10. 91 million and we had various draws off that for Underwriter discount, bond
insurance, and we had to create a reserve account and there was $ 724, 000. 00 set aside for that, which
left us with a remaining balance of $9. 8155 million for the capital improvements to the water and
sewer system. We also developed early on a probably opinion of cost for the various elements
identified in the bond project listing. We estimated our projects, again, in February of 05' prior to
going into the bond market, essentially knocking the dust off prior estimates we had for those projects.
At the time we estimated for the elevated storage tank improvement roughly $ 1. 8 million including the
cost of construction and contingency. For the 18" transmission main we identified another $ 1.8
million including contingencies for the installation of that three miles of transmission main. We also
lumped into the water side of the projects CIP 50- 56 which is one of our on- going Capital
Improvement Projects for the replacement of 2 y,." water lines with larger diameter, and thus more
capacity, 6" water lines. So we set aside $ 225, 000.00 in there for those projects. On the wastewater
side of the house, at the time back in February of 05' we felt like, given the level of renovation we
were going to have to do at the plant, we were looking at roughly $ 3. 835 million for wastewater plant
improvements with contingencies factored in for about $ 1.3 million. We also, at the time, lumped in
CIP 50- 32, which is our on- going sewer system rehabilitation project. Each year we take various
segments of our sanitary sewer system, some segments we line in place simply because its cost
prohibitive to dig the line up and replace it plus the impact to private properties is such that it' s more
efficient to go into that sewer line and line it in place and not have to dig it up. So we do some of that
work. We do some actual point repairs where if we have areas where we can dig the line up and
replace it and do it cheaper than lining it in place we will do that. We also do some root control
treatment for our sanitary, our gravity sewer lines; the roots can get into that system, cause quite a bit
of blockage, further damage, so we' ll treat segments of the line with a chemical to kill the roots off.
We lumped all of those projects into this bond issuance as well to the tune of $800, 000. 00. So the
total, as you' ll see, for all projects $ 9, 815, 500. 00. Then we started bidding projects, and this was post
Ivan, post Dennis, post Katrina in some regards, and the cost of construction was heavily escalated
over what we were looking at in the Spring of 05'. And I have a slide later where I'll get to the
particular variables that we identified that lead to cost increases in some of our major capital
improvements. But I wanted to include where we are currently and this slide kind of breaks that down.
The elevated water tanks projects that we initially estimated at $ 1. 815 million, when we actually
opened bids on that it was $ 1.969 million that was the low bid for the project. We have since
completed that project at a cost of $1 million 952 thousand and some change for a savings over the bid
award amount of $137, 000. Excuse me
Mayor - it cost you more than you budgeted.
John Hofstad - I've actually broke it down further on in another slide. I just wanted to give you a
quick look at some of the projects of what we had, where the bid cost came in, and again I'll explain
where we are as far as what has caused some of the escalation of some of these construction projects.
One of the first projects
we out on the street was the wastewater treatment plant renovation project.
put
We brought that before Council in June of 05' and we awarded services to Brown and Caldwell in an
amount not to exceed $ 840, 000. 00. We successfully negotiated that project with Brown and Caldwell
at $ 769, 000. 00.
Page 2 of 11
COUNCIL WORKSHOP 6- 12- 07
John Hofstad - The project status, we expect 100% design plans in hand any day with revised cost
estimates. And, again, we' ve made this comment to you before in the past, but we cannot begin
construction until we' ve resolved all the issues relative to our wastewater treatment plant operating
permit which is currently being held by DEP until we review the issue with an Administrative Law
Judge. The new elevated water storage tanks, in June of 05' we brought before Council a bid award
for construction of two new elevated water storage tanks. That project was awarded to Chicago Bridge
and Iron in the amount of $1, 969, 800. 00. Project status, we' ve completed that projects, excuse me,
both of the elevated water storage tanks, we completed that in August of 06' at a cost of $1, 952, 644. 00
so we actually enjoyed a contract under run in that project of$ 17, 156. 00 so we actually had a savings
over what the bid award amount was and we were able to reduce some of the steel needed for the
project because of Florida wind loading requirements and enjoyed a bit of a cost savings for that
project over what was awarded. The 18" water transmission main project, we brought that to Council
in April of 06', Council approved the award of that effort to Hemphill Construction in the amount of
2, 723, 645. 00. That far exceeded our estimates in February of OS' for that particular project. The
current status is we completed construction of the water transmission main in May of 01', we' re
currently awaiting as- builts and final quantities from Fabre Engineering, who is our consulting
engineer for the project and once we receive that information we will approve the fmal invoicing and
we can, as soon as we get our certification of completion from DEP we can place that line in service,
so we expect that to take place some time here in the next two weeks, two to four weeks. We do have,
based on what we' ve seen from the final invoicing submitted by the contractor, again it's not yet been
approved by our consulting engineers but we' re seeing a potential savings there of $100, 000. 00 and
maybe a little more. So actually we' re having a, we' re seeing a pretty good savings with the project
vs. what was originally awarded by Council.
