READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — March 4, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 27 of 40. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 36-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
existing pipes, valves or other underground structures, the CONTRACTOR shall examine
all available records and shall make all explorations and excavations necessary for such purpose.
SC-5.01 Add the following new paragraph immediately after paragraph 5.01.C of the General
Conditions:
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-2 Job No. 41-459
D. Prior to commencing work, payment and performance bonds required by this contract shall be filed
in the public records of the county where said is performed pursuant to the requirements of Title
XVIII, Section 255.05, Florida Statutes.
SC-5.04 Add the following new paragraph immediately after paragraph 5.04.B of the General
Conditions:
C. The limits of liability for the insurance required by paragraph 5.04 of the General Conditions
shall provide coverage for not less than the following amounts or greater where required by Laws and
Regulations:
1. Workers' Compensation and related coverages under paragraphs 5.04.A.1 and 5.04.A.2 of the
General Conditions:
a.) State: Statutory
b.) Applicable Federal (e.g. Longshoreman's): Statutory
c.) Employer’s Liability $1,000,000
2. CONTRACTOR's Liability Insurance under paragraphs 5.04.A.3 through A.6 of the General
Conditions which shall also include completed operations and product liability coverages and eliminate
the exclusion with respect to property under the care custody and control of the CONTRACTOR:
a.) General Aggregate
(Except Products - Completed Operations) $2,000,000
b.) Products - Completed Operations Aggregate $2,000,000
c.) Personal and Advertising
Injury (Per Person/Organization) $1,000,000
d.) Each Occurrence
(Bodily Injury and Property Damage) $1,000,000
e.) Property Damage Liability Insurance will provide Explosion,
Collapse and Underground coverages where applicable.
f.) Excess Liability
General Aggregate $2,000,000
Each Occurrence $2,000,000
3. Automobile Liability:
a.) Bodily Injury: $1,000,000 Each Person
$1,000,000 Each Accident
b.) Property Damage: $500,000 Each Accident
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-3 Job No. 41-459
OR
c.) Combined Single Limit
(Bodily Injury and Property Damage): $2,000,000 Each Accident
4. In addition to the requirements of Paragraph 5.04.B.1 of the General Conditions concerning
the naming of the Owner, Engineer, and Engineer's consultants as additional insureds under the
CONTRACTOR's General Liability Policy. Also, the CONTRACTOR shall at his expense provide an
OWNER's and CONTRACTOR's Protective Liability Policy issued in the name of the OWNER and
ENGINEER covering the CONTRACTOR's obligations under Paragraph 5.04.B.4 of the General
Conditions. Coverage shall be provided under this policy for not less than the following amounts:
(1) Bodily Injury: $1,000,000 Each Occurrence
(2) Property Damage: $1,000,000 Each Occurrence
$1,000,000 Annual Aggregate
SC-5.07
A. OWNER and CONTRACTOR intend that all policies purchased in accordance with paragraphs SC
5.06 will protect OWNER, CONTRACTOR, Subcontractors, ENGINEER, ENGINEER's Consultants and
all other persons or entities identified in the Supplementary Conditions to be listed as insured or additional
insureds (and the officers, directors, partners, employees, agents, and other consultants and subcontractors
of each and any of them) in such policies and will provide primary coverage for all losses and damages
caused by the perils or causes of loss covered thereby. All such policies shall contain provisions to the
effect that in the event of payment of any loss or damage the insurers will have no rights of recovery
against any of the insureds or additional insureds thereunder. OWNER and CONTRACTOR waive all
rights against each other and their respective officers, directors, partners, employees, agents and other
consultants and subcontractors of each and any of them for all losses and damages caused by, arising out
of or resulting from any of the perils covered by such policies and any other property insurance applicable
to the Work; and, in addition, waive all such rights against Subcontractors, ENGINEER, ENGINEER's
Consultants and all other individuals or entities identified in the Supplementary Conditions to be listed as
insureds or additional insureds (and the officers, directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them) under such policies for losses and damages so
caused. None of the above waivers shall extend to the rights that any party making such waiver may have
to the proceeds of insurance held by CONTRACTOR as trustee or otherwise payable under any policy so
issued.
B. In addition, OWNER waives all rights against CONTRACTOR, Subcontractors, ENGINEER,
ENGINEER's Consultants and the officers, directors, partners, employees and agents and other consultants
and subcontractors of each and any of them, for:
1. loss due to business interruption, loss of use or other consequential loss extending beyond direct
physical loss or damage to OWNER's property or the Work caused by, arising out of or resulting from fire
or other peril, whether or not insured by OWNER; and
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-4 Job No. 41-459
2. loss or damage to the completed Project or part thereof caused by, arising out of or resulting from
fire or other insured peril covered by any property insurance maintained on the completed Project or part
thereof by OWNER during partial utilization pursuant to paragraph 14.05, after substantial completion
pursuant to paragraph 14.04 or after final payment pursuant to paragraph 14.07.
