READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — 2013 meeting #1140 (date undetermined) — Fee Schedule Matrix Design Group — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 50-Fee Schedule Matrix Design Group.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Scope of Work, Task List, and Fee Schedule
Okaloosa County RESTORE Act Consultant
June 24, 2013
Matrix Design Group (Matrix) prepared a written proposal and provided an oral
presentation to the committee charged with selecting a management consult to provide
services related to RESTORE Act funding (RFP #: BCC-19-13). This proposal and a copy of the
presentation were provided to the selection committee. Based on all factors (the written
proposal, the formal presentation, and the question and answer period), the committee
selected Matrix as the highest ranked offeror; the Okaloosa Board of County Commissioners
approved the recommendation on June 18, 2013.
As we move to the fee negotiation phase, this letter summarizes the proposed scope of
work, provides a proposed task list, a brief milestone schedule, and summarizes with an
initial fee schedule. If requested, Matrix will provide a more detailed breakdown of the task
list during face-to-face discussions.
Scope of Work
The Matrix team will utilize our experience of the local area, the State of Florida, and
throughout the country to successfully address each of the requirements outlined in the
RFP. Our team will obtain public input, offer technical support, refine the information, and
deliver an effective and fully-compliant program for Okaloosa County. Our familiarity and
understanding of the project requirements enable an efficient, transparent process that
ensures Okaloosa County optimizes available resources for economic recovery and
restoration of our ecological treasures. The Matrix-led team will assist the County in the
development of a Multi-Year Plan and the formulation of a comprehensive roadmap to help
restore and protect our portion of the Gulf Coast region impacted by the Deepwater
Horizon oil spill. We envision this effort as the first year of a multi-year relationship with
the County.
Specifically, the following tasks will be completed for this effort:
Task 1 Meetings (internal to Okaloosa County) and Public Engagement
Matrix will meet (at varying frequencies) with a number of officials and representatives
from the County. This group will include the Board of County Commissioners, the County
Administrator, the RESTORE Advisor, the Okaloosa County Advisory Committee (ORAC), and
various members of the Okaloosa County Staff (Public Works, TDC, Growth Mgt). These
meetings will be crucial in ensuring we achieve the objects of the County and critical to our
facilitation process. We will obtain information relative to the effort, set project goals and
timetables, review opportunities and discuss project constraints (among many other issues).
We understand a working dialogue is critical to this process and must occur to obtain
meaningful input from key stakeholders and partners. Our approach includes an iterative
and collaborative methodology to continuously receive and process inputs from vested
parties. We anticipate this project will demand a high degree of facilitation, program
management, communication, and consensus building.
As part of this task, Matrix will meet with and facilitate information gathering from a
number of constituents (stakeholders) in Okaloosa County. Public engagement will most
likely occur in conjunction with regularly scheduled ORAC meetings or similar public forums.
A unique aspect of our approach is to provide a wide range of facilitation and consensus
building methods that provide both active and passive opportunities for input. If the
County chooses to host workshops (or gather input in a regularly scheduled setting), one
preferred method of participation includes interactive sessions where participants are able
to gather in small groups and work together to determine issues, ideas, and solutions. It
includes the use of easy to use electronic audience response systems. These systems allow
audience interaction by selecting their response on a wireless keypad that can be linked
into the presentation, encouraging full participation and the display of immediate results.
Task 2 Meeting / Engagement (external to Okaloosa County)
Matrix will meet (at varying frequencies) with a number of officials and representatives
from outside the County. Just a brief summary of these potential partners and stakeholders
include surrounding counties, state-level governmental agencies (Dept of Environmental
Protection, Florida Fish and Wildlife, Florida Department of Labor, etc), state-level non- or
quasi-governmental agencies (Workforce Florida, Florida Forever, Florida Consortium, etc),
regional and local agencies (Economic Development Council of Okaloosa County, NW
Florida Water Management District, etc), and numerous federal agencies (Department of
Labor, Department of Treasury, Department of Defense, etc). These meetings will be vital
in ensuring we meet the objectives of the County and will help inform our process. The
interface/dialogue generated by this external engagement will also be key for our project
and grant submittal process.
Task 3 Metric and Data Collection Development
Matrix will work with the individuals and offices identified in Task 1 (BCC, County
Administrator, ORAC, etc) to develop project evaluation metrics and a data collection tool.
Both products will be utilized in Task 4.
Task 4 Data Analysis
Matrix will work with the individuals and offices identified in Task 1 (BCC, County
Administrator, ORAC, etc) to analyze the data collected under Task 3. This will include
feasibility analysis, cost estimating, project impact, financial modeling, and general
database management.
Task 5 Research
As this process is still being defined, Matrix will continue to research the latest
developments on the RESTORE Act, to include possible avenues of funding and limitations
of the various financial sources. The information gathered during the research task will be
shared with the various constituents identified in Task 1.
