PHASE II SUBMITTAL:
The CONSULTANT shall submit to the COUNTY's Project Manager for
distribution:
two (2) copies of the Phase Submittal CD/DVD,
three (3) hard copies of the Plans,
three (3) hard copes of any Design Reports (Roadway, Drainage and
Geotech)
The Phase Submittal CD/DVD shall include *.PDF files of the components
listed above.
PHASE III SUBMITTAL:
The CONSULTANT shall submit to the COUNTY's Project Manager for
distribution:
two (2) copies of the Phase Submittal CD/DVD,
three (3) hard copies of the Plans,
three (3) hard copies of the Computation Book,
three (3) hard copies of the Construction Cost Estimate,
three (3) hard copes of any Design Reports Roadway, Drainage and
Geotech),
two (2) hard copies of the CONSULTANT's Contract Time Estimate,
one (1) hard copy of Phase II Submittal Comment Responses
The Phase Submittal CD/DVD shall include *.PDF files of the components
listed above.
FINAL SUBMITTAL:
The CONSULTANT shall submit to the COUNTY's Project Manager for
distribution:
two (2) copies of the Phase Submittal CD/DVD,
three (3) hard copies of the Plans,
three (3) hard copies of the Computation Book,
three (3) hard copies of the Construction Cost Estimate,
three (3) hard copes of any Design Reports Roadway, Drainage and
Geotech),
one (1) hard copy of Phase III Submittal Comment Responses,
one (1) hard copy of COUNTY Bid Documentation and Specification
Package
The Phase Submittal CD/DVD shall include *.PDF files of the components
listed above.
2.19 Provisions for Work
Maps, plans and designs are to be prepared with English values in
accordance with applicable current COUNTY manuals, memorandums,
guidelines including but not limited to:.
General
o 29 CFR, Part 1910.1101 – Asbestos Standard for Industry, U.S.
Occupational Safety and Health Administration (OSHA)
o 29 CFR, Part 1926, 1101 – Asbestos Standard for Construction,
OSHA
o 40 CFR, Part 61, Subpart M - National Emission Standard for
Hazardous Air Pollutants (NESHAP), Environmental Protection
Agency (EPA)
o 40 CFR, Part 763, Subpart E – Asbestos-Containing Materials in
Schools, EPA
o 40 CFR, Part 763, Subpart G – Asbestos Worker Protection, EPA
o Americans with Disabilities Act Accessibility Guidelines (ADAAG)
o Any special instructions from the COUNTY
o Bicycle Facilities Planning and Design Manual,
o CADD Manual
o CADD Production Criteria Handbook
o Ch. 469, F.S. – Asbestos Abatement, Florida COUNTY of Business
and Professional Regulation (DBPR)
o Ch. 62257, F.A.C. – Asbestos Program, Florida COUNTY of
Environmental Protection (DEP)
o Code of Federal Regulations
o Design Traffic Procedure
o Equivalent Single Axle Load Guidelines
o Florida Administrative Codes
o Florida Department of Business & Professional Regulations Rules
o Florida Department of Environmental Protection Rules
o Florida Department of Transportation Basis of Estimates Manual
o Florida Department of Transportation Design Standards for Design,
Construction, Maintenance, and Utility Operations on the State
Highway System
o Florida Department of Transportation Instructions for Structures
Related Design Standards
o Florida Department of Transportation Handbook for Preparation of
Specifications Package
o Florida Department of Transportation Materials Manual
o Florida Department of Transportation Plans Preparation Manual
o Florida Department of Transportation Project Development and
Environmental Manual
o Florida Department of Transportation Standard Specifications for
Road and Bridge Construction
o Florida Statutes
o Florida’s Level of Service Standards and Guidelines Manual for
Planning
o K-Factor Estimation Process
o Manual of Uniform Minimum Standards for Design, Construction, and
Maintenance for Streets and Highways
o Model Guide Specifications – Asbestos Abatement and Management
in Buildings, National Institute for Building Sciences (NIBS)
o Policy for Geometric Design of Highways and Streets
o Project Traffic Forecasting Guidelines
o Quality Assurance Guidelines
o Rule 61G17-6, F.A.C., Minimum Technical Standards for
Professional Surveyors and Mappers
o Safety Standards
o Utility Accommodations Guidelines
Permits
o Chapter 373, F.S.
o Bridge Permit Application Guide, COMDT PUB P16591.3B
o Building Permit
o 425-000-005 Asbestos Management Program
o 625-020-020 Asbestos on Bridges
Drainage
o Cross Drain
o Drainage Handbooks
o Drainage Manual
o Erosion and Sediment Control
o Hydrology
o Optional Pipe Materials
o Storm Drain
o Stormwater Management Facility
o Temporary Drainage Handbook
Survey and Mapping
o Applicable Florida Statutes and Administrative Codes
o Applicable Rules, Guidelines Codes and authorities of other
Municipal, County, State and Federal Agencies.
