BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: March 4, 2014
TO: Honorable Chairman and Members of the Board
FROM: Jeff Littrell
SUBJECT: Insituform Technologies Change Order #1
DEPARTMENT: Water and Sewer
BCC DISTRICT: All
STATEMENT OF ISSUE: Approve Change Order #1 to add additional scope of work for the
rehabilitation of gravity sewer (Phase II of maintenance contract).
BACKGROUND: An annual maintenance contract with a two year initial contract period for
the rehabilitation of gravity sanitary sewer was awarded on April 17, 2012. The initial phase was
completed in 2012-2013 and consisted of relining over 7,000 feet of main trunk line sewer and
11 point repairs on Okaloosa Island (predominantly, the remaining main sewer line that runs the
length of Santa Rosa Blvd). The lines that were repaired are the original sewer lines installed by
the former Okaloosa Island Authority in the 1960s and are constructed of terra cotta pipe in 4’
sections. Most of the joints in these sewer lines were found to be leaking groundwater into the
sewer system during an inspection program several years ago. The repair of the lines has cut
down on the amount of groundwater being unnecessarily treated at the Arbennie Pritchett Water
Reclamation Facility (conserving capacity) and will prevent future potential subsidence of the
ground surrounding the leaking lines. OCWS staff is satisfied with the quality of work
performed on the original phase and is ready to add to the contract, to facilitate the rehab of more
gravity sewer.
The next phase (Change Order #1) will consist of pre-rehabilitation cleaning and CCTV
inspection of an additional 45,000+ LF of gravity sewer previously identified as problematic,
primarily on the Island and in the Ocean City/Wright areas. In addition, two heavily corroded
cast iron pipe lines (one under Eglin Parkway in Shalimar) will be cleaned with specialty
equipment, then relined in this phase.
The original contract was awarded to Insituform Technologies LLC in the amount of $288,383.
This change order will add $193,820.00 to the original contract, for a revised contract total of
$482,203. The Change Order Form and project breakdown spreadsheet are attached for your
review. No change in contract time is needed for this change order. Although this is called a
"change order", no changes are being made to the contract terms and conditions, time, or unit
prices; this change order simply adds scope/quantities, as was originally intended to be Phase II.
OPTIONS: Approve or deny.
RECOMMENDATION: OCWS requests BCC approval to authorize the Chairman to execute
Change Order #1 to Contract # C12-1955-WS with Insituform Technologies LLC, adding
$193,820.00 in scope of work for the rehabilitation of gravity sewer (Phase II of maintenance
contract).
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator