DESCRIPTION OF CHANGES:
The purpose of this final change order is to reconcile the final contract amount in accordance
with the work completed and accepted in the field. This construction contract included a ORIGINAL: 180 Days from NTP (11/1/12)
ADJUSTED CALENDAR DAYS-CONTRACT TIME
$25,000 utility allowance for work to be completed by Gulf Power (provide primary power from TO DATE: 41 Days
existing Gulf Power transformer to the new high mast light transformer.) The amount of the THIS C.O.: 0 Days
utility allowance was based o coordination with Gulf Power during the design phase and the
contractor is to be reimbursed for the actual costs invoiced by Gulf Power, The utility allowance TOTAL: 221 Days
will be reduced from $25,000 to $12,521.00 in accordance with Exhibit 1.
During construction, it was identified that the 2/0 cable reel (which was incorrectly identified by ORIG. COMPL. DATE April 30, 2013
the manufacturer during the design phase) must be upgraded to a larger 4/0 cable reel to
accommodate the electrical load fram the Auxiliary Power Unit to the aircraft. The incremental REVISED DATE/COMPL. June 10, 2013
cost for this upgrade is $2,117.53. Lump sum Pay Item E-3, 4/0 Cable Reel Upgrade, in the
amount of $2,1 17,53 is added in this change order in accordance with Exhibit 1.
SOURCE OF FUNDS: FEDERAL AVIATION ADMINISTRATION/FLORIDA DEPT. OF TRANS./OKALOOSA COUNTY
» ADD DELETE xX $ -10,361.47
AMOUNT OF THIS CHANGE ORDER ...
PERCENTAGE CHANGE FROM CONTRACT PRICE -2.70
ORIGINAL TOTAL CONTRACT PRICE $ 378,840.00
APPROVED ADDITIONS TO CONTRACT TO DATE. $ 0.00
APPROVED DELETIONS TO CONTRACT TO DATE. $ 0,00
oe) 368,478.53
REVISED TOTAL CONTRACT PRICE
CONTRACTOR ACKNOWLEDGES, BY ITS EXECUTION AND ACCEPTANCE OF THIS CHANGE ORDER, THAT THE ADJUSTMENTS IN
CONTRACT PRICE AND TIME SHOWN HEREON CONSTITUTE FULL AND COMPLETE COMPENSATION AND SATISFACTION FOR ALL
COSTS AND MODIFICATIONS OF PERFORMANCE TIME INCURRED BY THE CONTRACTOR AS A RESULT OF THIS CHANGE ORDER. NO
OTHER CLAIM FOR INCREASED COSTS OF PERFORMANCE OR MODIFICATIONS OF TIME WILL BE GRANTED BY THE OWNER FOR THE
WORK COVERED BY THIS CHANGE ORDER. THE CONTRACTOR HEREBY WAIVES AND RELEASES ANY FURTHER CLAIMS FOR COST OR
TIME AGAINST THE OWNER ARISING FROM OR RELATING TO THE MATTERS OR WORK SET FORTH OR CONTEMPLATED BY THIS
CHANGE ORDER. CONTRACTOR ALSO ACKNOWLEDGES THAT THERE HAS BEEN NO CHANGE IN ITS OPERATIONS WHICH WOULD
REQUIRE A MODIFICATION OF ITS SWORN STATEMENT ON PUBLIC ENTITY CRIMES SUBMITTED WITH ITS BID.
CONTRACTOR’S ACCEPTANCE:
For? Bil] Smith Electric, Inc,
eo
é Quit, 9 duly 2013
/ DATE
SIGNATURE
Jake Smith Project Manager
TITLE
/ NAME
tL. OLE FA AZ
Pu U3
DATE
716-1
DATE
Detle
OWNER: INTERIMAIRPORTS DIRECTOR: OKALOOSA COUNTY / DATE
AIRPORTS
EPT, OF TRANSPORTATION, DISTRICT 3
RAL: FEDERAL AVIATION ADMINISTRA TION
OWNER: OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS DATE
EXHIBIT 1
RON Apron High Mast Lighting project
Northwest Florida Regional Airport
July 9, 2013
The following line items shall be added to the contract as follows:
item No. Item Description Unit Ounntity [unit Price | ota Amount
E-3 | 4/0 CABLE REEL UPGRADE LS I $2,117.53 $2,117.53
The following contract amounts shall be revised as follows:
Item wae ., | Original Total | Revised Total
No. {tem Description Unit Amount Amount Net Change
E-2. | UTILITY ALLOWANCE | AL $25,000.00 $12,521.00 $1 nan |
Net Deduct for Change Order No. 2: -$10,361.47