READ ALONGSIDE THE SOURCE
Okaloosa County School Board — Regular Meeting, July 8, 2024 — reading text
Part 8 of 9. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — D5HM7F594317.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Purchase (ODP) - Trane Equipment, in
the amount of $604,287.00.
Public Content
Approval is requested for TPM Program #6, Task Order #37, GMP Sales Tax HVAC Projects at Fort Walton Beach High School and Mary
Esther Elementary School.
Scope of Work:
Mary Esther Elementary School HVAC Project – This project consists of the installation of new roof-top mounted HVAC systems at
each classroom in the Main Building. New electrical service and an FPL transformer will be added to the school and the new electrical
panels and associated wiring will terminate in the existing Boiler Room. New HVAC units will also be installed to provide conditioned air
to the existing main hallways in the school. At the completion of the project the existing two-pipe HVAC equipment that currently feeds
each classroom will be removed and the piping abandoned in place.
Fort Walton Beach High School HVAC Project – This project consists of the demolition and replacement of the existing Cooling
Towers at the school as well as associated Central Plant upgrades and new controls.
The Total Cost of Work for Task Order #37 is recapped below:
Jacobs/Titan Guaranteed Maximum Price (GMP) $3,510,165.00
Pre-GMP Phase Services - Previously Authorized $400,000.00
Owner Direct Purchase (ODP) - Trane Equipment Allowance $604,287.00
Total Cost of Work $4,514,452.00
Please contact Dr. Bill Smith for additional information, 689-7158.
File Attachments
TO37 GMP Mary Esther & FWBHS HVAC Projects.pdf (216 KB)
TO37 GMP Comparison Spreadsheet.pdf (33 KB)
Motion & Voting
Motion to approve TPM Program #6,
Task Order #37, GMP Sales Tax
HVAC Projects at Fort Walton Beach
High School and Mary Esther
Elementary School, in the amount of
$3,510,165.00 and Owner Direct
Purchase (ODP) - Trane Equipment, in
the amount of $604,287.00.
Motion by Marti Gardner, second by
Tim Bryant.
Final Resolution: Motion Carries
Yes: Tim Bryant, Linda Evanchyk,
Marti Gardner, Lamar White
10. Construction Program/Owner's Representative's Business
Subject : 10.3 TPM Program #6, Task Order
#24, Scope Modification #4, GMP
Central Administration Phase 2
Renovation Project, presented by Dr.
Bill Smith, Facilities Planning, and
recommended by the Superintendent
for approval.
Meeting : Jul 8, 2024 - Regular Meeting
Type : Action
Preferred Date : Jul 08, 2024
Absolute Date : Jul 08, 2024
Dollar Amount : $4,839,191.00
Budget Source : Capital Funds - 1.50 Mill
Recommended Action : Motion to approve TPM Program #6,
Task Order #24, Scope Modification
#4, GMP Central Administration
Phase 2 Renovation Project, in the
amount of $4,695,179.00 and
Furniture, Fixtures & Equipment
(FF&E), in the amount of
$144,012.00.
Public Content
Approval is requested for TPM Program #6, Task Order #24, Scope Modification #4, GMP Central Administration Phase 2 Renovation
Project.
Scope of Work: This project consists of the demolition and reconfiguration of a portion of the existing OCSD Central Administration
Complex into useable office space for District staff. Work will include the installation of new walls and ceilings and selected floor finishes,
as well as required HVAC, Electrical, Plumbing, Fire Alarm, Security, Audio Visual, Data and Communication Systems. New Trane Roof
Top Mounted HVAC units will be provided by OCSD as Owner Furnished, Contractor Installed Equipment in Phase 2.
The Total Cost of Work for Task Order #24, Scope Modification #4 is recapped below:
Jacobs/Titan Guaranteed Maximum Price (GMP) $4,695,179.00
Furniture, Fixtures & Equipment (FF&E) $144,012.00
Total Cost of Work $4,839,191.00
Please contact Dr. Bill Smith for additional information, 689-7158.
File Attachments
TO24 GMP Phase 2 Central Admin Renovation.pdf (221 KB)
TO24 SM4 Comp Sheet.pdf (33 KB)
Motion & Voting
Motion to approve TPM Program #6,
Task Order #24, Scope Modification
#4, GMP Central Administration
Phase 2 Renovation Project, in the
amount of $4,695,179.00 and
Furniture, Fixtures & Equipment
(FF&E), in the amount of
$144,012.00.
Motion by Linda Evanchyk, second by
Tim Bryant.