Task 6 Deliverables
Tasks 1 and 2 require a significant amount of support materials, which in general, includes:
briefing slides; survey tools; and, handouts. Matrix will also assist in website currency
(theme and content verses actual web-design or management), grant writing, and project
submittals. Ultimately, the efforts outlined in many of the above tasks will result in a Multi-
Year Implementation Plan, which Matrix will help produce in coordination with the
individuals and offices identified in Task 1 (BCC, County Administrator, ORAC, etc)
Additional Services Not in Contract (NIC)
Any services outside of this scope of work or substantial changes to the effort based on
direction from Okaloosa County will require a revision in scope and fee. Matrix has
provided a Standard Fee Schedule along with this letter. Matrix will not proceed with any
additional work without prior approval of the Client. All project expenses including fees
incurred (outside county travel, per diem, tolls, etc) will be billed at cost without markup.
Matrix proposes we use county rates for cost calculations.
Proposed Project Schedule Milestones
Contract Execution July 5, 2013
Meetings (internal to Okaloosa County) and Public Engagement On-going (NTP+7 days)
Meeting / Engagement (external to Okaloosa County) On-going (NTP+14 days)
Metrics and Data Collection Development Sep 2, 2013
Data Analysis On-going (after approval of data collection tool)
Multi-Year Plan Dec 15, 2013
Research On-going (NTP+7 days)
Other Deliverables Jun 30, 2014
Fee Schedule (Lump Sum)
Task 1 - Meetings (internal to Okaloosa County) and Public Engagement $40,950
Task 2 - Meeting / Engagement (external to Okaloosa County) $30,600
Task 3 - Metrics and Data Collection Development S 5,250
Task 4 - Data Analysis $28,188
Task 5 — Research S 8,775
Task 6 - Deliverables (to include Multi-Year Plan) $30,673
Subtotal Fee (Lump Sum) $144,436
Project Expenses (Pass Through Expenses as Incurred) S$ 3,000
Total Fee $147,436
Billing Method
Matrix will bill Okaloosa County at the end of each month for services rendered. The fee
will cover all incurred expenses for the month and the remittance shall be considered
progress payments towards the overall scope of work. A letter summarizing
accomplishments by task, hours consumed, and percentage of progress will accompany the
monthly invoice. An invoice will be submitted for every month for the duration of the
contract (12 months).
Option Years
Matrix stands ready to support Okaloosa County as its RESTORE Act Consultant for the
duration of the RESTORE program. As such, the terms laid out in this agreement shall serve
as a baseline for the options years the Client elects to pursue. Matrix may request a small
inflationary adjustment to our standard schedule (not to exceed 3% per year), which can be
addressed during scope of work negotiations. Matrix understands the Board of County
Commissioners will need to approve any extensions to this contract. As we have done in
this baseline year of the contract, Matrix will work extremely hard to keep rates competitive
and provide the Client the best possible value for their investment.
Matrix ag
DESIGN GROUP
STANDARD HOURLY RATES
2013
Classification Hourly Rate
Principal $230.00
Vice President $190.00
Senior Associate $150.00
Associate $130.00
Sr. Consultant $125.00
Consultant III $110.00
Consultant II $100.00
Consultant | $ 90.00
Professional Ill $ 95.00
Professional II $ 85.00
Professional | $ 75.00
Staff V $ 95.00
Staff IV $ 79.00
Staff Ill $ 70.00
Staff Il $ 60.00
Staff | $ 45.00
1- Person Survey Crew $ 100.00
2- Person Survey Crew $ 140.00
3- Person Survey Crew $ 190.00
If applicable, mileage will be charged at the Federal government allowable rate. All other
direct expenses attributable to the Project will be charged to Client at cost.
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: June 18, 2013
TO: Honorable Chairman and Members of the Board
FROM: Richard Brannon
SUBJECT: Restore Act Consulting Firm Selection
DEPARTMENT: _ Purchasing
BCC DISTRICT: = All
STATEMENT OF ISSUE: Proposals to provide Restore Act Consulting Services were opened
on April 19, 2013. Proposals were received from ten (10) firms (see attached list). The Board
Appointed Review Committee (attached) met on May 22, 2013, reviewed all proposals received
and short listed three (3) firms for presentations. On June 10, 2013 the Committee met, heard
presentations and ranked the firms as follows:
1. Matrix Design Group - Niceville, FL
2. CH2MuHill - Pensacola, FL
3. Tetra Tech - Destin, FL
The resulting contract would provide assistance to the Board in developing a multi year plan
related to Restore Act Funding and help with oversight to ensure funds spent will maximize
ecological and economical benefits. It is anticipated that the cost of this contract will be
reimbursed through administrative fees paid through the Restore Act.
OPTIONS: Approve the Ranking or Reject.
RECOMMENDATION: Staff recommendation is to approve the ranking and allow staff to
negotiate fees with Matrix Design Group. Fees would be brought back to the Board for
approval.
VA
Richard Brannon, Diréétor” j 6/12/2013
RECOMMENDED BY: