30.4 Coordinate and Develop MOT Plans for Field Investigation
Coordinate and develop Maintenance of Traffic (MOT) plan. Work zone traffic
control will be performed in accordance with the FDOT’s Roadway and
Traffic Design Standards Index 600 series.
30.5 Drilling Access Permits
Obtain State, County, City, and Water Management District permits for
performing geotechnical borings, as needed.
30.6 Property Clearances
Notify property tenants in person of drilling and field activities, if applicable.
Written notification to property owners/tenants is the responsibility of the
COUNTY’s Project Manager.
30.7 Groundwater Monitoring
Monitor groundwater, using piezometers.
30.8 LBR / Resilient Modulus Sampling
Collect appropriate samples for Limerock Bearing Ratio (LBR) testing.
30.9 Coordination of Field Work
Coordinate field work required to provide geotechnical data for the project.
30.10 Soil and Rock Classification - Roadway
Refine soil profiles recorded in the field, based on results of laboratory
testing.
30.11 Design LBR
Determine design LBR values from the 90% and mean methods.
30.12 Laboratory Data
Tabulate laboratory test results for inclusion in the geotechnical report, the
report of tests sheet (Roadway Soil Survey Sheet), and for any necessary
calculations and analyses.
30.13 Seasonal High Water Table
Review the encountered ground water levels and estimate seasonal high
ground water levels. Estimate seasonal low ground water levels, if requested.
30.14 Parameters for Water Retention Areas
Calculate parameters for water retention areas, exfiltration trenches, and/or
swales.
30.15 Delineate Limits of Unsuitable Material
Delineate limits of unsuitable material(s) in both horizontal and vertical
directions. Assist the Engineer of Record with detailing these limits on the
cross-sections. If requested, prepare a plan view of the limits of unsuitable
material.
30.16 Electronic Files for Cross-Sections
Create electronic files of boring data for cross-sections.
30.17 Embankment Settlement and Stability
Estimate the total magnitude and time rate of embankment settlements.
Calculate the factor of safety against slope stability failure.
30.18 Stormwater Volume Recovery and/or Background Seepage Analysis
Perform stormwater volume recovery analysis as directed by the COUNTY.
30.19 Geotechnical Recommendations
Provide geotechnical recommendations regarding the proposed roadway
construction project including the following: description of the site/alignment,
design recommendations and discussion of any special considerations (i.e.
removal of unsuitable material, consolidation of weak soils, estimated
settlement time/amount, groundwater control, high groundwater conditions
relative to pavement base, etc.) Evaluate and recommend types of
geosynthetics and properties for various applications, as required.
30.20 Pavement Condition Survey and Pavement Evaluation Report (Not
applicable to this project)
30.21 Preliminary Roadway Report
If a preliminary roadway investigation is performed, submit a preliminary
roadway report before the Phase II plans submittal. The purpose of the
preliminary roadway report will be to assist in setting road grades and
locating potential problems.
Copies of U.S.G.S. and S.C.S. maps with project limits shown.
A report of tests sheet that summarizes the laboratory test results, the
soil stratification (i.e. soils grouped into layers of similar materials) and
construction recommendations relative to Standard Indices 500 and 505.
Results of tasks discussed in the previous section (Data Interpretation
and Analysis).
An appendix that contains stratified soil boring profiles, laboratory test
data sheets, sample embankment settlement and stability calculations,
design LBR calculation/graphs, and other pertinent calculations.
The CONSULTANT will respond in writing to any changes and/or
comments from the COUNTY and submit any responses and revised
reports.
30.22 Final Report
The Final Roadway Report shall include the following:
Copies of U.S.G.S. and S.C.S. maps with project limits shown.
A report of tests sheet that summarizes the laboratory test results, the
soil stratification (i.e. soils grouped into layers of similar materials) and
construction recommendations relative to Standard Indices 500 and 505.
Results of tasks discussed in the previous section (Data Interpretation
and Analysis).
An appendix that contains stratified soil boring profiles, laboratory test
data sheets, sample embankment settlement and stability calculations,
design LBR calculation/graphs, and other pertinent calculations.
The CONSULTANT will respond in writing to any changes and/or
comments from the COUNTY and submit any responses and revised
reports.
30.23 Auger Boring Drafting
Draft auger borings as directed by the COUNTY.
30.24 SPT Boring Drafting
Draft SPT borings as directed by the COUNTY.
Structures (Not applicable to this project)
30.47 Other Geotechnical (Not applicable to this project)
30.48 Technical Special Provisions
30.49 Field Reviews
Identify and note surface soil and rock conditions, surface water conditions
and locations, and preliminary utility conflicts. Observe and note nearby
structures and foundation types.
30.50 Technical Meetings
30.51 Quality Assurance/Quality Control
30.52 Supervision
30.53 Coordination
30.54 Optional Preliminary Contamination Assessment (Not applicable to this
project)
31 ARCHITECTURE DEVELOPMENT (Not applicable to this project)
32 NOISE BARRIERS IMPACT DESIGN ASSESSMENT IN THE DESIGN PHASE
(Not applicable to this project)
33 INTELLIGENT TRANSPORTATION SYSTEMS ANALYSIS (Not applicable to this
project)
34 INTELLIGENT TRANSPORTATION SYSTEM PLANS (Not applicable to this
project)
35 PROJECT REQUIREMENTS
35.1 Liaison Office
The COUNTY and the CONSULTANT will designate a Liaison Office and a
Project Manager who shall be the representative of their respective
organizations for the Project. While it is expected the CONSULTANT shall
seek and receive advice from various state, regional, and local agencies, the
final direction on matters of this project remain with the COUNTY Project
Manager.
35.2 Key Personnel
The CONSULTANT’s work shall be performed and directed by the key
personnel identified in the proposal presentations by the CONSULTANT. Any
changes in the indicated personnel shall be subject to review and approval
by COUNTY.
35.3 Progress Reporting
The CONSULTANT shall meet with the COUNTY as required and shall
provide a written progress and schedule status reports that describe the work
performed on each task. Progress and schedule status reports shall be
delivered to the COUNTY concurrently with the monthly invoice. The Project
Manager will make judgment on whether work of sufficient quality and
quantity has been accomplished by comparing the reported percent complete
against actual work accomplished.
35.4 Correspondence
Copies of written correspondence between the CONSULTANT and any party
pertaining specifically to this contract shall be provided to the COUNTY for
their records within one (1) week of the receipt or mailing of said
correspondence.
35.5 Professional Endorsement
The CONSULTANT shall have a Registered Professional Engineer in the
State of Florida sign and seal reports, documents, and plans as required by
COUNTY standards.
35.6 Computer Automation
The project will be developed utilizing Computer Aided Drafting and Design
(CADD) systems. The COUNTY makes available software to help assure
quality and conformance with policy and procedures regarding CADD. It is
the responsibility of the CONSULTANT to meet the requirements in the
FDOT’s CADD Manual. The CONSULTANT will submit final documents and
files as described therein.
35.7 Coordination with Other Consultants
The CONSULTANT is to coordinate his work with any and adjacent and
integral consultants so as to effect complete and homogenous plans and
specifications for the project(s) described herein.
35.8 Optional Services
At the COUNTY’s option, the CONSULTANT may be requested to provide
optional services. The fee for these services shall be negotiated for a fair,
competitive and reasonable cost, considering the scope and complexity of
the project(s). Additional services may be authorized by Letter of
Authorization or supplemental amendment in accordance with paragraph
2.00 of the Standard Consultant Agreement. The additional services may
include Construction Assistance, Review of Shop Drawings, Final Bridge
Load Rating, update (Category II) bridge plans electronically (CADD) for the
Final "As-Built" conditions, based on documents provided by the COUNTY
(CADD Services Only) or other Services as required.
36 INVOICING LIMITS
Payment for the work accomplished will be in accordance with Method of
Compensation of this contract. Invoices shall be submitted to the COUNTY, in a
format prescribed by the COUNTY. The COUNTY Project Manager and the
CONSULTANT shall monitor the cumulative invoiced billings to insure the
reasonableness of the billings compared to the project schedule and the work
accomplished and accepted by the COUNTY.
The CONSULTANT will provide a list of key events and the associated total
percentage of work considered to be complete at each event. This list will be used
to control invoicing. Payments will not be made that exceed the percentage of work
for any event until those events have actually occurred and the results are
acceptable to the COUNTY.