Okaloosa County BOCC — October 7, 2014 — FOY SHAW SCOPE OF SERVICES_PHASE II DESIGN — reading text
Part 3 of 7. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 154-FOY SHAW SCOPE OF SERVICES_PHASE II DESIGN.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
submittals are complete.
The CONSULTANT shall be responsible for the professional quality, technical
accuracy and coordination of surveys, designs, drawings, specifications and other
services furnished by the CONSULTANT under this contract.
The CONSULTANT shall, without additional compensation, correct errors or
deficiencies in the designs, maps, drawings, specifications and/or other services.
Independent Peer Review: (Not applicable to this project)
Supervision: Includes efforts required to supervise technical design activities.
Coordination: Includes efforts to coordinate with disciplines of the project to produce
a final set of construction documents.
Project General Tasks
Project General Tasks, described in Sections 3.1 through 3.7 below, represent work
efforts that are applicable to the project as a whole and not to any one or more
specific project activity. The work described in these tasks shall be performed by
the CONSULTANT when included in the project scope.
3.1 Public Involvement (Not applicable to this project)
This item will be handled under the Phase I – NEPA Environmental
Assessment portion of the scope.
3.1.1 Community Awareness Plan (Not applicable to this project)
3.1.2 Notifications (Not applicable to this project)
3.1.3 Preparing Mailing Lists (Not applicable to this project)
3.1.4 Median Modification Letters (Not applicable to this project)
3.1.5 Driveway Modification Letters (Not applicable to this project)
3.1.6 Newsletters (Not applicable to this project)
3.1.7 Renderings and Fly-Throughs (Not applicable to this project)
3.1.8 PowerPoint Presentations (Not applicable to this project)
3.1.9 Public Meeting Preparations (Not applicable to this project)
3.1.10 Public Meeting Attendance and Follow-up (Not applicable to this
project)
3.1.11 MPO Meetings (Not applicable to this project)
3.1.12 Web Site (Not applicable to this project)
3.2 Joint Project Agreements (Not applicable to this project)
3.3 Specifications Package Preparation
The CONSULTANT shall prepare and provide a specifications package
prepared in accordance with the COUNTY’S standard requirements.
3.4 Contract Maintenance
Contract maintenance includes project management effort for complete setup
and maintenance of files, developing monthly progress reports, schedule
updates, work effort to develop and execute subconsultant agreements, etc.
3.5 Value Engineering (Multi-Discipline Team) Review (Not applicable to
this project)
3.6 Prime Consultant Project Manager Meetings
Includes only the Prime Consultant Project Manager's time for travel and
attendance at Activity Technical Meetings and other meetings listed in the
meeting summary for Task 3.6 on tab 3.0 Project General Task of the staff
hour forms. Staff hours for other personnel attending Activity Technical
Meetings are included in the meeting task for that specific Activity.
3.7 Plans Update (Not applicable to this project)
3.8 Post Design Services
Post Design Services may include, but not limited to, meetings, construction
assistance, plans revisions, shop drawing review, survey services and load
ratings. Specific services will be negotiated as necessary as a contract
amendment.
Post Design Services are not intended for instances of CONSULTANT errors
and/or omissions.
3.9 Electronic Delivery (Not applicable to this project)
3.10 Electronic Delivery (Not applicable to this project)
4 ROADWAY ANALYSIS
The CONSULTANT shall analyze and document Roadway Tasks in accordance
with applicable manuals, guidelines, standards, handbooks, procedures, and
current design memorandums.
4.1 Typical Section Package
The CONSULTANT shall provide an approved Typical Section Package prior
to the Phase II plans submittal date.
4.2 Pavement Design Package
The CONSULTANT shall provide an approved Pavement Design Package in
accordance with applicable FDOT pavement design manuals prior to the
Phase II plans submittal date.
4.3 Access Management
The CONSULTANT shall incorporate access management standards for
each project in coordination with COUNTY staff. The CONSULTANT shall
review adopted access management standards and the existing access
conditions (interchange spacing, signalized intersection spacing, median
opening spacing, and connection spacing). Median openings that will be
closed, relocated, or substantially altered shall be shown on plan sheets and
submitted with supporting documentation for review with the Phase I plans
submittal.
The access management classification information derived from the Phase I
– NEPA Environmental Assessment and public hearings will be used by the
CONSULTANT.
4.4 Horizontal/Vertical Master Design Files
The CONSULTANT shall design the geometrics using the design standards
that are most appropriate with proper consideration given to the design traffic
volumes, design speed, capacity and levels of service, functional
classification, adjacent land use, design consistency and driver expectancy,
aesthetics, pedestrian and bicycle concerns, ADA requirements, elder road
user policy, access management, and the Phase I – NEPA Environmental
Assessment.
4.5 Cross Section Design Files
The CONSULTANT shall establish and develop cross section of the
proposed design at 100’ intervals and any intermediate critical locations to
estimate R/W needs.
4.6 Traffic Control Analysis
The CONSULTANT shall design a safe and effective Traffic Control Plan to
move vehicular and pedestrian traffic during all phases of construction. The
design shall include construction phasing of roadways ingress and egress to
existing property owners and businesses, routing, signing and pavement
markings, and detour quantity tabulations, roadway pavement, drainage
structures, ditches, front slopes, back slopes, drop offs within clear zone, and
traffic monitoring sites.