C. Any insurance policy maintained by CONTRACTOR covering any loss, damage or consequential
loss referred to in this paragraph SC 5.07.B shall contain provisions to the effect that in the event of
payment of any such loss, damage or consequential loss the insurers will have no rights of recovery against
OWNER, Subcontractors, ENGINEER, ENGINEER's Consultants and the officers, directors, partners,
employees, agents and other consultants and subcontractors of each and any of them.
SC-6.06.B The CONTRACTOR, or apparent successful Bidder, shall identify Subcontractors,
Suppliers, or other persons or organizations as follows:
1) Prior to the Effective Date of the Agreement, the apparent Successful Bidder shall within
seven (7) days of the receipt of a Written Request from the OWNER or the ENGINEER
identify Subcontractors, Suppliers, or others specifically requested. Should such
identification be required, attention is directed to Article 12 of the Information For Bidders.
2) Within thirty (30) days following the Effective Date of the Agreement, all Subcontractors
shall be identified.
SC-6.06.C OWNER or ENGINEER may furnish to any such Subcontractor, Supplier or other
individual or entity, to the extent practicable, information about amounts paid to CONTRACTOR on
account of work performed for Contractor by a particular Subcontractor, supplier, or other individual or
entity.
SC-6.13 The following paragraphs shall apply in addition to the requirements in 6.13 of the General
Conditions:
CONTRACTOR agrees to waive any claim against OWNER and OWNER’s agents, architects, engineers,
consultants, and their employees acting within the scope of their duties, and to defend, indemnify, and hold
them harmless from any claim or liability for injury or loss that allegedly arises from CONTRACTOR’s
performance of the work described herein. CONTRACTOR will require all SUBCONTRACTORS to
conform with this provision before they start any work. CONTRACTOR shall insure this provision in
conformity with the insurance provisions of this CONTRACT.
Until final acceptance of the Work by the ENGINEER as evidenced by approval of the final estimate, the
Work shall be in the custody and under the charge and care of the CONTRACTOR and he shall take every
necessary precaution against injury or damage to any part thereof by the action of the elements or from any
other cause, whether arising from execution or from the non-execution of the Work, unless otherwise
provided for elsewhere in the Specifications or Contract. The CONTRACTOR shall rebuild, repair, restore
and make good, without extra compensation, all injuries or damages to any portion of the work occasioned
by any of the above causes before its completion and acceptance, and shall bear the expenses thereof. In
case of suspension of the Work from any cause whatever, the CONTRACTOR shall be responsible for all
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-5 Job No. 41-459
materials and equipment and shall properly store them if necessary and shall provide suitable shelter from
damage and shall erect temporary structures where necessary.
SC-11.03.C Paragraph 11.03.C of the General Conditions is hereby deleted in its entirety and the
following is substituted in its place:
"C. The unit price of an item of Unit Price Work shall be subject to reevaluation and adjustment under
the following conditions:
1. If the total cost of a particular item of Unit Price Work amounts to five percent (5%) or more of the
Contract Price and the variation in the quantity of that particular item of Unit Price Work performed by
Contractor differs by more than twenty-five percent (25%) from the estimated quantity of such item
indicated in the Agreement; and
2. If there is no corresponding adjustment with respect to any other item of Work; and
3. If CONTRACTOR believes that it has incurred additional expense as a result thereof; or if OWNER
believes that the quantity variation entitles it to an adjustment in the Unit Price, either OWNER or
CONTRACTOR may make a claim for an adjustment in the Contract Price in accordance with Article 10
if the parties are unable to agree as to the effect of any such variations in the quantity of Unit Price Work
performed."
SC-13.03.B CONTRACTOR shall employ and pay for the services of an independent testing laboratory
acceptable to the OWNER and the ENGINEER to perform all inspections, tests, or approvals required by
the Contract Documents except:
1. that costs incurred in connection with tests or inspections conducted pursuant to paragraph 13.04.B
of the General Conditions shall be paid as provided in said paragraph 13.04.B; and
2. as otherwise specifically provided in the Contract Documents.
14.02.B.5 In addition to reasons listed in G.C. 14.02.B.5.a through 14.02.B.5.d, the ENGINEER may
refuse to recommend the whole or any part of any payment to the CONTRACTOR because liability for
liquidated damages has been incurred by the CONTRACTOR.
S.C.-14.05.A Add