o FDOT Aerial Surveying Standards for Transportation Projects Topic
550-020-002
o FDOT Right of Way Mapping Handbook
o FDOT Surveying Procedure Topic 550-030-101
o Florida Department of Transportation Right of Way Procedures
Manual
o Florida Department of Transportation Surveying Handbook
o Right of Way Mapping Procedure 550-030-015
Traffic Operation Manuals
o AASHTO - An Information Guide for Highway Lighting
o AASHTO - Guide for Development of Bicycle Facilities
o American Disabilities Act
o Federal Highway Administration Manual on Uniform Traffic Control
Devices (MUTCD)
o Federal Highway Administration Standard Highway Signs Manual
o FHWA - Roundabouts: An Informational Guide
o Florida Department of Transportation - Florida Roundabout Guide
o Florida Department of Transportation Manual on Uniform Traffic
Studies (MUTS)
o Florida Department of Transportation Median Handbook
o Florida Department of Transportation Traffic Engineering Manual
o Minimum Specifications for Traffic Control Signal Devices
o National Electric Safety Code
o National Electrical Code
Geotechnical
o FHWA Checklist and Guidelines for Review of Geotechnical Reports
and Preliminary Specifications
o Manual of Florida Sampling and Testing Methods
o Soils and Foundation Handbook
These documents are revised periodically by the responsible agencies
and adopted by authorities having jurisdiction on building projects. The
design consultant and the project manager are advised to obtain
applicable versions of these documents from the responsible agency
prior to use.
o American Concrete Institute
o American Institute of Architects - Architect’s Handbook of
Professional Practice
o American Society for Testing and Materials - ASTM Standards
o Brick Institute of America
o DMS - Standards for Design of State Facilities
o Florida Building Code
o Florida Concrete Products Association
o Florida Department of Transportation - ADA/Accessibility Procedure
o Florida Department of Transportation - Asbestos Management
Program Procedure
o Florida Department of Transportation - Building Code Compliance
Procedure
o Florida Department of Transportation – Design Build Procurement
and Administration
o Florida Department of Transportation - Standard Specifications for
Road and Bridge Construction
o Florida Department of Transportation - Structures Manual
o Florida Department of Transportation - Design Standards
o National Concrete Masonry Association
o National Electrical Code (current edition)
o National Fire Protection Association - Life Safety Code (current
edition)
o Portland Cement Association - Concrete Masonry Handbook
2.20 Services to be Performed by the COUNTY
o When appropriate the COUNTY will provide project data currently on file.
o Provide numbers for field books.
o Regarding Environmental Permitting Services:
Approve contacts with environmental agencies.
Provide general philosophies and guidelines of the COUNTY to be
used in the fulfillment of this contract. Objectives, constraints,
budgetary limitations, and time constraints will be completely defined
by the Project Manager.
Provide the appropriate signatures on application forms.
o Provide letters of authorization designating the CONSULTANT as an
agent of the COUNTY in accordance with F.S. 327.274.
o Provide phase reviews of plans and engineering documents.
o Provide access for the CONSULTANT to utilize the COUNTY’s
Information Technology Resources.
o Furnish COUNTY agreements with Utility Agency Owner (UAO).
o Furnish certifications necessary for project letting.
o Provide information that may come to the COUNTY pertaining to future
improvements.
3 PROJECT COMMON and PROJECT GENERAL TASKS
Project Common Tasks
Project Common Tasks, as listed below, are work efforts that are applicable to
many project activities, 4.0 Roadway Analysis through 32.0 Noise Impact Design
Assessment. These tasks are to be included in the project scope in each applicable
activity when the described work is to be performed by the CONSULTANT.
Cost Estimates: The CONSULTANT shall be responsible for producing a
construction cost estimate and reviewing and updating the cost estimate when
scope changes occur and/or at milestones of the project. A Summary of Pay Items
sheet shall be prepared with required Phase III and Final Plans submittals.
Technical Special Provisions: (Not applicable to this project)
Field Reviews: Includes trips required to obtain necessary data for elements of the
project.
Technical Meetings: Includes meetings with COUNTY and/or Agency staff, between
disciplines and subconsultants, such as access management meetings, pavement
design meetings, local governments, railroad companies, progress review meetings
(phase review), and miscellaneous meetings. The CONSULTANT shall prepare,
and submit to the COUNTY’s Project Manager for review, the meeting minutes for
meetings attended by them. The meeting minutes are due within five (5) days of
attending the meeting.
Quality Assurance/Quality Control: It is the intention of the COUNTY that design
CONSULTANTS are held responsible for their work, including plans review.
Detailed checking of CONSULTANT plans or assisting in designing portions of the
project for the CONSULTANT is not the intent of having external design
consultants. The purpose of CONSULTANT plan reviews is to ensure that
CONSULTANT plans follow the plan preparation procedures outlined in the FDOT
Plans Preparation Manual, that state and federal design criteria are followed with
the COUNTY concept, and that the CONSULTANT