Mayor - excuse me John, Mr. Hofstad, but both these projects costing more than we originally
budgeted though.
John Hofstad - right
Mayor - granted they' re under the bid price but they' re still more expensive than we budgeted.
John Hofstad - absolutely and again, there is several variables that come into place since the time that
we originally estimated; in a couple of slides I'll address those issues.
Mayor - OK, thank you.
John Hofstad - one of the projects that came up after we had gone to bond market and started our bond
projects was the Cinco Bayou force main. Previous to September 06' we had a sub(?) force main, a
force main that laid on the bottom of Cinco Bayou, in the vicinity of Cinco Bayou bridge. During both
of our most recent hurricanes, Ivan and Dennis, we had some damage to that force main and we
actually lost raw sewage in Cinco Bayou as a result. That force main had been on the bottom of the
bayou for some forty years. We had concerns of the reliability of that line to the point we made
permitting application to DEP to replace it with an aerial line under Cinco Bayou Bridge and received
approval from DEP to do that project. So in May of 06' we brought forward to you a bid award to
Hemphill Construction in the amount of $254,000.00 to relocate that force main underneath the bridge.
Page 3 of 11
COUNCIL WORKSHOP 6- 12- 07
John Hofstad - This project was not originally programmed in the Series 2005 Bond projects but it
does fall into that CIP that I referenced earlier, the sewer main rehabilitation project and we saw an
immediate need, an immediate impact, environmental impact by relocating this line. We completed
the construction in September of 06' at a final cost of $259, 950.00. We had a slight overrun of that
project of $3, 800.00 which was within the approval authority of the City Manager, and that was due to
some alignment problems on the western bridge approach, the line that was actually plum through the
bridge abutment had some problems when we pressure tested it and wouldn' t hold pressure. So we
had to actually route around the bridge so that increased the cost slightly. We also had the demolition
of two elevated storage tanks. Now we knew all along we were going to have to demolish two storage
tanks but early in 05' and late 04' when we were calling the various vendors that perform that type of
work there actually was an after market for used steel tanks in rural areas to the point where there was
no anticipated cost for their removal. The contractor would come in remove them and he would
remove them for the resale value. That market disappeared later in the year and there was a cost to
remove them. Now there is some salvage value in steel so actually to remove those things it's quite an
effort and when we originally bid it our low bid was $ 64,700.00 but actually we were able to complete
that project for $20,000.00 less, $ 44, 700. 00 and that was due to the City taking on some of the below
ground, below grade work instead of placing that on to the contractor because that was something that
we could perform in-house but we can' t do aerial demolition. So we did enjoy a bit of a savings on
that but again that was not a programmed cost because there was a market at one time for those tanks.
The on- going in-house Capital Improvement Programs, I touched on this earlier but I just wanted to
kind of give you an overview of what we' ve done to date. Again, for the CIP 50- 32 which is the sewer
system rehabilitation, the Cinco Bayou force main relocation cost us roughly $258, 000. 00. In addition
to that we' ve done $ 310, 000 a little over, in cured and placed pipe rehabilitation to the tune of
24,000. 00 linear feet of 8" to 15" gravity sewer main. So we' ve lined a few miles there of actual
sanitary sewer line. We' ve also done roughly, completed roughly $ 28, 830. 00 in chemical root
treatment for over 19, 000 linear feet of 6" and 8" gravity sewer main. On the water side, CIP 50- 56
our total expenditure since the inception of the program is around $ 142, 000. 00 of that we' ve replaced
4, 800 linear feet of 2 W' water pipe with 6" water pipe. Our cost for us to do that work and all total to
install that are manpower, our materials cost, our restoration are somewhere around $ 30 per linear foot.
And that number will be, there will be some significance to that number in the next slide when I
discuss some of the cost overruns in these projects. What we' re all getting to here, the reasons for the
construction cost increases. First and foremost is the instability in the petroleum market. The
petroleum industry drives the cost of piping materials and as the cost of a barrel of oil creeps up so
does the cost of our supplies. I could not tell you next week what the cost of PVC is going to be
because it changes that frequently. In August of 05' 8" PVC pipe, we could install that or a contractor
if we were to contract that out, would install that for us at roughly $ 22 a linear foot and for an 8" (?)
pipe $ 28 a linear foot; April of 06', not even a year later, the same installation for 8" PVC increased to
50 a linear foot and 8" (?) pipe increase to $ 66 a linear foot. So what I'm telling you is the projects
we do in-house there is a significant savings, we just don' t the capability for these large scale projects
doing that type of work. The Fort Walton Beach location is really not favorable for m~ or