READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 17, 2015 — TO44-BLF--FDEPapprovedRAP-MOD — reading text
Part 2 of 2. These parts divide the reading text for browsing; they are not the source document's page numbers.
TO44-BLF--FDEPapprovedRAP-MOD — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
and results from the logging and pump testing activities, as well as a
final overview of newly identified capture zone and groundwater potentiometric maps.
Task 6 Estimated Fee: $11,300
Optional Task 7 — System Consiruction Oversight
SCS understands that the County will contract directly with Holt Well Services (Holt) to perform
various RAP MOD implementation tasks.SCS has included this optional task to provide
intermittent construction observation. Holt and/or the County will remove the above ground
infrastructure from RW-5, RW-6, and RW-7, which will include the removal of above ground
piping, fittings, and valves. Holt and/or the County also will remove the pumps and drop-down
pipes from the three recovery wells. Discharge pipelines will be abandoned in place by the
County by draining and capping them at the well and at the terminus of each pipeline. If
requested, SCS will observe and document these field activities.
SCS also will provide observation, where necessary, during cleaning of the existing piping,
installation of new piping and retrofitting clean-outs every 100 feet along existing piping and
newly installed piping. SCS also will provide observation of installing and connecting pumps to
the newly existing flow lines including the fittings, valves, meters, gauges, and related
equipment and fittings.
Task 7 Estimated Fee: $14,500
Optional Task 8 ~ System Stari-Up and Shakedown
SCS has included this optional task to assist the County in conducting system start-up and
shakedown activities. The objectives of the start-up and shakedown phase are to 1) confirm the
system has been constructed as planned; 2) confirm that the equipment is functioning and
operating as planned; 3) facilitate modifications to the system by Holt and/or the County, if
needed; and 4) gather and assess operational data.
This task will include bringing the new recovery well RW-10 online and assisting the County in
initiating the start-up of the system as a whole. During construction and prior to the start-up of
the system, three rounds of water level measurements will be conducted approximately one week
Mr. Scott Henson
March 13, 2012
Page 6
apart to confirm the ambient groundwater levels at the site, and assist with assessing capture
zones after initiating the system start-up. The system will be allowed to operate for a minimum
of 24-hours prior to collecting an additional round of water level measurements for comparison
to the initial water level measurements.
It is anticipated that the start-up and shakedown will require various support activities of SCS
which may or may not be anticipated. Consequently, this task includes six weeks of the services
of a project professional for 10 hours per week for unspecified support to the County as'the
system is brought up to operational status.
With the system not operating (after the RW-10 step test), SCS will have at least three rounds of
water level measurements performed by RDH at least one week apart of all recovery and
monitoring wells at the site and map the potentiometric surfaces of the upper and lower surficial
aquifer. This mapping will characterize the static potentiometric surfaces before the new system
is brought on line. If one of the three measurements is dramatically out of sync with the other
two, additional measurements will be performed one week apart until potentiometric surfaces are
effectively stable. This task assumes no more than six rounds of measurements will be
necessary.
As soon as the system is operational at the design rate of groundwater recovery at all planned
recovery wells, SCS will have RDH begin weekly rounds of water level measurements until
relatively stable dynamic potentiometric surfaces are present. This task assumes this will require
four weekly measurements. Following these measurements, water level frequency then be
changed to monthly for one quarter. This will complete the data collection for this task. Further
water level measurements will be part of the routine RAPMOD measurements frequency.
This task will be complete upon completion of services described above and completion of the
mapping of the operational potentiometric systems, including delineating the extent of the
capture zones on the potentiometric maps.
Task 8 Estimated Fee: $13,800
FEE ESTIMATE
SCS will complete the scope of work for the estimated fees below:
Task 1 — $4,800
Task 2 —$4,100
Task 3 - $2,700
Task 4 — $6,500
Task 5—$21,500
Task 6 - $11,300
Task 7 — $14,500 - OPTIONAL
Task 8 — $13,800 - OPTIONAL
Mr. Scott Henson
March 13, 2012
Page 7
The total estimated fee to complete the proposed scope of services (not including the optional
tasks) is $50,900. However, the scope may be modified by the County to include the optional
tasks or other services. Actual fees will be dependent on time and expenses necessary to fulfill
the scope of services and will not exceed the estimated fee without the prior approval and
authorization of the County. Should additional services be necessary beyond those described
above, SCS will provide an amendment to this proposal for approval prior to proceeding with the
additional services. -
TERMS AND CONDITIONS
These services will be completed according the current terms and conditions of our existing
agreement with Okaloosa County. These services will be invoiced monthly on a time and
materials basis.
AUTHORIZATION
If the scope of services, schedule, and associated budget are acceptable, please provide your
authorization to proceed by signing and returning the attached task order authorization. SCS
appreciates the opportunity to provide environmental consulting services to Okaloosa County.
Should you have any questions or require additional information, please contact Mr. Bob Westly
at 850-432-6211.