Final Resolution: Motion Carries
Yes: Tim Bryant, Linda Evanchyk,
Marti Gardner, Lamar White
10. Construction Program/Owner's Representative's Business
Subject : 10.4 TPM Program #6, Task Order
#33, GMP Softball Concessions/Press
Box Projects at Fort Walton Beach
High School and Crestview High
School, presented by Dr. Bill Smith,
Program Director, Facilities Planning,
and recommended by the
Superintendent for approval.
Meeting : Jul 8, 2024 - Regular Meeting
Type : Action
Preferred Date : Jul 08, 2024
Absolute Date : Jul 08, 2024
Dollar Amount : $1,361,739.00
Budget Source : Capital Funds - 1.50 Mill
Recommended Action : Motion to approve TPM Program #6,
Task Order #33, GMP Softball
Concessions/Press Box Projects at
Fort Walton Beach High School and
Crestview High School, in the amount
of $1,311,739.00 and Furniture,
Fixtures & Equipment (FF&E), in the
amount of $50,000.00.
Public Content
Approval is requested for TPM Program #6, Task Order #33, GMP Softball Concessions/Press Box Projects at Fort Walton Beach High
School and Crestview High School.
Scope of Work:
Ft. Walton Beach High School Softball Concession/Press Box Project – This project consists of the construction of a two-story
Concessions/Press Box building at the Softball field. The structure measures 10’ x 16”. Concessions will be located on the ground floor
and service will be through a window with roll-up shutter. The Press Box will be on the second floor accessed via an exterior stairwell.
The Press Box is equipped with large operable windows facing the Softball field. The Concession area is equipped with a three
compartment sink, hand wash sink and a mop sink as well as cabinets and countertops for storage and service.
Crestview High School Softball Concession/Press Box Project – This project consists of the construction of a two-story
Concessions/Press Box building at the Softball field. The structure measures 10’ x 16”. Concessions will be located on the ground floor
and service will be through a window with roll-up shutter. The Press Box will be on the second floor accessed via an exterior stairwell.
The Press Box is equipped with large operable windows facing the Softball field. The Concession area is equipped with a three
compartment sink, hand wash sink and a mop sink as well as cabinets and countertops for storage and service.
The Total Cost of Work for Task Order #33 is recapped below:
Jacobs/Titan Guaranteed Maximum Price (GMP) $1,311,739.00
Portion of Pre-GMP Phase Services - Previously Authorized $74,842.00
Furniture, Fixtures & Equipment (FF&E) $50,000.00
Total Cost of Work $1,436,581.00
Please contact Dr. Bill Smith for additional information, 689-7158.
File Attachments
TO33 GMP Softball Pressbox Concession Projects.pdf (195 KB)
TO33 GMP Comp Sheet.pdf (33 KB)
Motion & Voting
Motion to approve TPM Program #6,
Task Order #33, GMP Softball
Concessions/Press Box Projects at
Fort Walton Beach High School and
Crestview High School, in the amount
of $1,311,739.00 and Furniture,
Fixtures & Equipment (FF&E), in the
amount of $50,000.00.
Motion by Tim Bryant, second by
Marti Gardner.
Final Resolution: Motion Carries
Yes: Tim Bryant, Linda Evanchyk,
Marti Gardner, Lamar White
10. Construction Program/Owner's Representative's Business
Subject : 10.5 TPM Program #6, Task Order
#34, GMP Sales Tax Projects at Meigs
Middle School and Destin Middle
School, presented by Dr. Bill Smith,
Program Director, Facilities Planning,
and recommended by the
Superintendent for approval.
Meeting : Jul 8, 2024 - Regular Meeting
Type : Action
Preferred Date : Jul 08, 2024
Absolute Date : Jul 08, 2024
Dollar Amount : $4,144,705.00
Budget Source : 3911- Other Capital - Capital Sales
Tax
Recommended Action : Motion to approve TPM Program #6,
Task Order #34, GMP Sales Tax
Projects at Meigs Middle School and
Destin Middle School, in the amount
of $3,361,137.00 and Furniture,
Fixtures & Equipment (FF&E), in the
amount of $783,568.00.
Public Content
Approval is requested for TPM Program #6, Task Order #34, GMP Sales Tax Projects at Meigs Middle School and Destin Middle School.
Scope of Work:
Meigs Middle School Sales Tax Projects – This project consists of minor renovation to the existing Gym which entails new bleachers,
lighting, ceilings and acoustical treatments. Work in the existing Locker Rooms will convert some shower areas to Storage and Custodial
Rooms. Also included is a conversion of the old Front Office building into gang restrooms, a Clinic, offices and a Teachers Lounge.
Finally, a new shade structure will be installed in the courtyard to provide a covered dining area outside the