4.7 Master TCP Design Files (Not applicable to this project)
4.8 Design Variations and Exceptions (Not applicable to this project)
4.9 Design Report
The CONSULTANT shall submit to the COUNTY design notes, data, and
calculations to document the design conclusions reached during the
development of the contract plans.
The design notes, data, and computations shall be recorded on size 8½"x11"
sheets, fully titled, numbered, dated, indexed and signed by the designer and
the checker. Computer output forms and other oversized sheets shall be
folded to 8½"x11" size. The data shall be in a hardback folder for submittal to
the COUNTY.
4.10 Computation Book and Quantities
The CONSULTANT shall prepare the Computation Book and various
summary of quantities sheets. This includes efforts required to develop the
Computation Book and the supporting documentation, including construction
days when required.
4.11 Cost Estimate
The CONSULTANT will compile a Construction Cost Estimate for the Phase
III (90%) and Final Submittals. The CONSULTANT will provide a R/W
acquisition needs estimate based on the design and Pond Siting Report. The
CONSULTANT will supply the R/W acreages and limits as set forth in the
plan set. The CONSULTANT will not supply real estate cost estimates as a
part of this Scope of Services.
4.12 Technical Special Provisions (Not applicable to this project)
4.13 Other Roadway Analysis
Aviation Support Services
The CONSULTANT shall review the final design plans and specifications to
ensure compliance with FAA criteria and the approved ALP for CEW. The
CONSULTANT shall prepare the package for CEW to file FAA Form 7460-1
which shall cover impacted airspace during construction of the project. This
will include the preparation of drawings and calculations required to
accompany FAA Form 7460-1 and the completion of FAA Form 7460-1
Notice of Proposed Construction or Alteration. The preparation of FAA Form
7460-2 will be developed by the selected contractor.
4.14 Field Reviews
4.15 Technical Meetings
4.16 Quality Assurance/Quality Control
4.17 Independent Peer Review (Not applicable to this project)
4.18 Supervision
4.19 Coordination
5 ROADWAY PLANS
The CONSULTANT shall prepare Roadway, Drainage, Traffic Control, Utility
Adjustment Sheets, plan sheets, notes, and details. The plans shall include the
following sheets necessary to convey the intent and scope of the project for the
purposes of construction.
Plan content of the phase submittals will follow the general guidelines of Florida
Department of Transportation’s Phase II (60%), Phase III (90%), and Final
Submittals Plans Checklist as set forth in the FDOT Plans Preparation Manual.
5.1 Key Sheet
5.2 Summary of Pay Items
5.3 Drainage Map
5.4 Interchange Drainage Map (Not applicable to this project)
5.5 Typical Section Sheets
5.6 General Notes/Pay Item Notes
5.7 Summary of Quantities
5.8 Box Culvert Data Sheet (Not applicable to this project)
5.9 Bridge Hydraulics Recommendation Sheets (Not applicable to this
project)
5.10 Summary of Drainage Structures
5.11 Optional Pipe/Culvert Material
5.12 Project Layout
5.13 Plan/Profile Sheet (Not applicable to this project)
5.14 Profile Sheet
5.15 Plan Sheet
5.16 Special Profile (Not applicable to this project)
5.17 Back of Sidewalk Profile Sheet (Not applicable to this project)
5.18 Interchange Layout Sheet (Not applicable to this project)
5.19 Ramp Terminal Details (Plan View) (Not applicable to this project)
5.20 Intersection Layout Details
5.21 Miscellaneous Detail Sheets (Not applicable to this project)
5.22 Drainage Structure Sheet (Per Structure)
5.23 Miscellaneous Drainage Detail Sheets
5.24 Lateral Ditch Plan/Profile (Not applicable to this project)
5.25 Lateral Ditch Cross Sections (Not applicable to this project)
5.26 Retention/Detention Ponds Detail Sheet
5.27 Retention Pond Cross Sections
5.28 Cross-Section Pattern Sheet (Not applicable to this project)
5.29 Roadway Soil Survey Sheet
5.30 Cross Sections
5.31 Traffic Control Plan Sheets
5.32 Traffic Control Cross Section Sheets (Not applicable to this project)
5.33 Traffic Control Detail Sheets
5.34 Utility Adjustment Sheets
5.35 Selective Clearing and Grubbing (Not applicable to this project)
5.36 Erosion Control Plan
5.37 SWPPP
5.38 Project Control Network Sheet
5.39 Environmental Detail Sheets (Not applicable to this project)
5.40 Utility Verification Sheet (SUE Data)
5.41 Quality Assurance/Quality Control
5.42 Supervision
6 DRAINAGE ANALYSIS
The CONSULTANT shall analyze and document Drainage Tasks in accordance
with applicable manuals, guidelines, standards, handbooks, procedures, and
current design memorandums.
The CONSULTANT shall be responsible for designing a drainage and stormwater
management system. Design work shall comply with the requirements of the
appropriate regulatory agencies and the FDOT’s Drainage Manual.
The CONSULTANT shall develop a drainage map based upon available information
and field reviews. The available information should consist of old Florida
Department of Transportation