Sincerely,
Robert L. Westly, P.G., CPG
Project Director / Sr. Hydrogeologist Vice President
SCS ENGINEERS SCS ENGINEERS
RLW/KMT: nch
ATTACHMENT A - MANPOWER AND FEE ESTIMATE - PROPOSAL # 090002212 - March 2012, REV 2
OKALOOSA COUNTY - BAKER LANDFILL RAP MOD IMPLEMENTATION, FY 2012
Tasks (Hours) Total Rate Total
Personnel 1 2 3 4 5 G 7 8 9 10 14 12 (hours) | (8} {5}
Office Director/Advisor [ 185 90
Project Director (Bob Westly) 2 2 16 12 10 12 64 195 12,480
Senior Project Engineer (Bruce Clark) i 2 3 195 585!
Project Manager (Nic Howard) 12 4 4 2 24 20 20 20 106 125 13,250
Senior Project Geologist 0 108 [
Project Engineer/Geologist 0 97 [1]
Staff Engineer/Geologist (John Cooey)} 8 24 12 8 40 50 100 36, 278 95 26,410
Site/O&M Superintendent 0 86 0
Designer 0 97 0
Draftsperson (Kim Knapp) 8 16 24 72 1,728
Technician 0 74 0
0 155 0
9 195 0
[Secretarial/Clerical {Marie Bores) 4 2 4 2 2 10 2 2 28 60 1,680:
Subtotal Labor (hours) 36 31 28 14 82 108 134 70 0 [ 0 Q 503
Subtotal Labor ($) 4,840 3,095 2,456 1,520 10,0407 11,342| 14,460 8,380 0 Q 0 0 503 56,133
Reimbursables 0 975 200 5,000) (1,450 0 0 5,400 0 0 0 Q | $23,025.
[Contingency o 0 0 0 0 0 0 0 0
Total Fee Estimate $4,800| $4,100 $2,700 $6,500) $21,500]| $11,300] $14,500{ $13,800 50 30 50 $0 579,200
Notes:
Task 1-FY2012 Logistics, Corresponence & Management
Task 2 - FY2012 Health & Safety Plan
Task 3 - FY2012 Permitting
Tesk 4 - FY2012 Site Survey
Task 5 - FY2012 Installation of Recovery Well-10
Task 6 - FY2012 Reporting
Task 7-FY2012 System Construction Oversight - OPTIONAL
Task § - FY2012 System Start-Up & Shakedown - OPTIONAL
REIMBURSABLE COSTS Page 2
Unit Cost Task (Quantity) Total Total
Reimbursable (5) Unit 1 2 3 4 5 6 7 8 9 10 11 12 Units (%)
RDH 1} I [ 0 0 ¢ 0 0 0 4,800, 9 0 9 Y 4,800 4,800
Drifling (Holt} 1 Is Q 0 0 Q] 10,000 Q 0 0 0 0 0 Q 10,000 10,000]
Surveying 1 I [1 )] 0 5,000 ¢ [ 0 0 0 0 0 o 5,000 5,000
GEM 2000 Plus . 1/ I ] 875 0 19 o ) 0 0 0 0 9 0 875 875
iEguipment /Instrumentation 1} I ] Q 0 0 1,250! 0 0 500. 9 0 1] (] 1,750 1,750
Supplies 1) each [ 100 Q 0 200 0 0 100} 0 0 0 [ 400 400
{Permits 1| T&M ¢ 4 200 0 0 0 0 0, [ 0 0 2 200 200
1| T&M O Q 0 0. 0 0 0 0 [ 0 0 [ 0 0|
ZAPROPOSALIZDI 296002212 - Okaloos RAP Mod lnstedi\Fina! Proposal Docs\{ProposslFaeEst REV 2_Mer 12_FINAL xsBaker LF RAP MOD Inipl
Scoitt Henson
From: Jack Alien _
Sent: Wednesday, March 28, 2012 12:40 PM
To: Scott Henson
Cc: Kathy Carroli; Richard Brannon
Subject: RE: AgendaltemBLFSCSRAPMod.pdf - Adobe Acrobat Standard
From: Scott Henson
Sent: Wednesday, March 28, 2012 1:31 PM
To: Jack Allen
Cc: Kathy Carroli
Subject: AgendaltemBLFSCSRAPMod.pdf - Adobe Acrobat Standard
Attached is a proposal from SCS for Baker Landfill Work. I believe we are on TO 44 but you will need to verify that for
me. Total TO cost for the proposed work is $79,200 against account number 4301-549304. As you can see | am
shooting for the April 17" Board meeting. | have the Task Order Approval with original signatures page that I will give to
Kathy for Johns review/approval once you guys give me the thumbs up— unless you want to see the original signatures
NOow.
Please note: Due to Florida’s very broad public records laws, most written communications to or from County employees regarding County business are
public records, available to the public and media upon request. Therefore, this e-mail communication, including your email address, may be subject to public
disciosure and public record retention requirements.
T
OFFICE OF CONTRACTS & GRANTS
CLERK OF THE CIRCUIT COURT
1804 Lewis Turner Blvd, Suite 206
(850) 651-7200, ext 4381
AR A5OSR
MEMORANDUM
R S ARSI o
TO: Jack Allen,
Purchasing Manager
FROM: Brenda L. Bailey,
7 Contracts & Grants Manager
DATE: May 2, 2012
RE: BCC Meeting Date: April 17,2012
The Okaloosa County Board of Commissioners has approved the attached
document(s) on the date specified above. The documents are being returned for
the following action:
D Please submit to other party for signatures. When fully executed
please return one “original” to our office.
)X{ If document is fully executed, please make final distribution including
returning one original to our office.