Okaloosa County BOCC — July 6, 2016 — Revisions — reading text
Part 2 of 8. These parts divide the reading text for browsing; they are not the source document's page numbers.
Revisions — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Parties List System. Even though the
recipient may collect a debarment and suspension certification from the prospective third party
contractor, or include a clause in the third party contract requiring disclosure, FTA strongly
recommends that the recipient check the Excluded Parties List System (EPLS). Now a part of the
System for Awards Management (SAM), the EPLS is an electronic, web-based system that
identifies those parties excluded from receiving Federal contracts, certain subcontracts, and
certain types of Federal financial and non-financial assistance and benefits. The EPLS keeps its
user community aware of administrative and statutory exclusions across the entire government,
and individuals barred from entering the United States. Go to www.sam.gov and the Extracts
and Data Access area and click on the Public Data Access box to find the individual firm,
individual or vessel you may seek
Buy America Pre-Award Review (Steel or manufactured products)
49 CFR 661.6
661.6 Certification requirements for procurement of steel or manufactured products.
If steel, iron, or manufactured products (as defined in §§ 661.3 and 661.5 of this part) are being
procured, the appropriate certificate as set forth below shall be completed and submitted by each
bidder or offeror in accordance with the requirement contained in § 661.13(b) of this part.
Certificate of Compliance with Buy America Requirements
The bidder or offeror hereby certifies that it will comply with the requirements of 49 U.S.C.
5323(j)(1), and the applicable regulations in 49 CFR part 661.
Date
Signature
Company
Name
Title
Certificate of Non-Compliance with Buy America Requirements
The bidder or offeror hereby certifies that it cannot comply with the requirements of 49 U.S.C.
5323(j), but it may qualify for an exception to the requirement pursuant to 49 U.S.C. 5323(j)(2),
as amended, and the applicable regulations in 49 CFR 661.7.
Date
Signature
Company
Name
Title
Brooks Act/ Qualifications-based procurements
FTA C4220.1F, IV, 2.h.(1); (2) (a)
(1) Qualifications-Based Requirements. For projects related to or leading to construction, an
FTA recipient must use the qualifications-based procurement procedures of 40 U.S.C.
Chapter 11 (“Brooks Act” procedures) when contracting for A&E services and other services
described in 49 U.S.C. Section 5325(b), which include program management, construction
management, feasibility studies, preliminary engineering, design, architectural, engineering,
surveying, mapping, or related services.
(2)(a) Purpose of Services. (2) (a) FTA has long administered the requirement for using
qualifications-based procurement procedures for selection of contractors that perform A&E
services, generally associated with the construction, alteration, or repair of real property. FTA
interprets 49 U.S.C. Section 5325(b) to authorize the use of qualifications-based procurement
procedures only for those services that directly support or are directly connected or related to
construction, alteration, or repair of real property. FTA’s interpretation of 49 U.S.C. Section
5325(b) is consistent with typical Federal policies implementing the “Brooks Act,” 40 U.S.C.
Section 1102, which limits qualifications-based procurement procedures to research, planning,
development, design, construction, alteration, or repair of real property. Thus if services, such as
program management, feasibility studies, or mapping, are not directly in support of, directly
connected to, or directly related to, or lead to construction, alteration, or repair of real property,
then the recipient may not use qualifications-based procurement procedures to select the
contractor that will perform those services.
Construction Contract Bonds
Contractors shall provide performance and construction bonds for construction contracts greater than
$100,000 in value as follows:
(a) Performance Bond. Both FTA and the Common Grant Rules generally
require the third party contractor to obtain a performance bond for 100 percent
of the contract price. A “performance bond” is obtained to ensure completion
of the obligations under the third party contract.
(b) Payment Bond. The Common Grant Rules generally require the third party
contractor to obtain a standard payment bond for 100 percent of the contract
price. A “payment bond” is obtained to ensure that the contractor will pay all
people supplying labor and material for the third party contract as required by
law. FTA, however, has determined that payment bonds in the following
amounts are adequate to protect FTA’s interest and will accept a local bonding
policy that meets the following minimums:
1 Less Than $1 Million. Fifty percent of the contract price if the contract
price is not more than $1 million,
2 More Than $1 Million but Less Than $5 Million. Forty percent of the
contract price if the contract price is more than $1 million but not more
than $5 million, or
3 More Than $5 Million. Two and one half million dollars if the contract
price is more than $5 million.
Design-Bid-Build
FTA C4220.1F, VI, 3.g.
Design-Bid-Build. The design-bid-build procurement method requires separate contracts for
design services and for construction.
Design Services. For design services, the recipient must use qualifications-based procurement
procedures, in compliance with applicable Federal, State and local law and regulations.
Construction. Because the recipient may not use qualifications-based procurement procedures
for the actual construction, alteration or repair of real property, the recipient generally must use
competitive procedures for the construction. These may include sealed bidding or competitive
negotiation procurement methods, as appropriate.
Design-Build
FTA C4220.1F, VI, 3.h.
h. Design-Build. The design-build procurement method consists of contracting for design and
construction simultaneously with contract award to a single contractor, consortium, joint venture,
team, or partnership that will be responsible for both the project’s design and construction.
FTA’s enabling legislation expressly authorizes the use of FTA capital assistance to support
design-build projects “after the recipient complies with Government requirements,” 49 U.S.C.
Section 5325(d)(2).
(1) Procurement Method Determined by Value. First, the recipient must separate the various
contract activities to be undertaken and classify them as design or construction, and then
calculate the estimated total value of each. Because both design and construction are included in
a single procurement, the FTA expects the recipient to use the procurement method appropriate
for the services having the greatest cost, even though other necessary services would not
typically be procured by that method.
(a) Construction Predominant. The construction costs of a design-build project are usually
predominant so that the recipient would be expected to use competitive negotiations or sealed
bids for the entire procurement rather than the qualification-based “Brooks Act” procurement
procedures. Specifically, when construction costs will be predominant, unless FTA determines
otherwise in writing, an FTA recipient may not use qualifications-based procurement procedures
to acquire architectural engineering, program management, construction management, feasibility
studies, preliminary engineering, design, architectural and engineering, surveying, mapping, or
related A&E services unless required by State law adopted before August 10, 2005.
(b) Design Services Predominant. In the less usual circumstance in which the cost of most work
to be performed will consist of costs for architectural and engineering, program management,
construction management, feasibility studies, preliminary engineering, design, architectural
engineering, surveying, mapping, or related A&E services, FTA expects the recipient to use
qualifications-based procurement procedures based on the “Brooks Act,” 40 U.S.C. Sections
1101 through 1104, as described in subsection 3.e of this Chapter.
(2) Selection Processes. The recipient may structure its design-build procurement using one or
more steps as described below:
(a) One-Step Method. The recipient may undertake its design-build procurement in a single
step.
(b) Two-Step Method. Another procurement method the recipient may use for large design-
build projects is a two-step selection process as authorized for Federal Government use by 41
U.S.C. Section 253m. This method consists of:
Review of Technical Qualifications and Approach. The first step is a review of the prospective
contractors’ technical qualifications and technical approach to the project. The recipient may
then narrow the competitive range to those prospective contractors with satisfactory
qualifications that demonstrate a technically satisfactory approach.
Review of Complete Proposals. The second step consists of soliciting and reviewing complete
proposals, including price, submitted by prospective contractors first determined to be qualified.
By using this two-step method, it will not be necessary for the recipient to undertake extensive
proposal reviews, nor will prospective offerors need to engage in expensive proposal drafting.
This two-step selection procedure is separate and distinct from prequalification and is but one
procurement method available to the recipient.
Tag-Ons
FTA C4220.1F, V,7. b.(2)
(2) Cardinal Changes. A significant change in contract work (property or services) that causes a
major deviation from the original purpose of the work or the intended method of achievement, or
causes a revision of contract work so extensive, significant, or cumulative that, in effect, the
contractor is required to perform very different work from that described in the original contract,
is a cardinal change. Such practices are sometimes informally referred to as “tag-ons.” A
change within the scope of the contract (sometimes referred to as an “in-scope” change) is not a
“tag-on” or cardinal change.
(a) Identifying Cardinal Changes. Although FTA has provided additional guidance in its Best
Practices Procurement Manual, FTA has not developed a finite list of acceptable contract
changes. Recognizing a cardinal change to a third party contract can be difficult. A cardinal
change cannot be identified easily by assigning a specific percentage, dollar value, number of
changes, or other objective measure that would apply to all cases.
(b) Changes in Quantity. To categorize virtually any change in quantity as a prohibited cardinal
change (sometimes referred to as an “out-of-scope” change) fails to account for the realities of
the marketplace and unnecessarily restricts a recipient from exercising reasonable freedom to
make minor adjustments contemplated fairly and reasonably by the parties when they entered
into the contract. The U.S. Supreme Court decision in Freund v. United States, 260 U.S. 60
(1922) supports FTA’s policy.
(c) Tests. Among other things, customary marketing practices can influence the determination
of which changes will be “cardinal.” Other tests involve the nature and extent of the work to be
performed, the amount of effort involved, whether the change was originally contemplated at the
time the original contract was entered into, or the cumulative impact on the contract’s quantity,
quality, costs, and delivery terms.
(d) Rolling Stock. In the case of rolling stock, a major change in quantity or a substitution of
major end items not contemplated when competition for the original award took place would
generally be a cardinal change. Another cardinal change would, at this time, include a change
from a high-floor to a low-floor vehicle.