Okaloosa County BOCC — March 4, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 23 of 40. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 36-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
period hereunder with respect to such Work will be
13.06 Correction or Removal of Defective Work extended for an additional period of one year after such
correction or removal and replacement has been
A. CONTRACTOR shall correct all defective Work, satisfactorily completed.
whether or not fabricated, installed, or completed, or, if the
Work has been rejected by ENGINEER, remove it from the D. CONTRACTOR’s obligations under this
Project and replace it with Work that is not defective. paragraph 13.07 are in addition to any other obligation or
CONTRACTOR shall pay all Claims, costs, losses, and warranty. The provisions of this paragraph 13.07 shall not
damages (including but not limited to all fees and charges be construed as a substitute for or a waiver of the
of engineers, architects, attorneys, and other professionals provisions of any applicable statute of limitation or repose.
and all court or arbitration or other dispute resolution costs)
arising out of or relating to such correction or removal 13.08 Acceptance of Defective Work
(including but not limited to all costs of repair or
replacement of work of others). A. If, instead of requiring correction or removal and
replacement of defective Work, OWNER (and, prior to
13.07 Correction Period ENGINEER’s recommendation of final payment,
ENGINEER) prefers to accept it, OWNER may do so.
A. If within one year after the date of Substantial CONTRACTOR shall pay all Claims, costs, losses, and
Completion or such longer period of time as may be damages (including but not limited to all fees and charges
prescribed by Laws or Regulations or by the terms of any of engineers, architects, attorneys, and other professionals
applicable special guarantee required by the Contract and all court or arbitration or other dispute resolution costs)
Documents or by any specific provision of the Contract attributable to OWNER’s evaluation of and determination
Documents, any Work is found to be defective, or if the to accept such defective Work (such costs to be approved
repair of any damages to the land or areas made available by ENGINEER as to reasonableness) and the diminished
for CONTRACTOR’s use by OWNER or permitted by value of the Work to the extent not otherwise paid by
Laws and Regulations as contemplated in paragraph 6.11.A CONTRACTOR pursuant to this sentence. If any such
is found to be defective, CONTRACTOR shall promptly, acceptance occurs prior to ENGINEER’s recommendation
without cost to OWNER and in accordance with of final payment, a Change Order will be issued
OWNER’s written instructions: (i) repair such defective incorporating the necessary revisions in the Contract
land or areas, or (ii) correct such defective Work or, if the Documents with respect to the Work, and OWNER shall be
defective Work has been rejected by OWNER, remove it entitled to an appropriate decrease in the Contract Price,
from the Project and replace it with Work that is not reflecting the diminished value of Work so accepted. If the
defective, and (iii) satisfactorily correct or repair or remove parties are unable to agree as to the amount thereof,
and replace any damage to other Work, to the work of OWNER may make a Claim therefore as provided in
others or other land or areas resulting there from. If paragraph 10.05. If the acceptance occurs after such
CONTRACTOR does not promptly comply with the terms recommendation, an appropriate amount will be paid by
of such instructions, or in an emergency where delay would CONTRACTOR to OWNER.
cause serious risk of loss or damage, OWNER may have
the defective Work corrected or repaired or may have the 13.09 OWNER May Correct Defective Work
rejected Work removed and replaced, and all Claims, costs,
losses, and damages (including but not limited to all fees
General Conditions Page 00700-36
A. If CONTRACTOR fails within a reasonable time ARTICLE 14 - PAYMENTS TO CONTRACTOR AND
after written notice from ENGINEER to correct defective COMPLETION
Work or to remove and replace rejected Work as required ______________________________________________
by ENGINEER in accordance with paragraph 13.06.A, or
if CONTRACTOR fails to perform the Work in accordance 14.01 Schedule of Values
with the Contract Documents, or if CONTRACTOR fails to
comply with any other provision of the Contract A. The schedule of values established as provided in
Documents, OWNER may, after seven days written notice paragraph 2.07.A will serve as the basis for progress
to CONTRACTOR, correct and remedy any such payments and will be incorporated into a form of Applica-
deficiency. tion for Payment acceptable to ENGINEER. Progress
payments on account of Unit Price Work will be based on
B. In exercising the rights and remedies under this the number of units completed.
paragraph, OWNER shall proceed expeditiously. In
connection with such corrective and remedial action, 14.02 Progress Payments
OWNER may exclude CONTRACTOR from all or part of
the Site, take possession of all or part of the Work and A. Applications for Payments
suspend CONTRACTOR’s services related thereto, take
possession of CONTRACTOR’s tools, appliances, con- 1. At least 20 days before the date estab-
struction equipment and machinery at the Site, and lished for each progress payment (but not more
incorporate in the Work all materials and equipment stored often than once a month), CONTRACTOR shall
at the Site or for which OWNER has paid CONTRACTOR submit to ENGINEER for review an Application for
but which are stored elsewhere. CONTRACTOR shall Payment filled out and signed by CONTRACTOR
allow OWNER, OWNER’s representatives, agents and covering the Work completed as of the date of the
employees, OWNER’s other contractors, and ENGINEER Application and accompanied by such supporting
and ENGINEER’s Consultants access to the Site to enable documentation as is required by the Contract
OWNER to exercise the rights and remedies under this Documents. If payment is requested on the basis of
paragraph. materials and equipment not incorporated in the
Work but delivered and suitably stored at the Site or
C. All Claims, costs, losses, and damages (including at another location agreed to in writing, the
but not limited to all fees and charges of engineers, Application for Payment shall also be accompanied
architects, attorneys, and other professionals and all court by a bill of sale, invoice, or other documentation
or arbitration or other dispute resolution costs) incurred or warranting that OWNER has received the materials
sustained by OWNER in exercising the rights and remedies and equipment free and clear of all Liens and
under this paragraph 13.09 will be charged against evidence that the materials and equipment are
CONTRACTOR, and a Change Order will be issued covered by appropriate property insurance or other
incorporating the necessary revisions in the Contract arrangements to protect OWNER’s interest therein,
Documents with respect to the Work; and OWNER shall be all of which must be satisfactory to OWNER.
entitled to an appropriate decrease in the Contract Price. If
the parties are unable to agree as to the amount of the 2. Beginning with the second Application
adjustment, OWNER may make a Claim therefore as for Payment, each Application shall include an
provided in paragraph 10.05. Such claims, costs, losses affidavit of CONTRACTOR stating that all
and damages will include but not be limited to all costs of previous progress payments received on account of
repair, or replacement of work of others destroyed or the Work have been applied on account to discharge
damaged by correction, removal, or replacement of CONTRACTOR’s legitimate obligations associated
CONTRACTOR’s defective Work. with prior Applications for Payment.
D. CONTRACTOR shall not be allowed an exten- 3. The amount of retainage with respect to
sion of the Contract Times (or Milestones) because of any pro-gress payments will be as stipulated in the
delay in the performance of the Work attributable to the Agreement.
exercise by OWNER of OWNER’s rights and remedies
under this paragraph 13.09. B. Review of Applications
1. ENGINEER will, within 10 days after
receipt of each Application for Payment, either
indicate in writing a recommendation of payment
and present the Application to OWNER or return
the Application to CONTRACTOR indicating in
writing ENGINEER’s reasons for refusing to
General Conditions Page 00700-37
recommend payment. In the latter case, CON- Regulations applicable to CONTRACTOR’s
TRACTOR may make the necessary corrections performance of the Work. Additionally, said review
and resubmit the Application. or recommendation will not impose responsibility
on ENGINEER to make any examination to
2. ENGINEER’s recommendation of any ascertain how or for what purposes
payment requested in an Application for Payment CONTRACTOR has used the moneys paid on
will constitute a representation by ENGINEER to account of the Contract Price, or to determine that
OWNER, based on ENGINEER’s observations on title to any of the Work, materials, or equipment has
the Site of the executed Work as an experienced and passed to OWNER free and clear of any Liens.
qualified design professional and on ENGINEER's
review of the Application for Payment and the SEE ALSO SUPLEMENTARY CONDITIONS
accompanying data and schedules, that to the best of (SECTION 00800)
ENGINEER’s knowledge, information and belief: