Okaloosa County BOCC — October 7, 2014 — FOY SHAW SCOPE OF SERVICES_PHASE II DESIGN — reading text
Part 4 of 7. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 154-FOY SHAW SCOPE OF SERVICES_PHASE II DESIGN.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Plans, USGS Quadrangles, USGS Studies,
NWFWMD Studies, FEMA Studies, Local Government Agency Studies or Contours,
etc. The drainage map should be included in the Hydraulic Design Study. The
Hydrology should be by regional or local regression equations, or by the rational
method. An assumed velocity should not be used. The CONSULTANT shall
document the Drainage Design in the Drainage Design Study. The Design Study
should show that the design requirements of the COUNTY, FDOT and FAA have
been met.
The CONSULTANT has the responsibility for determining the need, appropriate
locations, and sizes for water management facilities, and drainage outfalls. The
CONSULTANT shall refer Phase I – NEPA Environmental Assessment for
preliminary pond sites studied. The CONSULTANT shall be advised that pond
locations must be located within the footprint of the Phase I – NEPA Environmental
Assessment. The CONSULTANT shall evaluate the need for diversion ditch
systems along the project length to prevent comingling of overland runoff with
roadway runoff in order to minimize pond sizings.
The CONSULTANT shall provide the COUNTY a Drainage Design Documentation.
The documentation shall include a narrative description of existing and proposed
drainage structures, conditions, and facilities, and a listing of environmental
regulatory permits required. Hydrologic and hydraulic drainage computations for the
design presented in the plans shall be included along with supporting design
information such as drainage maps, geotechnical data (such as soil borings and
permeability tests), and correspondence that directly affected design decisions.
The CONSULTANT shall coordinate fully with the appropriate permitting agencies
and the COUNTY’s staff. Activities and submittals should be coordinated through
the COUTNY’s Project Manager. The work will include the engineering analyses for
any of the following:
6.1 Determine Base Clearance Water Elevation
Analyze, determine, and document high water elevations which will be used
to set roadway profile grade. Determine surface water elevations at cross
drains, floodplains, outfalls and adjacent stormwater ponds. Determine
groundwater elevations at intervals between the above-mentioned surface
waters.
6.2 Pond Siting Analysis and Report
Update Pond Siting Analysis and Report done in the Phase I – NEPA
Environmental Assessment.
6.3 Design of Cross Drains
Analyze the hydraulic design of cross drains. Check existing cross drains to
determine if they are structurally sound and can be extended. Document the
design as required. Determine and provide flood data as required.
6.4 Design of Roadway Ditches
Design roadway conveyance ditches. This includes determining ditch cross
sections, grades, selecting suitable channel lining, designing the side drain
pipes, and documentation.
6.5 Design of Outfalls
Analyze and document the design of ditch or piped outfalls. (Pond outlet
structure included in task 6.6)
6.6 Design of Stormwater Management Facility (Offsite Pond)
Design stormwater management facilities to meet requirements for
stormwater quality treatment and attenuation. Develop proposed pond layout
(shape, contours, slopes, etc.), perform routing calculations, and design the
outlet control structure.
6.7 Design of Stormwater Management Facility (Roadside Ditch as Linear
Pond or Infield Pond) (Not applicable to this project)
6.8 Design of Flood Plain Compensation Area
Determine flood plain encroachments, coordinate with regulatory agencies,
and develop proposed compensation area layout (shape, contours, slopes,
etc.). Document the design following the requirements of the regulatory
agency.
6.9 Design of Storm Drains
Develop a “working drainage map”, determine runoff, inlet locations, and
spread. Calculate hydraulic losses (friction, utility conflict and, if necessary,
minor losses). Determine Design Tailwater and, if necessary, outlet scour
protection.
6.10 Optional Culvert Material
Determine acceptable options for pipe materials.
6.11 French Drain Design (Not applicable to this project)
6.12 Drainage Wells (Not applicable to this project)
6.13 Drainage Design Documentation Report
Compile drainage design documentation into report format. Include
documentation for the drainage design tasks and associated meetings and
decisions, except the Pond Siting Analysis Report.
6.14 Bridge Hydraulic Report (Not applicable to this project)
6.15 Temporary Drainage Analysis (Not applicable to this project)
6.16 Cost Estimate
6.17 Technical Special Provisions (Not applicable to this project)
6.18 Other Drainage Analysis (Not applicable to this project)
6.19 Field Reviews
6.20 Technical Meetings
6.21 Quality Assurance/Quality Control
6.22 Independent Peer Review (Not applicable to this project)
6.23 Supervision
6.24 Coordination
7 UTILITIES
The CONSULTANT shall identify utility facilities and secure agreements, utility work
schedules, and plans from the Utility Agency Owners (UAO) ensuring no conflicts
exist between utility facilities and the COUNTY’s construction project. The
CONSULTANT shall certify utility negotiations have been completed with
arrangements made for utility work to be undertaken.
7.1 Kickoff Meeting (Not applicable to this project)
7.2 Identify Existing UAO(s)
Identify utilities in the corridor; check with Maintenance for Permits, Sunshine
State One Call, Subsurface Utility Engineering (SUE) Report, Design
Location Survey, and Existing Plans.
7.3 Make Utility Contacts
First Contact: Send letters and two sets of plans to each utility, one set for
the utility office, one set each to construction and maintenance if required.
Includes contact by phone for meeting coordination. Request type, size,
location, easements, cost for compensable relocation, and justification for
any utility exceptions. Include the meeting schedule (if applicable) and the
design schedule. Include typical meeting agenda.
Second Contact: At a minimum of 4 weeks prior to the meeting, the
CONSULTANT shall transmit two complete sets of Phase II plans to each
UAO having facilities located within the project limits, and one set to the
COUNTY Offices as required by the District.
Third Contact: Identify agreements and assemble packages. Send
agreements, letters and two sets of plans to the UAO(s) including component
sets, one set for the utility office, one set to construction and maintenance if
required. Include the design schedule. Not all projects will have all contacts
as described above.
7.4 Exception Coordination (Not applicable to this project)
7.5 Preliminary Utility Meeting (Not applicable to this project)
7.6 Individual/Field Meetings
The CONSULTANT shall meet with each UAO separately throughout the
project design duration to provide guidance in the interpretation of plans,
review changes to the plans and schedules, optional clearing and grubbing
work, and assist in the development of the UAO(s) plans and work
schedules. The CONSULTANT is responsible for motivating the UAO to
complete and return the necessary documents after each Utility Contact or
Meeting.
7.7 Collect and Review Plans and Data from UAO(s)
Make Determinations (Compensable Interest, Easements, Coordinate,
Analyze). Ensure information (utility type, material and size) is sent to the
designer for inclusion in the plans. Coordinate programming of funds.
7.8 Subordination of Easements Coordination (Not applicable to this
project)
7.9 Utility Design Meeting (Not applicable to this project)
7.10 Review Utility Markups and Work Schedules and Processing of
Schedules and Agreements
Review utility marked up plans individually as they are received for content
and coordinate review with the designer. Send color markups and schedules
to the appropriate COUNTY office(s) for review and comment if required.
7.11 Utility Coordination/Followup
This includes follow-up, interpreting plans, and assisting and the completion
of the UAO(s) work schedule and agreements. Includes phone calls, face-to-
face meetings, etc., to motivate and ensure the UAO(s) complete and return
the required documents in accordance with the project schedule. Ensure the
resolution of known conflicts. This task can be applied to all phases of the
project.
7.12 Utility Constructability Review
Review utility schedules against construction contract time, and phasing for
compatibility. Coordinate with and obtain written concurrence from the
construction office.
7.13 Additional Utility Services (Not applicable to this project)
.
7.14 Processing Utility Work by Highway Contractor (UWHC) (Not applicable
to this project)
7.15 Contract Plans to UAO(s) (Not applicable to this project)
7.16 Certification/Close-Out
This includes hours for transmitting utility files to the DUO and preparation of
the Utility Certification Letter. The CONSULTANT shall certify to the
appropriate COUNTY representative the following:
Utility negotiations (Full execution of each agreement, approved Utility Work
Schedules, technical special provisions written, etc.) have been completed
with arrangements made for utility work to be undertaken and completed as
required for proper coordination with the physical construction schedule.
OR
An on-site inspection was made and no utility work will be involved.
OR
Plans were sent to the Utility Companies/Agencies and no utility work is
required.
7.17 Other Utilities (Not applicable to this project)
8 ENVIRONMENTAL PERMITS, COMPLIANCE AND CLEARANCES
The CONSULTANT shall notify the COUNTY Project Manager and other
appropriate personnel in advance of scheduled meetings with the regulatory
agencies to allow a COUNTY representative to attend. The CONSULTANT shall
copy in the Project Manager and the Environmental Permit Coordinator on permit
related correspondence and meetings.
8.1 Preliminary Project Research
The CONSULTANT shall perform preliminary project research and shall be
responsible for early identification of and coordination with the appropriate
regulatory agencies to assure that design efforts are properly directed toward
permit requirements.
8.2 Complete Permit Involvement Form
The CONSULTANT shall document permit involvement in coordination with
the COUNTY Project Manager. This is to be done upon completion of
preliminary project research.
8.3 Establish Wetland Jurisdictional Lines and Assessments
The CONSULTANT shall collect data and information necessary to
determine the boundaries of wetlands and surface waters defined by the
rules or regulations of each agency processing or reviewing a permit
application necessary to construct a COUNTY project.
The CONSULTANT is to stake or flag the State and Federal jurisdictional
lines. A registered surveyor will be required to survey these jurisdictional
lines. The consultant must remove stakes or flags after the environmental
permits are approved.
The contractor is